OPINION

Justice SUTTELL, for the Court.

The plaintiff, DeSimone Electric, Inc., appeals from a Superior Court judgment denying its petition to enforce a mechanic’s lien and awarding the defendants, CMG, Inc., Ashford Homes, LLC, and James Colucci, damages on their counterclaims for breach of contract and negligence. The plaintiff contends that the trial justice erred in finding the mechanics’ hen statute, G.L.1956 chapter 28 of title 34, unconstitutional and in denying its petition to enforce. The plaintiff also avers that the trial justice was clearly wrong and overlooked or misconceived evidence in her findings concerning the defendants’ counterclaims.

This case came before the Supreme Court for oral argument pursuant to an order directing the parties to show cause why the issues raised in this appeal should not be decided summarily. After considering the written and oral submissions of the parties and examining the record, we are of the opinion that the issues raised in this appeal may be resolved without further briefing or argument. For the reasons set forth herein, we affirm the judgment of the Superior Court.

Facts and Procedural History

The present dispute arose over two contracts between plaintiff and defendants. One of the contracts was created when James Colucci, in his capacity as president of CMG, Inc., hired plaintiff, DeSimone Electric, Inc., an electrical contractor, to do work on eight lots at City View Highlands Estates in Johnston, Rhode Island (the City View project). The parties orally agreed that plaintiff would complete the “basic” or “rough” wiring at each lot for a fixed price of $2,750 per lot. 1 To receive payment for the work it did on the City *616 View project, plaintiff would submit an invoice upon completion of the rough phase of the electrical work, and CMG-Ashford 2 would pay, usually within a week or two. The owner of DeSimone Electric, Alberto DeSimone, testified that CMG-Ashford never exceeded two or three months on a payment.

The plaintiff began work on the City View project at the end of 2000 and discontinued labor on July 17, 2001. Mr. DeSi-mone testified that CMG-Ashford owes the plaintiff corporation $4,795 for work done on five of the eight lots. Mr. DeSi-mone admitted that the plaintiff corporation did not complete work on all the lots, but he said that it stopped working because it was not receiving payment.

CMG-Ashford asserts, however, that the expenses it incurred to complete or fix plaintiffs electrical work, combined with resulting delays, additional management costs, and finance charges, exceeded the amount that plaintiff claims it is due. Specifically, CMG-Ashford maintains that plaintiff owes it $31,208.08 for management and supervision costs that resulted from being forced to review and correct plaintiffs work, dealing with the realtor and town inspectors during the delay, and the compounded daily interest that CMG-Ashford paid to the bank on construction loans for the houses during the delay. James Colucci testified that he spoke to Mr. DeSimone “on a couple of different occasions” concerning the poor quality of plaintiffs work on the City View project and about the fact that plaintiffs work sometimes had not passed inspection. He also chided plaintiff for not always cleaning up the site after work. He further testified that it was particularly important that plaintiffs electrical work be finished in a timely manner so that other trades could follow with their portions of the work. James Colucci testified that Mr. DeSimone “worked with [defendants] long enough that he knew to keep up with the other trades.” Nonetheless, he said that he had to hire other contractors to complete the electrical work when plaintiff refused to return to the job. Thomas Colucci, James Colucci’s brother and an employee of CMG-Ashford, also testified that plaintiff left the work site “unclean” and did not finish the rough wiring according to plan. He said that he spoke to Mr. DeSimone about his dissatisfaction in the spring or early summer of 2001.

Karen Rainone, the former office manager of CMG, testified that she took phone calls from Mr. DeSimone during which he expressed his desire to be paid before completing additional work. She also said that she remembered hearing complaints about plaintiff and other subcontractors concerning their failure to clean up after themselves at the City View project work *617 site. She testified that her job sometimes required her to inform subcontractors when their work did not pass inspection. Although Ms. Rainone first stated that she did not recall a failed inspection concerning plaintiffs work, she later testified on cross-examination that she communicated with plaintiff on at least one occasion concerning a failed inspection on the City View project.

The other contract disputed in this case was created when Mr. DeSimone and James Colucci orally agreed that plaintiff would do electrical work on James Coluc-ci’s private home on Iroquois Trail in Glo-cester, Rhode Island (the Iroquois Trail project). The plaintiff worked on the Iroquois Trail project from August 2000 until February or April of 2001. James Colucci testified that plaintiffs work on the Iroquois Trail project already had begun when the City View project commenced. The parties presented conflicting testimony concerning the price specified in the oral agreement for the Iroquois Trail project. Mr. DeSimone testified that he and James Colucci agreed that the price was “not to exceed” $9,500. James Colucci, on the other hand, testified that he agreed to pay plaintiff a flat price of $6,800. Thomas Colucci also testified that the price was $6,800. In addition, the record reflects an electrical permit application in which plaintiff listed $5,000 as the “ESTIMATED COST OF COMPLETED INSTALLATION” for the Iroquois Trail project. Mr. DeSimone testified, however, that this was only a “rough estimate,” that he wrote the $5,000 amount to save money on the permit fee, and that he filled out the permit application before knowing the extent of the work to be done on the Iroquois Trail project. 3 Mr. DeSimone could not remember whether he ever submitted an amended electrical permit application to the Town of Glocester reflecting a more “accurate” estimate.

Mr. DeSimone testified that the plaintiff corporation had performed $9,410 worth of the work on the Iroquois Trail project when it ceased labor. It is undisputed that plaintiff received $6,000 over four payments from James Colucci for the contract. Mr. DeSimone contends that the plaintiff corporation still is owed the balance of $3,410 for the work completed, even though he admitted that “the house wasn’t completed a hundred percent.” James Co-lucci testified, however, that plaintiffs work on the Iroquois Trail project was only about 80 to 85 percent done when plaintiff stopped work. James Colucci also said that although he was satisfied with the work that plaintiff did finish at the Iroquois Trail project “[f]or the most part,” there were several problems with the work, including jobs that were not completed or were done incorrectly, so that other contractors had to be hired to fix plaintiffs work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butterfly Realty v. James Romanella & Sons, Inc.
93 A.3d 1022 (Supreme Court of Rhode Island, 2014)
Alexander Rose v. State of Rhode Island
92 A.3d 903 (Supreme Court of Rhode Island, 2014)
Corbin v. Dept. of Human Serv.
Superior Court of Rhode Island, 2011
Cahill v. Morrow
11 A.3d 82 (Supreme Court of Rhode Island, 2011)
Horbet v. New Penn, Inc.
Superior Court of Rhode Island, 2011
Fatulli v. Bowen's Wharf Co. Inc.
Superior Court of Rhode Island, 2010
Sheehan v. Town of North Smithfield
Superior Court of Rhode Island, 2010
Alpha Omega Construction, Inc. v. Proprietors of Swan Point Cemetery
962 A.2d 733 (Supreme Court of Rhode Island, 2008)
New England Development, LLC v. Berg
913 A.2d 363 (Supreme Court of Rhode Island, 2007)
Design Fabricators v. Sixty
Superior Court of Rhode Island, 2007

Cite This Page — Counsel Stack

Bluebook (online)
901 A.2d 613, 2006 R.I. LEXIS 131, 2006 WL 1793599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desimone-electric-inc-v-cmg-inc-ri-2006.