FIFTH DIVISION MCFADDEN, P. J., BROWN and MARKLE, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules
June 27, 2023
In the Court of Appeals of Georgia A23A0136. DEPARTMENT OF TRANSPORTATION v. 0.095 ACRES OF LAND et al.
MCFADDEN, Presiding Judge.
This case involves the just and adequate compensation that the Department of
Transportation owes Lamar and Melody Pendley for the partial taking of their
property for a highway project. See Ga. Const. of 1983, Art. I, Sec. III, Par. I (a). In
a partial-taking case, “just and adequate compensation is the sum of the market value
of the property that is taken and the consequential damage, if any, to the property that
remains, both measured at the time of taking.” Toler v. Dept. of Transp., 328 Ga. App.
144, 146 (1) (761 SE2d 550) (2014) (citation and punctuation omitted).
After the trial court entered judgment on a jury verdict awarding the Pendleys
$648,800, the Department of Transportation appealed. The Department contends that the trial court improperly allowed the Pendleys to present certain evidence of
consequential damages to their remaining property because that evidence pertained
to losses caused by the overall project rather than the specific taking; addressed
damages that were shared by the public rather than specific to the Pendleys; or
concerned the condition of the property after the taking had occurred.
But as detailed below, the Department did not preserve its evidentiary
objections for ordinary appellate review. The trial court never definitively denied the
motion in limine in which the Department raised these objections, and the Department
did not object contemporaneously to the evidence when it was presented.
Moreover, the Department has not met the stringent requirements to obtain
reversal based on plain error. The Department has made no argument whatsoever as
to plain error, and any error by the trial court was not obvious. So we affirm.
1. Facts and procedural history.
The record shows that the Pendleys owned approximately 14 acres of real
property. Although their property was zoned for residential use, the Pendleys had a
variance that allowed them to operate a commercial business on it behind their
residence.
2 In December 2015, the Department petitioned to take .095 acres of the
Pendleys’ property as part of a project to replace the two-lane county road fronting
the property with a four-lane state highway. The new highway would not actually be
built on the property taken from the Pendleys; instead, the taken property would be
used as a right-of-way next to the highway. The Department estimated $4,500 to be
just and adequate compensation for the taking.
Dissatisfied with that amount of compensation, the Pendleys sought a jury trial
under OCGA §§ 32-3-14 and 32-3-16. After the parties conducted discovery, the
Department filed a pretrial motion in limine to prevent the introduction of certain
evidence of purported consequential damages. In that motion, the Department argued
that the Pendleys should be barred from introducing “evidence purporting to show a
diminution in fair market value of [the Pendleys’] remaining property based solely
upon the widening of the existing road fronting [their] property[,]” specifically the
anticipated testimony of the Pendleys’ expert appraiser, Bruce Penn. The Department
also argued that the Pendleys should be barred from introducing “evidence of
purported consequential damages based upon facts derived significantly after the date
of taking[,]” specifically the anticipated testimony of the Pendleys’ expert traffic
engineer, Marc Acampora.
3 After a hearing on the Department’s motion in limine, the trial court entered
an order provisionally denying it, holding that the Department “ha[d] not shown that
the evidence it seeks to exclude would not be admissible under any circumstances at
trial[.]” The trial court noted that her denial of the motion was based on the limited
record before her and was without prejudice. And the trial court stated that the
Department could “rais[e] these same objections at trial on the basis of the evidentiary
record as developed at that time.”
During the jury trial but before the Pendleys presented testimony from either
Penn or Acampora, the Department renewed its motion in limine. The trial court
stated, “For purposes of the record, I note you renewed the motion. The motion is
made on all the same grounds as previously stated; is that correct?” The Department’s
counsel stated that it was. Then the following exchanged occurred:
THE COURT: And we were present here in court approximately two weeks ago, you presented your evidence. [The Pendleys’ counsel] was here. He presented his defenses, and the Court denied your motion in limine.
[THE DEPARTMENT’S COUNSEL]: Has the Court changed its mind?
THE COURT: No, I haven’t changed my mind. I still deny it today.
4 Subsequently, the Pendleys introduced the challenged testimony without
objection by the Department. Their expert appraiser, Penn, opined that just and
adequate compensation for the partial taking was $648,800. He based this figure in
part on his opinion that the Pendleys suffered consequential damages to their
remaining property caused by the conversion of the road to a four-lane state highway.
Penn testified that the construction of a four-lane highway would diminish the
remaining property’s fair market price and opined as to what someone would pay to
buy the property after the construction of the highway. This was partly because the
highway would negatively affect the ability for vehicles to safely enter and exit the
Pendleys’ driveway. He testified that some of those costs were unique to the Pendleys
due to their business use of the property.
The Pendleys’ expert traffic engineer, Acampora, addressed safety
improvements that he believed might be required by the construction of the four-lane
state highway. He opined at trial that, once the four-lane highway was built, a right-
turn deceleration lane would be needed for the Pendleys’ driveway. He based this
opinion on the anticipated volume of traffic on the road, including the volume of
traffic turning in and out of the Pendleys’ driveway, including trucks which served
5 their business. In support of this opinion, Acampora testified that he personally
performed traffic counts in December 2017 and May 2021, and the Pendleys also
introduced documentary evidence of those traffic counts. The Department expressly
did not object to the admission of the traffic-count exhibits.
On appeal, the Department argues that “[a]ll of the evidence of the Pendleys’
claim for consequential damages was improperly admitted at trial,” pointing to the
opinion testimony of the Pendleys’ expert appraiser, Penn, and their expert traffic
engineer, Acampora. The Department asserts that this evidence was not relevant, and
should not have been admitted, for three reasons: (1) because it concerned damages
that were not alleged to have been caused by the specific taking of the small portion
of land for the right-of-way, but rather concerned damages caused by the road-
Free access — add to your briefcase to read the full text and ask questions with AI
FIFTH DIVISION MCFADDEN, P. J., BROWN and MARKLE, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules
June 27, 2023
In the Court of Appeals of Georgia A23A0136. DEPARTMENT OF TRANSPORTATION v. 0.095 ACRES OF LAND et al.
MCFADDEN, Presiding Judge.
This case involves the just and adequate compensation that the Department of
Transportation owes Lamar and Melody Pendley for the partial taking of their
property for a highway project. See Ga. Const. of 1983, Art. I, Sec. III, Par. I (a). In
a partial-taking case, “just and adequate compensation is the sum of the market value
of the property that is taken and the consequential damage, if any, to the property that
remains, both measured at the time of taking.” Toler v. Dept. of Transp., 328 Ga. App.
144, 146 (1) (761 SE2d 550) (2014) (citation and punctuation omitted).
After the trial court entered judgment on a jury verdict awarding the Pendleys
$648,800, the Department of Transportation appealed. The Department contends that the trial court improperly allowed the Pendleys to present certain evidence of
consequential damages to their remaining property because that evidence pertained
to losses caused by the overall project rather than the specific taking; addressed
damages that were shared by the public rather than specific to the Pendleys; or
concerned the condition of the property after the taking had occurred.
But as detailed below, the Department did not preserve its evidentiary
objections for ordinary appellate review. The trial court never definitively denied the
motion in limine in which the Department raised these objections, and the Department
did not object contemporaneously to the evidence when it was presented.
Moreover, the Department has not met the stringent requirements to obtain
reversal based on plain error. The Department has made no argument whatsoever as
to plain error, and any error by the trial court was not obvious. So we affirm.
1. Facts and procedural history.
The record shows that the Pendleys owned approximately 14 acres of real
property. Although their property was zoned for residential use, the Pendleys had a
variance that allowed them to operate a commercial business on it behind their
residence.
2 In December 2015, the Department petitioned to take .095 acres of the
Pendleys’ property as part of a project to replace the two-lane county road fronting
the property with a four-lane state highway. The new highway would not actually be
built on the property taken from the Pendleys; instead, the taken property would be
used as a right-of-way next to the highway. The Department estimated $4,500 to be
just and adequate compensation for the taking.
Dissatisfied with that amount of compensation, the Pendleys sought a jury trial
under OCGA §§ 32-3-14 and 32-3-16. After the parties conducted discovery, the
Department filed a pretrial motion in limine to prevent the introduction of certain
evidence of purported consequential damages. In that motion, the Department argued
that the Pendleys should be barred from introducing “evidence purporting to show a
diminution in fair market value of [the Pendleys’] remaining property based solely
upon the widening of the existing road fronting [their] property[,]” specifically the
anticipated testimony of the Pendleys’ expert appraiser, Bruce Penn. The Department
also argued that the Pendleys should be barred from introducing “evidence of
purported consequential damages based upon facts derived significantly after the date
of taking[,]” specifically the anticipated testimony of the Pendleys’ expert traffic
engineer, Marc Acampora.
3 After a hearing on the Department’s motion in limine, the trial court entered
an order provisionally denying it, holding that the Department “ha[d] not shown that
the evidence it seeks to exclude would not be admissible under any circumstances at
trial[.]” The trial court noted that her denial of the motion was based on the limited
record before her and was without prejudice. And the trial court stated that the
Department could “rais[e] these same objections at trial on the basis of the evidentiary
record as developed at that time.”
During the jury trial but before the Pendleys presented testimony from either
Penn or Acampora, the Department renewed its motion in limine. The trial court
stated, “For purposes of the record, I note you renewed the motion. The motion is
made on all the same grounds as previously stated; is that correct?” The Department’s
counsel stated that it was. Then the following exchanged occurred:
THE COURT: And we were present here in court approximately two weeks ago, you presented your evidence. [The Pendleys’ counsel] was here. He presented his defenses, and the Court denied your motion in limine.
[THE DEPARTMENT’S COUNSEL]: Has the Court changed its mind?
THE COURT: No, I haven’t changed my mind. I still deny it today.
4 Subsequently, the Pendleys introduced the challenged testimony without
objection by the Department. Their expert appraiser, Penn, opined that just and
adequate compensation for the partial taking was $648,800. He based this figure in
part on his opinion that the Pendleys suffered consequential damages to their
remaining property caused by the conversion of the road to a four-lane state highway.
Penn testified that the construction of a four-lane highway would diminish the
remaining property’s fair market price and opined as to what someone would pay to
buy the property after the construction of the highway. This was partly because the
highway would negatively affect the ability for vehicles to safely enter and exit the
Pendleys’ driveway. He testified that some of those costs were unique to the Pendleys
due to their business use of the property.
The Pendleys’ expert traffic engineer, Acampora, addressed safety
improvements that he believed might be required by the construction of the four-lane
state highway. He opined at trial that, once the four-lane highway was built, a right-
turn deceleration lane would be needed for the Pendleys’ driveway. He based this
opinion on the anticipated volume of traffic on the road, including the volume of
traffic turning in and out of the Pendleys’ driveway, including trucks which served
5 their business. In support of this opinion, Acampora testified that he personally
performed traffic counts in December 2017 and May 2021, and the Pendleys also
introduced documentary evidence of those traffic counts. The Department expressly
did not object to the admission of the traffic-count exhibits.
On appeal, the Department argues that “[a]ll of the evidence of the Pendleys’
claim for consequential damages was improperly admitted at trial,” pointing to the
opinion testimony of the Pendleys’ expert appraiser, Penn, and their expert traffic
engineer, Acampora. The Department asserts that this evidence was not relevant, and
should not have been admitted, for three reasons: (1) because it concerned damages
that were not alleged to have been caused by the specific taking of the small portion
of land for the right-of-way, but rather concerned damages caused by the road-
expansion project generally; (2) because it concerned damages that were shared by
the public rather than being specific to the Pendleys; and (3) because, in the case of
the traffic engineer’s testimony, it was based on traffic-count data obtained after the
taking.
2. The claimed errors have not been preserved for ordinary appellate review.
The Department did not properly preserve its evidentiary challenges for
ordinary appellate review. Our Evidence Code provides that “[e]rror shall not be
6 predicated upon a ruling which admits . . . evidence unless a substantial right of the
party is affected and . . . a timely objection or motion to strike appears of record. . .
.” OCGA § 24-1-103 (a) (1). “Once the court makes a definitive ruling on the record
admitting . . . any evidence, either at or before trial, a party need not renew an
objection . . . to preserve such claim of error for appeal.” OCGA § 24-1-103 (a)
(emphasis supplied). The question here is whether the trial court’s rulings denying the
Department’s motion in limine were definitive rulings, such that the Department was
not required to object to the evidence when it was introduced.
The trial court’s initial, written ruling denying the Department’s motion in
limine was not a definitive ruling because it left open the possibility that the court
would revisit the issue later. As detailed above, the trial court made the ruling
“without prejudice” and contemplated that the Department could raise the issue again
at trial, after the evidence was more fully developed. A ruling that leaves open the
possibility of the future admission of the evidence is not definitive. See Wilson v.
State, 301 Ga. 83, 87-88 (2) (799 SE2d 757) (2017). See also Yates v. Pinella
Hematology & Oncology, 21 F4th 1288, 1297 (II) (11th Cir. 2021) (“if the trial
court’s ruling is tentative or without prejudice, there is no definitive ruling on the
objection”) (emphasis supplied).
7 And even though the Department renewed the motion in limine at trial, the
record does not show that the trial court definitively ruled on the renewed motion.
Rather, as set forth more fully above, when the Department’s counsel asked the trial
court if she had “changed [her] mind” about the earlier ruling, the trial court replied
that she had not and that she “still den[ied] it.” There was no indication that the trial
court intended her ruling on the renewed motion to be different in any way than her
earlier, non-definitive pretrial motion. There was also no discussion by counsel or the
trial court as to whether the evidence had been sufficiently developed to allow a
different, more definitive ruling. As stated above, neither of the expert witnesses
whose testimony was at issue had begun to testify in the trial.
Arguably, the definitiveness of the trial court’s ruling on the renewed motion
in limine was unclear. But in such circumstances, the Department had the burden to
clarify that issue. An advisory committee note to Federal Rule of Evidence 103 (b),
after which OCGA § 24-1-103 (a) is “specifically patterned,” Williams v. Harvey, 311
Ga. 439, 445 (1) (a) (858 SE2d 479) (2021), explains that the rule “imposes the
obligation on counsel to clarify whether an in limine or other evidentiary ruling is
definitive when there is doubt on that point.” Advisory Committee’s Notes to Federal
Rule of Evidence 103 (b). Such notes are highly persuasive authority in construing
8 provisions of our new Evidence Code that are materially identical to Federal Rules
of Evidence, such as OCGA § 24-1-103, see State v. Almanza, 304 Ga. 553, 559 (3)
n. 6 (820 SE2d 1) (2018), and our Supreme Court has acknowledged this particular
note in discussing OCGA § 24-1-103 (a). See Williams, 311 Ga. at 453 (2) n. 13.
Because the Department did not obtain a definitive ruling on the evidentiary
challenges raised in its motion in limine and did not object contemporaneously to that
evidence when it was introduced at trial, we may review its evidentiary challenges
only for plain error. See OCGA § 24-1-103 (d); Chrysler Group v. Walden, 303 Ga.
358, 359 (812 SE2d 244) (2018).
3. The Department has not shown plain error.
To show plain error, the Department
must show an error or defect that has not been affirmatively waived by the [Department], that is clear and obvious, and that affected the [Department’s] substantial rights by affecting the outcome of the trial court proceedings; if these three requirements are satisfied, we have the discretion to remedy the error but should do so only if the error seriously affects the fairness, integrity or public reputation of judicial proceedings.
Chrysler Group, 303 Ga. at 370 (II) (B) (citation and punctuation omitted).
9 Neither side has made any argument on appeal as to whether or not these
requirements for showing plain error have been met. Nevertheless, because the
Department properly enumerated and argued its claims of erroneous evidentiary
rulings, we will review those claims for plain error. Hines v. State, 320 Ga. App. 854,
864 (5) (b) (740 SE2d 786) (2013). But we point out that the Department’s “fail[ure]
to articulate how the alleged error[s] satisf[y] the high standards required to establish
plain error increases the likelihood that [we] will reject the claim[s].” Id. (citation and
punctuation omitted).
(a) Evidence of diminution of value to the remaining property caused by the
overall road project.
The Department argues that the challenged testimony was inadmissible because
it concerned the diminution of value to the Pendleys’ remaining property caused by
the overall road project, rather than by the taking of the specific .095 acres of land for
the right-of-way. The Department has cited to several cases for the proposition that
a property owner’s consequential damages cannot arise merely from the general
effects of a project but must arise from the use for which the specific property was
taken. See, e. g., Simon v. Dept. of Transp., 245 Ga. 478 (265 SE2d 777) (1980);
Herron v. MARTA, 177 Ga. App. 201, 202-203 (2) (338 SE2d 777) (1985); Riviera
10 Assoc. v. Dept. of Transp., 174 Ga. App. 29, 29-30 (329 SE2d 221) (1985); Mason
v. Dept. of Transp., 159 Ga. App. 471 (283 SE2d 690) (1981).
But the Pendleys argue that the Department’s cases are factually inapposite.
They cite Dept. of Transp. v. White, 270 Ga. 281, 282-283 (508 SE2d 407) (1998),
in which our Supreme Court recognized that, depending on the facts of the case, the
impact of an adjacent road or public transportation project may result in continuous
and permanent consequential damage to the remainder which is compensable in a
condemnation proceeding.
There is evidence in this case that the taking of the Pendleys’ property for a
right-of-way was necessary to facilitate the highway expansion, even if the expanded
highway itself was not going to be placed on that property. Arguably, the negative
effects of the highway expansion project on the Pendleys’ remaining property arose
from the use for which the right-of-way property was taken, making the facts of this
case more similar to those in White, supra, than those in the authorities cited by the
Department. Certainly, the availability of consequential damages in such
circumstances must be decided case by case. See generally DeKalb County v. United
Family Life Ins. Co., 235 Ga. 417, 418 (219 SE2d 707) (1975) (compensable elements
of damages in condemnation proceedings must be determined on a case-by-case
11 basis). So without reaching the issue of whether the trial court abused her broad
discretion in admitting the evidence in this particular case, see generally Smith v.
State, 299 Ga. 424, 429 (2) (b) (788 SE2d 433) (2016) (a trial court has broad
discretion in determining the relevance and admissibility of evidence), we conclude
that the Department “has failed to show plain error as it is not obvious under our
precedent that [the trial court so abused her discretion].” Williams v. State, __ Ga. __
(3) (Case No. S23A0203, decided May 16, 2023).
(b) Evidence of safety concerns with ingress and egress.
The Department argues that the testimony regarding the need to mitigate safety
concerns involving vehicles turning into the Pendleys’ driveway from a four-lane
state highway was inadmissible because it involved damages shared by the public
rather than damages specific to the Pendleys. But as with the above argument, the
Department has not shown that precedent demanded a different ruling by the trial
court, so it has not shown that any error by the trial court was an obvious error. See
Williams, __ Ga. at __ (3).
The Department cites authority for the proposition that changes in traffic
patterns on adjacent roads generally are not compensable as consequential damages
in condemnation proceedings. As a general rule, an “inconvenience . . . which is
12 shared by the public in general . . . is not compensable, [but one] which is special to
the landowner . . . is compensable.” Dept. of Transp. v. Taylor, 264 Ga. 18, 20 (3) (a)
(440 SE2d 652) (1994). If a property owner’s access to the property is not
“terminated or obstructed, if he has the same access to the highway as he did
[previously], his damage is not special, but is of the same kind, although it may be
greater in degree, than that of the general public, and he has lost no property right for
which he is entitled to compensation.” Dept. of Transp. v. Katz, 169 Ga. App. 310,
312 (2) (312 SE2d 635) (1983) (citation and punctuation omitted). “[G]reater
difficulty in ingress and egress which is occasioned by a change in traffic patterns is
not an appropriate item of damages in [condemnation] proceedings.” Taylor, 264 Ga.
at 20 (3) (a) (citation and punctuation omitted).
Nevertheless, there have been cases in which Georgia courts have recognized
compensable damages in condemnation proceedings based on facts similar to those
here. For example, in Dept. of Transp. v. George, 202 Ga. App. 270, 273 (5) (414
SE2d 307) (1991), we held that a trial court did not err in admitting, to show
consequential damages to the remaining property in a condemnation proceeding,
evidence that changes to the adjacent road limited the ability for certain types of
vehicles to access the property, where such access was “critical” to the business
13 conducted on that property. We cannot say that it was an obvious error for the trial
court to allow similar evidence in this case.
(c) Evidence of post-taking traffic data.
The Department argues that the opinion testimony of the expert traffic engineer
should not have been allowed because it was based on traffic counts performed after
the December 2015 taking. But the Department has not shown plain error. As stated
above, the Department affirmatively waived its objections to the underlying traffic-
count documents entered into evidence during the traffic engineer’s testimony,
because the Department expressly stated that it had no objection to them. See
McAllister v. State, 351 Ga. App. 76, 88 (3) (830 SE2d 443) (2019) (appellant
affirmatively waived his objection to exhibits by stating that he had “no objection”
to them when they were tendered into evidence, and so could not show plain error).
And as to the opinion testimony itself, the Department again has not shown that the
trial court made an obvious error.
“The proper measure of consequential damages to the remainder is the
diminution, if any, in the market value of the remainder in its circumstance just prior
to the time of the taking compared with its market value in its new circumstance just
after the time of the taking.” Wright v. MARTA, 248 Ga. 372, 376 (283 SE2d 466)
14 (1981). But in determining whether there was diminution to the fair market value of
the remaining property, a jury may consider whether a buyer contemplating a
purchase of the remaining property at the time of the taking would take into account
the impact of the anticipated completed project. See id. at 375. The expert traffic
engineer’s opinion testimony about the potential impact of the proposed four-lane
state highway on access into and out of the property was relevant to that issue, and
the Pendleys’ expert appraiser referred to the traffic counts as a basis for reaching his
opinion about the fair market value of the remaining property at the time of the
Judgment affirmed. Brown and Markle, JJ., concur.