Denison Construction Co. v. Manneschmidt

129 A.D. 600, 113 N.Y.S. 1071, 1908 N.Y. App. Div. LEXIS 1376

This text of 129 A.D. 600 (Denison Construction Co. v. Manneschmidt) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denison Construction Co. v. Manneschmidt, 129 A.D. 600, 113 N.Y.S. 1071, 1908 N.Y. App. Div. LEXIS 1376 (N.Y. Ct. App. 1908).

Opinion

Gaynor, J.:

The owner refusing to pay the contractor the fourth installment under the contract when it was demanded, the contractor quit and abandoned the work altogether. Thereupon it filed a lien for the balance it claimed was due under the contract for work and material it had furnished up to that time, and brought this suit to foreclose [602]*602such lien. Tlie complaint is for the said balance, viz., that the plaintiff had performed work and furnished material under the contract to the amount of $10,413.93, on which $5,700 had been paid, leaving a balance of $4,713.93 due to the plaintiff, to which are added some items of alleged extra work and material.

The learned trial Judge having found that the owner refused to pay the fourth installment on the ground that the contractor had not performed the contract up to that stage of payment, and that the contractor thereupon “ stopped work under the contract and thereafter refused to continue with the performance of said contract ”, found also that at that time the contractor “ had not performed its contract up to the period of performance which would entitle it to the fourth payment thereunder, and the work already done by it and materials already furnished were inferior and different from those called for by the said contract ”,

Now, it is trite to say that this finding required that the complaint should be dismissed (except, it may be, for the items of extra work found), for performance — or, as is sometimes tautologically said, substantial performance ”, which is “ performance ” — was a condition precedent to a right to recover anything under the contract (Rowe v. Gerry, 112 App. Div. 358; Van Orden v. MacRae, 121 id. 143). But instead judgment was given for the plaintiff; not on the cause of action set out in the complaint, however, but for the excess of the sum remaining unpaid on the contract when the plaintiff abandoned it, over the amount it cost the owner to complete the building after such abandonment. This was done on a finding that tlie owner completed the contract for the plaintiff’s account, i. e., as its agent or trustee; which, if true, required her to account to the contractor at the end, and pay it any part of the contract price that might remain unexpended, or, on the other hand, to enable her to exact of it any amount expended in excess of the contract price. It would suffice to say that there was.no such cause of action before the court; but to go further, there was no evidence whatever to support the said finding. It was made on the contract itself, viz., on the theory that it contained a provision that if the contractor should at any time break the contract and abandon the work the owner would be obliged to go on and finish the building according to the plans and specifications for the plaintiff’s account, [603]*603i. e., as his agent, or else that if she did finish it, it would be for the contractor’s account, whichever the claim is, for that is left in doubt. That would be a most extraordinary contract for owners to make with contractors. And when the contract in this case is looked at, it is of course found to contain no such thing, but quite the reverse. Instead of applying to the case of the contractor breaking the contract and abandoning the work, the clause of the contract on which the said finding is based, is the usual one found in such contracts, which applies only to the case of the owner terminating the work of the contractor while the latter is going on with it, and entering upon the premises and superseding him and completing the work. In such a case the owner completes for the account of the contractor. Owners would bo in ovil case indeed if this clause applied when the contractor, after breaking the contract by substituting inferior work and material for that contracted for, or altogether omitting work and material contracted for, abandons the work altogether, as is the case here; for they could not leave their property in its unfinished condition, and yet if they completed it they would have to do it as the agent of their contractor who had thus grievously wronged them. The idea that a contractor may by abandoning the work put the owner in the position of being obliged to complete as his agent or trustee, if he completes at all, and to account to him at the end, only needs to be stated to expose its absurdity. It could not have been intended by the court to decide such a thing in Van Clief v. Van Vechten (130 N. Y. 571), as is claimed. There the owner pleaded that he completed for the account of the contractor, which made an entirely different case to the present one.

Where the contractor breaks the contract and abandons the work, he is left without any cause of action whatever, for his right to recover depends on his performance of the contract; unless, of course, the owner has contracted with him that if he breaks the contract and abandons the work, the owner will complete for his account — if we can conceive of any sane owner malting such a contract. There is no such contract here. It is that if the architect certifies that the contractor fails to supply a sufficient number of workmen, or sufficient materials, or to prosecute the work with promptness and diligence, or fails in the performance of any agree[604]*604ment of the contract, the owner' may, after giving the contractor three days written notice, “ provide any such labor or materials ”, and deduct the cost thereof from any money then due or thereafter to become due to the Contractor under this contract ”, or (and this is the part applicable to the present case), if the architect shall certify that the foregoing “ refusal, neglect ol" failure is sufficient ground for such action, the Owner shall also be at liberty to terminate the employment of the Contractors for the said work and to enter upon the premises and take possession ” and complete, the contractor to be liable to the owner at the end for any excess the owner has paid over the contract price, and the owner to be liable to the contractor for the balance of the contract price if it be not all expended. In the present case the owner never elected to terminate ” the contract and take possession and complete. It was already terminated by the contractor.

The fact that there are lienors under the contract does not enter into the question. Their case may be hard, but courts have to heed the adage, often verified, that hard cases make bad law.

The judgment should be modified by reducing the amount found to be due to the sum of $284.10 found to be due for extra work and material.

Hooker and High, JJ., concurred ; Miller,-J., read for affirmance, with whom Woodward, J., concurred.

Miller, J.:

The defendant owner proved and the court found that after the plaintiff abandoned the contract the owner completed the building according to the plans and specifications and that the cost of completion plus the payments theretofore made, deducted from the contract price, left a balance of $2,163.95. The defendants McKenna and Wood furnished material of the value of $1,254.44, which is now in the owner’s building and for which they have not been paid.

Though the complaint was for the value of the work done up to the time the contractor stopped work, the question of performance up to that time was not the only issue litigated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ogden v. . Alexander
35 N.E. 638 (New York Court of Appeals, 1893)
Graf v. . Cunningham
16 N.E. 551 (New York Court of Appeals, 1888)
Van Clief v. . Van Vechten
29 N.E. 1017 (New York Court of Appeals, 1892)
Wheeler v. . Scofield
67 N.Y. 311 (New York Court of Appeals, 1876)
Rowe v. Gerry
112 A.D. 358 (Appellate Division of the Supreme Court of New York, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
129 A.D. 600, 113 N.Y.S. 1071, 1908 N.Y. App. Div. LEXIS 1376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denison-construction-co-v-manneschmidt-nyappdiv-1908.