Desert Protection Society v. Bernhardt

CourtDistrict Court, E.D. California
DecidedSeptember 29, 2023
Docket2:19-cv-00198
StatusUnknown

This text of Desert Protection Society v. Bernhardt (Desert Protection Society v. Bernhardt) is published on Counsel Stack Legal Research, covering District Court, E.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Desert Protection Society v. Bernhardt, (E.D. Cal. 2023).

Opinion

1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 FOR THE EASTERN DISTRICT OF CALIFORNIA 10 11 DESERT PROTECTION SOCIETY, No. 2:19-cv-00198-DJC-CKD 12 Plaintiffs, 13 v. ORDER

14 DEBRA HAALAND, in her official capacity as Secretary of the United 15 State Department of the interior, et al. 16 Defendants, 17 and

18 EAGLE CREST ENERGY COMPANY, INC. 19 Defendant-Intervenor. 20 21 This case deals with the Bureau of Land Management’s (“BLM”) decision to 22 amend the California Desert Conservation Area Plan and grant a right-of-way to 23 Intervenor-Defendant, Eagle Crest Energy Company to “construct, operate, maintain, 24 and decommission a gen-tie [electrical] line and water supply pipeline” (the “Right-of- 25 Way Project”) necessary for a pumped storage electrical generation project (the 26 “Energy Project”). The Energy Project was approved and licensed by the Federal 27 Energy Regulatory Commission (“FERC”) in 2014, and the Right-of-Way Project was 28 approved in 2018. Plaintiff, the Desert Protection Society, has brought this suit 1 contending that BLM violated the National Environmental Policy Act and the Federal 2 Land Policy Management Act, and has thereby violated the Administrative Procedure 3 Act in its assessment and grant of the right-of-way. While it is apparent that Plaintiff 4 disagrees with FERC’s assessment and approval of the underlying Energy Project, this 5 Court is limited to reviewing whether BLM acted in an arbitrary or capricious manner 6 or violated the relevant statutes and regulations in its assessment and approval of the 7 Right-of-Way Project, not FERC’s assessment of the Energy Project. 8 Each party — Plaintiff, Defendants, and Intervenor-Defendant — has filed a Cross 9 Motion for Summary Judgement. (Pl.’s Mot. (ECF No. 27-1), Defs.’ Mot. (ECF No. 30), 10 Int. Def.’s Mot. (EFC No. 31-1).) For the reasons below, Defendants’ and Intervenor- 11 Defendant’s Motions for Summary Judgement are GRANTED in full, and Plaintiff’s 12 Motion for Summary Judgement is DENIED. 13 I. Background 14 In 2014, FERC approved and licensed to Eagle Crest Energy Company (“Eagle 15 Crest”) the Energy Project, a large-scale pumped storage electrical generation project 16 which repurposes a defunct mine near Joshua Tree National Park in Southern 17 California. (Int. Def.’s Mot. at 9–10.) The Energy Project is licensed to operate for at 18 least 50 years with the potential for renewal. ( at 11.) FERC completed a 19 comprehensive Environmental Impact Statement (“EIS”) assessing the impacts of the 20 Energy Project, including the portions of the project that would be on BLM-managed 21 land, and various mitigation measures as part of its approval process. (Defs.’ Mot. at 22 2.) Plaintiff intervened in the FERC proceedings, submitted comments on the EIS and 23 sought a rehearing of the project’s license in 2014, but ultimately did not seek timely 24 judicial review of the license. ( at 7.) 25 After the Energy Project was licensed, Eagle Crest sought a right-of-way from 26 BLM to access and construct the required gen-tie line and water pipeline on land that 27 FERC had withdrawn for Eagle Crest’s use pursuant to the Federal Power Act, but 28 which was managed by the BLM. (Int. Def.’s Mot. at 11.) While the impacts of the 1 utility lines and the proposed right-of-way were already assessed in FERC’s EIS, BLM 2 prepared an Environmental Assessment which incorporated (or “tiered to”) the FERC 3 EIS, but conducted further, more detailed assessment of the impacts of the right-of- 4 way specifically. (Int. Def.’s Mot. at 11–12; Admin. R. (“A.R.”) 015467.) After 5 completing the Environmental Assessment, BLM concluded that the right-of-way 6 would not have a significant impact on the environment, and therefore determined an 7 EIS for the Right-of-Way Project was not necessary. (Int. Def.’s Mot. at 12.) Instead, 8 BLM issued a Finding of No Significant Impact on August 1, 2018. ( ) 9 In the intervening period between the Energy Project approval and BLM’s 10 assessment of the Right-of-Way Project, BLM’s California Desert Conservation Area 11 Plan (“California Conservation Plan”) was amended by the Desert Renewable Energy 12 Conservation Plan (“Renewable Energy Plan”). The Renewable Energy Plan 13 established Areas of Critical Environmental Concern (“Area(s) of Critical Concern”) 14 and conservation and management actions for certain land uses in the California 15 deserts. ( Pl.’s Mot. at 35); U.S. Bureau of Land Mgmt., 16 42, 90–92 (2016). Part of the right-of-way granted to Eagle Crest 17 runs through an Area of Critical Concern that was designated under the Renewable 18 Energy Plan after FERC approved the Energy Project and withdrew lands for the 19 associated utility lines. (Pl. Mot. at 35.) Ordinarily, pursuant to the Renewable Energy 20 Plan, any utility lines running through this region would need to be routed through a 21 designated utility corridor. However, the utility corridor was full, and the siting of the 22 FERC licensed project would not allow for the use of a different utility corridor. (Pl.’s 23 Mot. at 31; Defs.’ Mot. at 26–27.) To address this inconsistency, BLM amended the 24 relevant land use plan, the California Conservation Plan, to allow a portion of the right- 25 of-way to exist outside of the designated utility corridor. (Pl.’s Mot. at 12.) The 26 California Conservation Plan amendment was assessed within the Environmental 27 Assessment for the Right-of-Way Project. (A.R. 015480–82.) 28 1 On May 17, 2017, Plaintiff submitted a protest letter in response to the 2 proposed plan amendment. (Pl.’s Mot. at 36.) BLM issued an individualized response 3 letter to Plaintiff on August 1, 2018, and directed Plaintiff to the Protest Resolution 4 Report it issued the same day. (A.R. 010417, 004434.) The Protest Resolution Report 5 included individual responses to two of the issues Plaintiff raised, as well as responses 6 to issues raised by other parties. 7 On August 1, 2018, BLM issued a Decision Record approving the plan 8 amendment and granting the right-of-way. (A.R. 010425–26.) 9 On September 17, 2018, Plaintiff filed an administrative appeal challenging 10 BLM’s Decision Record and a Petition to Stay BLM’s decision with the Interior Board of 11 Land Appeals (“Appeals Board”). (Int. Def.’s Mot. at 13.) On November 26, 2018, the 12 Appeals Board denied Plaintiff’s Petition to Stay, and Plaintiff moved to dismiss its 13 appeal on January 31, 2019 before the Appeals Board reached a decision on the 14 merits. ( ) The Appeals Board removed the appeal from its docket on February 16, 15 2019. ( ) Plaintiff filed the instant case the same day it withdrew its appeal on 16 January 31, 2019. (Compl. (ECF No.1).) 17 II. Legal Standard for Motion for Summary Judgement 18 Ordinarily, summary judgment is appropriate under Rule 56 where the moving 19 party “shows that there is no genuine dispute as to any material fact and the movant is 20 entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). However, “[i]n a case 21 involving review of a final agency action under the Administrative Procedure Act . . . 22 the standard set forth in Rule 56(c) does not apply because of the limited role of a 23 court in reviewing the administrative record.” , 459 F. Supp. 2d 24 76, 90 (D. D.C. 2006). “A court conducting APA judicial review does not resolve 25 factual questions, but instead determines ‘whether or not as a matter of law the 26 evidence in the administrative record permitted the agency to make the decision it 27 did.’” , No. 2:12-CV-02800-TLN, 2014 WL 28 2092385, at *4 (E.D. Cal. May 19, 2014) (quoting , 459 F. Supp. 2d at 90).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kleppe v. Sierra Club
427 U.S. 390 (Supreme Court, 1976)
Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
Marsh v. Oregon Natural Resources Council
490 U.S. 360 (Supreme Court, 1989)
Auer v. Robbins
519 U.S. 452 (Supreme Court, 1997)
Norton v. Southern Utah Wilderness Alliance
542 U.S. 55 (Supreme Court, 2004)
Colorado Environmental Coalition v. Dombeck
185 F.3d 1162 (Tenth Circuit, 1999)
McGrath v. Rhode Island Retirement Board
88 F.3d 12 (First Circuit, 1996)
Nicolaci v. Anapol
387 F.3d 21 (First Circuit, 2004)
Gardner v. United States Bureau of Land Management
638 F.3d 1217 (Ninth Circuit, 2011)
Center for Biological Diversity v. Ken Salazar
695 F.3d 893 (Ninth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Desert Protection Society v. Bernhardt, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desert-protection-society-v-bernhardt-caed-2023.