Denbury Onshore, Llc and Denbury Resources Inc. N/K/A Denbury Inc. v. Apmtg Helium Llc

2020 WY 146, 476 P.3d 1098
CourtWyoming Supreme Court
DecidedDecember 4, 2020
DocketS-19-0172
StatusPublished
Cited by8 cases

This text of 2020 WY 146 (Denbury Onshore, Llc and Denbury Resources Inc. N/K/A Denbury Inc. v. Apmtg Helium Llc) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denbury Onshore, Llc and Denbury Resources Inc. N/K/A Denbury Inc. v. Apmtg Helium Llc, 2020 WY 146, 476 P.3d 1098 (Wyo. 2020).

Opinion

IN THE SUPREME COURT, STATE OF WYOMING

2020 WY 146

OCTOBER TERM, A.D. 2020

December 4, 2020

DENBURY ONSHORE, LLC and DENBURY RESOURCES INC. n/k/a DENBURY INC.

Appellants (Defendants), S-19-0172 v.

APMTG HELIUM LLC,

Appellee (Plaintiff).

Appeal from the District Court of Sublette County The Honorable Marvin L. Tyler, Judge

Representing Appellant: Darin B. Scheer, James R. Belcher, and Casey R. Terrell of Crowley Fleck PLLP, Casper, Wyoming. Argument by Mr. Scheer.

Representing Appellee: Scott P. Klosterman and Amy M. Iberlin of Williams, Porter, Day, and Neville, P.C., Casper, Wyoming; Jason A. Neville of the Spence Law Firm, LLC, Casper, Wyoming. Argument by Mr. Neville.

Before DAVIS, C.J., and FOX, KAUTZ, GRAY, JJ, and FENN, DJ.

NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third. Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building, Cheyenne, Wyoming 82002, of typographical or other formal errors so correction may be made before final publication in the permanent volume. KAUTZ, Justice.

[¶1] Denbury Onshore, LLC (Denbury), a subsidiary of Denbury Resources Inc., agreed to deliver certain amounts of helium to APMTG Helium LLC (APMTG) each year. Denbury failed to deliver the agreed-upon amounts but claimed its nonperformance was excused by two force majeure events—the failure of its contractor to complete its natural gas processing plant and the ongoing failure of its supply wells due to sulfur deposition plugging the wellbores. After a bench trial, the district court found Denbury had failed to show its non-performance was excused by a force majeure event except for a period of 36 days. It awarded APMTG over $35 million in damages and interest. Denbury appealed. We affirm.

ISSUES

[¶2] We restate and reorder Denbury’s issues as follows:

1. Did the district court err by denying Denbury’s request to terminate the parties’ agreement under the doctrines of frustration of purpose and/or impossibility of performance?

2. Did the district court err in deciding Denbury had failed to prove its non- performance between April 23, 2013, and December 30, 2013, was excused by a force majeure event (Contractor Failure FM)?

3. Did the district court err in deciding Denbury had failed to prove its non- performance after mid-August of 2014 was excused by a force majeure event (Well Failure FM)?

FACTS

Original Helium Feedgas Agreement (HFA I)

[¶3] On January 30, 2009, APMTG, a joint venture between Air Products and Chemicals, Inc. (Air Products) and Matheson Tri-Gas, Inc. (Matheson), entered into a Helium Feedgas Agreement (HFA I) with Cimarex Energy Co. (Cimarex) and Riley Ridge, LLC (Riley Ridge). Under the agreement, Cimarex and Riley Ridge agreed to design, construct, and operate a natural gas processing plant (the Riley Ridge Plant or Plant) and to annually deliver specified quantities of helium to APMTG.1 APMTG, in turn, agreed to design, construct and operate its own gas processing plant and to purchase the specified quantities of helium from Cimarex and Riley Ridge. The HFA I required Cimarex and Riley Ridge

1 The parties’ agreements refer to “helium feedgas” and “contained helium.” We will simply refer to helium. 1 to deliver 200 million standard cubic feet (MMscf) of helium to APMTG the first and second years of the contract and 400 MMscf per year thereafter. Cimarex and Riley Ridge agreed to expand the Riley Ridge Plant on or before the start of the third year in order to meet their increased obligations. If they failed to deliver the required quantities in any given year, they were to pay APMTG liquidated damages pursuant to a designated formula. The liquidated damages were capped at $8 million per year, and total liquidated damages for the life of the contract could not exceed APMTG’s final investment to construct its plant, which APMTG predicted would be $38.6-$42.9 million.

[¶4] The HFA I “estimated” that Cimarex and Riley Ridge would begin delivering helium to APMTG on December 1, 2010, but required delivery to begin no later than December 1, 2011, absent “delays caused by any Force Majeure” or unless the parties otherwise agreed in writing. The life of the agreement was 20 years.

[¶5] Section 17 of the HFA I excused a party’s failure to perform its obligations under the agreement “to the extent that such failure is caused by Force Majeure.” “Force Majeure” was defined in § 17.1 as

any event outside the reasonable control of a Party that could not have been avoided or overcome by that Party’s exercise of reasonable care and due diligence and shall include without limitation the following: strike, lockout, concerted act of workers or other industrial disturbance; fire, explosion, flood, blizzard, extreme weather conditions or other natural catastrophe; epidemic or pandemic; civil disturbance, riot or armed conflict (whether declared or undeclared); acts of terrorism; curtailment, shortage, rationing or allocation of normal sources of supply of labor, materials, transportation, energy or utilities; accident; act of God; delay(s) or failure of performance of contractor(s) (of any tier) or vendor(s); sufferance of or voluntary compliance with act of government and government regulations and/or orders (whether or not valid); cancellation by the U.S. Bureau of Land Management, Department of the Interior, of the “Contract for Extraction and Sale of Federal Helium”; embargo; natural or mechanical supply well failure (in whole or in part) and machinery or equipment breakdown. Notwithstanding anything herein to the contrary, the following events shall not be considered Force Majeure events: the concentration of helium contained in the Helium Feedgas below that defined in Clause 9.1; and loss of markets for natural gas or Helium.

2 (Emphasis added). Section 17.3 of the HFA I required the party “whose performance under this Agreement is affected by Force Majeure [to] promptly Notify the other Party of the occurrence, and the effect and likely duration of the Force Majeure event, and . . . keep the other Party informed of any changes to those circumstances.” Section 17.4 required the party claiming force majeure to “as soon as practicable after the commencement of the Force Majeure, proceed with diligence and do all things reasonably practicable at its own cost to overcome and/or remedy the situation, and to recommence performance of its obligations, provided that . . . neither Party shall be required to incur any extraordinary costs or make more than commercially reasonable investments.”

Failure of Contractor Force Majeure

[¶6] Cimarex was the majority owner and operator of the Riley Ridge Plant project; Riley Ridge owned only a minority interest in the project. As operator, Cimarex made the day-to-day decisions about how to run the project. It hired BCCK Engineering Incorporated (BCCK) pursuant to a turn-key contract to engineer, design and construct the Riley Ridge Plant in Big Piney, Wyoming, and bring it to “mechanical completion,” which was expected to occur by December 2011.

[¶7] In July 2010, Denbury purchased Riley Ridge’s interests in the Riley Ridge Plant and assumed all of its rights and obligations under the HFA I. About a year later, in June 2011, Denbury acquired Cimarex’s interests in the Plant and the HFA I, as well as Cimarex’s rights and obligations under the construction contract with BCCK. Two months later, on August 1, 2011, Denbury officially took over as operator of the Riley Ridge Plant project from Cimarex, which meant it began making the day-to-day decisions about how to run the Plant and Cimarex’s employees became Denbury’s employees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janet G. Peterson v. Meritain Health, Inc.
2022 WY 54 (Wyoming Supreme Court, 2022)
In the Interest of Asm: Asm v. The State of Wyoming
2021 WY 109 (Wyoming Supreme Court, 2021)
Brendon A. Boyce v. Julie A. Jarvis, f/k/a Julie A. Boyce
2021 WY 80 (Wyoming Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2020 WY 146, 476 P.3d 1098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denbury-onshore-llc-and-denbury-resources-inc-nka-denbury-inc-v-apmtg-wyo-2020.