Denig, F. v. 501 Grandview, Inc.

Superior Court of Pennsylvania·Decided August 22, 2014·No. 1081 WDA 2013·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

FRED DENIG, JR., : IN THE SUPERIOR COURT OF : PENNSYLVANIA

Appellee :

:

v. :

:

501 GRANDVIEW, INC., A : PENNSYLVANIA CORPORATION, AND : 501 GRANDVIEW ASSOCIATES, LP, A : PENNSYLVANIA LIMITED : PARTNERSHIP, :

:

Appellants : No. 1081 WDA 2013

Appeal from the Judgment Entered June 6, 2013, In the Court of Common Pleas of Allegheny County, Civil Division, at No. G.D. 09-21205.

BEFORE: SHOGAN, OLSON and WECHT, JJ. MEMORANDUM BY SHOGAN, J.: FILED AUGUST 22, 2014 501 Grandview, Inc. and 501 Grandview Associates, LP (collectively,

-jury trial. We affirm.

Denig performed contract work as an architect for Grandview.

Pursuant to a contract dated March 28, 2006, Denig provided drawings and supervisory services for the construction of a five-story, eleven-unit,

prepare revisions, as well as additional drawings and plans. Denig

performed some of the additional work for which he was paid; he performed other portions of the additional work for which he was not paid. Eventually, Grandview and Denig ended their relationship. Grandview claimed the last day Denig furnished services under the contract was April 30, 2009. Denig maintained his last performance of contract work was a site visit on May 18,

$9,000.00 for contract administration.

Lien Claim, 11/16/09, at Exhibit C. Damages were based, in part, on two invoices: one dated March 31, 2009, for unpaid work totaling $8,710.00 (Trial Exhibit 30), and one dated April 30, 2009, for contract administration services totaling $9,000.00 (Trial Exhibit 31). According to an AIA application certificate (Trial Exhibit 32), Denig approved payment by the bank and agreed that construction had reached 35% as of April 30, 2009. However, through testimony at trial, Denig claimed an additional $1,000.00 for contract administration performed in April 2009 and disputed that the Project was only 35% complete as of April 30, 2009. Denig further testified that the Project was almost 50% complete at the time of his termination.

March 18, 2013, for $17,710.00. Grandview filed post-trial motions, which the trial court denied. Order, 6/3/13. Judgment was entered on June 6,

2013. Grandview timely appealed. Both Grandview and the trial court subsequently complied with Pa.R.A.P. 1925.

On appeal, Grandview presents the following issues for our consideration:

1. DID THE TRIAL COURT ERR IN FINDING THAT [DENIG] HAD COMPLETED 50% OF HIS CONTRACTED WORK?

2. DID THE TRIAL [COURT] DISREGARD CLEAR LAW AND EVIDENCE THAT [DENIG] HAD FAILED TO MEET THE CONDITIONS PRECEDENT IN THE WRITTEN AGREEMENT BETWEEN THE PARTIES?

1

Initially, we no brief differ from those raised in its Rule 1925(b) statement. Upon examination of the various issues, however, we conclude that the questions presented on appeal are fairly subsumed in the third error raised in

1

many parts as there are questions to be argued; and shall have at the head of each part--in distinctive type or in type distinctively displayed--the particular point treated therein, followed by such discussion and citation of

violates Rule 2119(a) in that it contains two questions but only one argument section. Nonetheless, because this violation does not hamper our

Grandview attempts to argue in its brief that the trial court improperly awarded damages for extra work beyond the scope of the contract. We agree with Denig that Grandview has waived this issue by failing to include it in its Statement of Questions Involved. See will be considered unless it is stated in the statement of questions involved

presented are inter-related, we shall address them in tandem.

Here, the trial court sat as the finder of fact. Appellate review in non-

jury cases implicates the following general principles:

Our appellate role in cases arising from non-jury trial verdicts is to determine whether the findings of the trial court are supported by competent evidence and whether the trial court committed error in any application of the law. The findings of fact of the trial judge must be given the same weight and effect on appeal as the verdict of a jury. We consider the evidence in a light most favorable to the verdict winner. We will reverse the trial court only if its findings of fact are not supported by competent evidence in the record or if its findings are premised on an error of law. However, [where] the issue...

concerns a question of law, our scope of review is plenary.

originating from a non-

duty to determine if the trial court correctly applied

Wyatt Inc. v. Citizens Bank of Pennsylvania, 976 A.2d 557, 564 (Pa. Super. 2009) (quoting Wilson v. Transp. Ins. Co., 889 A.2d 563, 568 (Pa. Super. 2005) (citations omitted)).

In the case at hand, we view the evidence in the light most favorable to Denig, the verdict winner. Stratford v. Boland, 452 A.2d 824, 826 (Pa. Super. 1982) (citation omitted). Moreover, we will not disturb the trial See Atlantic LB, Inc. v. Vrbicek, 905

of credibility and weight accorded the evidence at trial, we will not substitute

nt of all debts due by the owner to the contractor or by the contractor to any of his subcontractors for labor or materials furnished in the erection or construction, or the alteration or repair s definition of

implied, in addition to the preparation of drawings, specifications and contract documents also superintends or supervises any such erection, construction, alteration We have explained that:

lien to amounts owed for labor and materials only. The

and materials allowing the contractor to obtain a lien interest in the property Matternas v. Stehman, 434 Pa.Super. 255, 642 A.2d 1120, 1124 (1994).

unliquidated damages for breach of contract. Alan Porter Lee, Inc. v. Du-Rite Products Co., 366 Pa. 548, 79 A.2d 218

to settle the contractual obligations of the parties. Matternas, supra. See also TCI Const. Corp. v. Gangitano, 403 Pa.Super. 621, 589 A.2d 1135, 1137 (1991) (housing and

feeding of employees, in addition to costs of equipment, labor and materials, were costs that were incurred solely for the particular project and were necessary for the work to go forward

not an attempt to recover unliquidated damages for breach of contract); Halowich v. Amminiti, 190 Pa.Super. 314, 154 A.2d stained only for work done or materials furnished and not for unliquidated damages for breach of contract).

remedy in favor of a unique class of creditors and the liens are thus generally reviewed with a strict construction of the statute that created them. Sampson-Miller Assoc. Companies v.

Landmark Realty Co., 224 Pa.Super. 25, 303 A.2d 43 (1973).

be resolved in favor of a strict, narrow construction. Denlinger v. Agresta, 714 A.2d 1048 (Pa.Super.1998).

Artsmith Development Group, Inc. v. Updegraff, 868 A.2d 495, 496 497 (Pa. Super. 2005).

Grandview challenges the award of contract administration fees totaling $10,000.00 to Denig. Grandview argues that 50% completion of the Project was a condition precedent to Denig receiving one-half of his contract administration fees. According to Grandview, because Denig submitted an application certificate for payment (Trial Exhibit 32) that indicated the Project was 35% complete as of April 30, 2009, he did not fulfill the condition precedent and, consequently, was not entitled to payment for

complains, the trial court erred in finding that Denig was entitled to contract

In response, Denig argues that he completed contract administration services valued at $10,000.00, which he was entitled to receive from Grandvie administration provision refers to when Denig would bill for those fees; it was not a condition precedent to receipt of the contract administration fees. Id. at 7.

The contract language regarding contract administration appears in the context of billing for fees:

Free access — add to your briefcase to read the full text and ask questions with AI

Denig, F. v. 501 Grandview, Inc., (Pa. Ct. App. 2014).

Denig, F. v. 501 Grandview, Inc. (Denig, F. v. 501 Grandview, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stratford v. Boland
452 A.2d 824 (Superior Court of Pennsylvania, 1982)
Matternas v. Stehman
642 A.2d 1120 (Superior Court of Pennsylvania, 1994)
Wyatt Inc. v. CITIZENS BANK OF PA
976 A.2d 557 (Superior Court of Pennsylvania, 2009)
TCI Construction Corp. v. Gangitano
589 A.2d 1135 (Superior Court of Pennsylvania, 1991)
Denlinger, Inc. v. Agresta
714 A.2d 1048 (Superior Court of Pennsylvania, 1998)
Artsmith Development Group, Inc. v. Updegraff
868 A.2d 495 (Superior Court of Pennsylvania, 2005)
Wilson v. Transport Ins. Co.
889 A.2d 563 (Superior Court of Pennsylvania, 2005)
Alan Porter Lee, Inc. v. Du-Rite Products Co.
79 A.2d 218 (Supreme Court of Pennsylvania, 1951)
Halowich v. Amminiti
154 A.2d 406 (Superior Court of Pennsylvania, 1959)
Sampson-Miller Associated Companies v. Landmark Realty Co.
303 A.2d 43 (Superior Court of Pennsylvania, 1973)