DeROSSETT v. DUKE ENERGY CAROLINAS, LLC

698 S.E.2d 455, 206 N.C. App. 647, 2010 N.C. App. LEXIS 1628
Court of Appeals of North Carolina·Decided September 7, 2010·No. COA09-820·Published·Cited by 6 cases

Opinion

ERVIN, Judge.

Plaintiffs Julie A. DeRossett and Richard A. Sutton appeal from the trial court’s order granting partial summary judgment in favor of Defendant Duke Energy Carolinas, LLC. After a careful review of Plaintiffs’ challenges to the trial court’s order in light of the record and the applicable law, we conclude that the trial court’s order should be affirmed.

I. Factual Background

A. Substantive Facts

In 1942, Duke Energy’s predecessor, Nantahala Power and Light Company, initiated condemnation proceedings against Margaret Jordan and Dixie Freeman for the purpose of obtaining an easement authorizing the construction and operation of an electric transmission line across a tract of property in which they owned interests located in Graham County, North Carolina. 1 At the conclusion of the condemnation proceeding, the parties entered into a consent judgment which granted an easement across the property of Ms. Jordan and Ms. Freeman to Nantahala. 2 During the pendency of the condemnation *649 proceeding, Nantahala constructed the proposed transmission line across Ms. Freeman’s property. Nantahala merged into Duke Energy Corporation in 1998, with the properties that had formerly been part of the Nantahala system coming under the ownership of Duke Energy Carolinas, LLC, in 2006 as part of a further corporate reorganization. Duke Energy Carolinas continues to operate the transmission line located on Ms. Freeman’s property.

Since 1942, the property formerly held by Ms. Jordan and Ms. Freeman has been divided among multiple owners because of inheritance or sale to third parties. Plaintiffs own a small section of the property previously owned by Ms. Freeman. However, the tract of property specifically delineated in the condemnation petition does not include any of Plaintiffs’ property. The remainder of Ms. Freeman’s property, including the tract specifically described in the consent judgment, is owned by individuals who are not parties to this case. However, in order to access the right-of-way granted in the consent judgment for the purpose of maintaining the transmission line without traveling the length of the described easement, Duke Energy believes that it is entitled to cross property owned by Plaintiffs or others.

In 2006, Plaintiff Richard A. Sutton granted permission to James Hollifield and Larry Jenkins, who were acting as agents for Duke Energy, to use Plaintiffs’ property to access the right-of-way granted in the consent judgment. Duke Energy’s agents had already made an unsuccessful attempt to gain access to the right-of-way from individuals holding title to other portions of Ms. Freeman’s property. After Defendant’s agents entered Plaintiffs’ property, altered a roadway, and destroyed a bridge leading to a residence located on Plaintiffs’ property, Plaintiff Sutton revoked the permission to enter on to his property that he had previously granted to Duke Energy’s agents.

B. Procedural Background

On 24 October 2006, Plaintiffs filed a complaint in Graham County District Court seeking to quiet title to their property and alleging that Duke Energy’s agents had trespassed upon their property On 28 December 2006, Defendants filed a Motion to Dismiss. On 5 March 2007, Defendants filed an Answer; Counterclaims; and Motion for Preliminary and Permanent Injunction. On 10 May 2007, Plaintiffs filed a Reply to Defendants’ Counterclaims.

*650 On 4 April 2008, an order was issued transferring the case from the District Court to the Superior Court. Defendants filed a Motion for Summary Judgment and an affidavit by Sue C. Harrington on 22 July 2008. In response, Plaintiffs filed the affidavits of Ms. DeRossett and Mr. Sutton on 30 July 2008. Defendants’ summary judgment motion was heard at the 2 February 2009 session of Macon County Superior Court.

On 9 February 2009, the trial court signed an order that was subsequently filed on 11 February 2009 granting Duke Energy’s motion for partial summary judgment. In its order, the trial court declared that Duke Energy was “the owner of a secondary easement and right of way as set forth in the” consent judgment; found and determined “that said Judgment is not ambiguous;” construed the consent judgment, “as a matter of law, to include the right of [Duke Energy] and its agents to go over and across Plaintiffs’ lands outside of the right of way strip described in said Judgment, for any and all purposes related to facilities within said right of way strip;” and found “that the reasonableness of the construction of the new bridge and the location of the access right of way on Plaintiffs’ property is a jury question not resolved by this order.” The trial court also certified its order for immediate appellate review pursuant to N.C. Gen. Stat. § 1A-1, Rule 54(b).

On 13 February 2009, Plaintiffs filed a Motion for Reconsideration in which they alleged that the trial court had entered partial summary judgment in favor of Duke Energy without joining all necessary parties in violation of N.C. Gen. Stat. § 1A-1, Rule 19. The trial court denied Plaintiffs’ reconsideration motion by means of an order that was sighed on 25 March 2009 and filed on 1 April 2009. On 7 April 2009, Plaintiffs noted an appeal to this Court from the trial court’s order.

II. Legal Analysis

A. Standard of Review

This Court reviews orders granting partial summary judgment on a de novo basis. Sturgill v. Ashe Mem’l Hosp., Inc., 186 N.C. App. 624, 626, 652 S.E.2d 302, 304 (2007), disc. rev. denied, 362 N.C. 180, 658 S.E.2d 662 (2008). Summary judgment is appropriate if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.” N.C. Gen. Stat. § 1A-1, Rule 56(c).

*651 [Defendants] may show entitlement to summary judgment by (1) proving that an essential element of [Plaintiffs’] case is nonexistent, or (2) showing through discovery that [Plaintiffs] cannot produce evidence to support an essential element of [their] claim, or (3) showing that [Plaintiffs] cannot surmount an affirmative defense .... Once the party seeking summary judgment makes the required showing, the burden shifts to the nonmoving party to produce a forecast of evidence demonstrating specific facts, as opposed to allegations, showing that [Plaintiffs] can at least establish a prima facie case at trial.

Draughon v. Harnett County Bd. of Educ., 158 N.C. App. 208, 212, 580 S.E.2d 732, 735 (2003) (internal citations and quotations omitted), aff’d, 358 N.C. 131, 591 S.E.2d 521 (2004).

Free access — add to your briefcase to read the full text and ask questions with AI

DeROSSETT v. DUKE ENERGY CAROLINAS, LLC, 698 S.E.2d 455, 206 N.C. App. 647, 2010 N.C. App. LEXIS 1628 (N.C. Ct. App. 2010).

698 S.E.2d 455 (DeROSSETT v. DUKE ENERGY CAROLINAS, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Paez v. Pettis
Court of Appeals of North Carolina, 2026
The Armstrong Law Firm, P.A. v. Chapman
Court of Appeals of North Carolina, 2025
Paul A. Hinshaw v. M-C-M Properties, LLC
450 S.W.3d 823 (Missouri Court of Appeals, 2014)
Wallach v. Linville Owners Ass'n, Inc.
760 S.E.2d 23 (Court of Appeals of North Carolina, 2014)
Barker v. Barker
745 S.E.2d 910 (Court of Appeals of North Carolina, 2013)
Yost v. Yost
713 S.E.2d 758 (Court of Appeals of North Carolina, 2011)