Detroit Edison Co. v. Public Service Commission

417 Mich. 1133
CourtMichigan Supreme Court
DecidedMay 25, 1983
DocketDocket Nos. 61294, 61295
StatusPublished

This text of 417 Mich. 1133 (Detroit Edison Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Edison Co. v. Public Service Commission, 417 Mich. 1133 (Mich. 1983).

Opinion

Rehearing denied. Reported at 416 Mich 510.

Boyle, J., not participating. Kavanagh, J., would grant rehearing. Levin, J., would grant the motion for rehearing and says:

Detroit Edison has filed a motion for rehearing of this Court’s December, 1982, decision sustaining an appropriation of $23,500,000 of Detroit Edison’s capital. The motion should be granted and the case once again set down for plenary hearing and decision.

On December 22, 1975, the Michigan Public Service Commission entered an order requiring Detroit Edison to write off accumulated deferred fuel costs of approximately $26,350,000 against net income over a period of ten years. The circuit court reversed, and Detroit Edison was authorized to collect the deferred fuel costs from its customers over a 12-month period; Detroit Edison actually collected approximately $23,500,000.

In March, 1978, the Court of Appeals reversed the circuit court. In December 1982, the Court of Appeals was affirmed by an equal [1134]*1134division in this Court. Chief Justice Fitzgerald’s opinion for affirmance was signed by Justices Williams and Ryan. I wrote for reversal and Justices Kavanagh and Coleman signed that opinion. The Detroit Edison Co v Public Service Comm, 416 Mich 510 (1982).

I

On February 4, 1974, the commission authorized Detroit Edison to add a fuel adjustment clause for domestic service, the adjustment to apply to the second billing month following the calendar month in which the fuel is burned.1 On July 29, 1974, Detroit Edison was authorized to set up on its balance sheet as an asset the "fuel expense” to be collected two months hence.2 On February 3, 1975, the commission revised the fuel adjustment clause to eliminate the two-month lag, and Detroit Edison was directed to file an application with the commission for a determination of the disposition of the accumulated fuel cost deferral.3

[1135]*1135Detroit Edison filed such an application. A hearing referee found that Detroit Edison had "experienced an increase in the cost of fuel consumed [during a part of December, 1974 and January, 1975] which [1136]*1136exceeded by $26,349,806 the existing respective base points for fuel cost adjustment calculations, and which under the then existing procedures, would have been recoverable from and billed to customers in February and March 1975”, and that said sum is reflected by Detroit Edison in the account in which deferred fuel costs were required to be set forth by the July 29, 1974, order. The hearing referee further found that the February 3,1975, order had established a new fuel adjustment clause "that substantially eliminated the previous 'billing lag’ for fuel costs occurring after February 3, 1975, thereby vitiating the need for future accumulations of deferred fuel costs”. The hearing referee further stated:

"There is nothing in the record to support a finding that the cost of fuel should be written off against net income, and the staff’s position is asserted without any probative evidence to justify altering the premise that the applicant’s customers should pay for the cost of fuel incurred on their behalf. On the other hand, the evidence submitted by the applicant persuasively establishes that if applicant is not permitted to recover the deferred fuel costs from its customers, then the applicant must, in effect, write off an asset account of $26,349,806 against its common equity.”

The hearing referee recommended that the accumulated deferred fuel costs be billed to customers over a 12-month period.

On December 22, 1975, the commission rejected his recommendation and ordered the write-off over a ten-year period of the $26,350,-000 accumulated fuel cost deferral. The commission acknowledged that "during part of December 1974 and part of January 1975” Detroit Edison had experienced "an increase in costs of fuel consumed” and that, during that period, its "actual fuel costs exceeded the amount it was able to recover under the fuel cost adjustment clause which existed at that time by $26,349,806”.4

[1137]*1137n

Although appellees assert that Detroit Edison has recovered the deferred fuel costs, it clearly appears from the findings of the. hearing referee and the orders of the commission and it is implicit in the analysis of the opinion for affirmance in this Court that Detroit Edison did not, before the circuit court order authorizing it to do so was entered, recover the $23,500,000 from its customers.

The opinion for affirmance states that the fuel clause "was not designed to recover all past costs, but was intended only to estimate current costs on the basis of past experience”. Detroit Edison Co v Public Service Comm, supra, p 515. (Emphasis supplied.)

The opinion for affirmance begins by stating the first issue posed in this Court’s order granting leave to appeal but does not address another issue posed in that order: "If the utility is not allowed the proposed surcharge, would confiscation result?” 403 Mich 853 (1978).

A fuel clause "not designed to recover all past costs”, which, in a period of rising costs, "inherently”5 must fail to do so, does not constitute an appropriate exercise of the power confided to the commission. The commission failed to justify the "designing” of a fuel clause which "inherently” requires Edison to absorb and charge its stockholders, rather than its customers, for $23,500,000 of actual fuel costs.

In allowing Detroit Edison to set up as an asset on its books accumulated deferred fuel costs of $26,350,000, the commission, in effect, represented that the amount was a true asset, and not a "paper asset” as the Court of Appeals6 incorrectly characterized it. Surely the commission does not authorize public utilities to "display”7 "paper assets”. To do so would be to mislead stockholders, investors, and the public.

The opinion for affirmance states that three features of the fuel clause demonstrate that the fuel clause was intended only to "estimate” current costs on the basis of past experience. Detroit Edison asserts in its motion for rehearing that those features are generally characteristic of utility rates, billing, and collection. Detroit Edison states that there cannot be an exact match between the month of expenditure and the month of billing. Meters are read every other [1138]*1138month, necessitating an estimate of actual usage for each month of the two-month period. Meters are read on 20 different days in each month for a total of 40 different days. The meter of only 1 customer in 20 is read on the first day of the month. It is not practical, because of the small amounts involved, to bill former customers. Detroit Edison explains further that the fuel clause did not become effective until after the test year used in the prior rate case.

It appears that utility rates and fuel clauses inevitably incorporate estimates made on the basis of past experience.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Detroit Edison Co. v. Public Service Commission
331 N.W.2d 159 (Michigan Supreme Court, 1982)
Detroit Edison Co. v. Public Service Commission
266 N.W.2d 665 (Michigan Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
417 Mich. 1133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-edison-co-v-public-service-commission-mich-1983.