Denapoli v. Hart

103 N.E.3d 772, 93 Mass. App. Ct. 1107
CourtMassachusetts Appeals Court
DecidedApril 23, 2018
Docket17–P–868
StatusPublished

This text of 103 N.E.3d 772 (Denapoli v. Hart) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denapoli v. Hart, 103 N.E.3d 772, 93 Mass. App. Ct. 1107 (Mass. Ct. App. 2018).

Opinion

Following a bench trial, a Superior Court judge found for the plaintiffs on their claim of breach of contract against the defendants and awarded the plaintiffs $139,707.08 in damages, which the judge then doubled due to the defendants' violation of G. L. c. 93A. The defendants appeal on several grounds. We affirm.

Background. We summarize the facts pertinent to this appeal, as found by the trial judge. In 2010, the plaintiffs entered into written agreements with the defendants, under the terms of which the defendants were to enlarge and renovate the plaintiffs' kitchen and construct a barn on their property. The parties entered into two separate agreements, one for the renovation of the kitchen, and one for the kitchen addition and barn construction. The cost of the kitchen renovation was $48,337.50, and the cost of the kitchen addition and barn construction was $296,179.14. Each agreement included scheduled payment dates and stated that the work would be completed "in a workmanlike manner." This appeal concerns only the agreement for the kitchen addition and barn construction project (the project).

The project was scheduled to begin on July 1, 2010, and be completed by November 15, 2010. The work was delayed, "primarily and substantially [because of] a lack of manpower and supervision at the site." As the project encountered delays that left it uncompleted through the summer of 2011, several defects in the work presented themselves. In response, and because the defendants stopped communicating with the plaintiffs and the work was not being done on the house, the plaintiffs contacted another contractor, Sean DiCataldo, to inspect the project. The town building inspector, an architect, and two engineers all also inspected the project, and each agreed that the construction of the barn deviated from the building plan and that multiple aspects of the construction were done "in a substandard manner."

As a result, the plaintiffs sent the defendants a demand letter pursuant to G. L. c. 93A on September 1, 2011, alleging violations of both c. 93A, and G. L. c. 142A (governing regulation of home improvement contractors). The plaintiffs demanded the return of all funds they had paid the defendants plus additional damages. Specifically, the plaintiffs' demand letter accused the defendants of abandoning the project, cited the defendants' ongoing lack of communication with the plaintiffs, and noted several structural and aesthetic defects in the work. Defendant Clarence Hart, on behalf of all the defendants, responded by claiming they had not abandoned the project and that they were awaiting the plaintiffs' response on options for portions of the project before progressing. He further offered to remedy a defective portion of the project and stated that the project was nearly complete, that they were willing and able to complete the project, and that they were owed $50,000 for past services and materials.

The plaintiffs terminated the defendants and hired DiCataldo to complete the project. The complaint against the defendants was filed in the Superior Court on November 23, 2011, and the case ultimately proceeded to a bench trial. Regarding the plaintiffs' claims of breach of contract and negligence, the judge found for the plaintiffs and ordered the defendants to pay $139,707.08 in damages; the judge concluded that Hart was personally liable for the damages. The judge determined the measure of damages to be the cost to complete the project and correct mistakes made by the defendants less the amount left unpaid on the original contract. The judge further found for the plaintiffs on their claims of violation of G. L. c. 93A, specifically § 9, and violation of G. L. c. 142A, and he doubled the damages award. The judge awarded the plaintiffs reasonable attorney's fees and costs pursuant to c. 93A.

Discussion. The defendants advance several arguments on appeal: (1) the judge's finding that the plaintiffs suffered damages was an error of law; (2) Hart was incorrectly held personally liable for the damages because he had signed the agreement with the plaintiffs as an agent for Lewis and Weldon Custom Builders; (3) the plaintiffs' demand letter was deficient under G. L. c. 93A; (4) the judge made erroneous factual findings which gave rise to the double damages under G. L. c. 93A; (5) the judge erred in determining the barn construction was covered by G. L. c. 142A; (6) the judge improperly found the defendants violated the implied covenant of good faith and fair dealing; and (7) the judge abused his discretion in denying the defendants' motion to enlarge the time for discovery.

Having reviewed the record and considered the defendants' arguments, we affirm.4

1. Standard of review. We briefly discuss our standards of review. For questions of law, we review de novo. U.S. Bank Natl. Assn. v. Schumacher, 467 Mass. 421, 427 (2014). We are bound by the judge's findings of fact so long as they are supported by the evidence and will only disturb the challenged findings if clearly erroneous to the extent that we are "left with the definite and firm conviction that a mistake has been committed" after considering the record. White v. Hartigan, 464 Mass. 400, 414 (2013) (quotation omitted). Finally, the judge's denial of the defendant's motion to enlarge the discovery period is reviewed for an abuse of discretion, where we address whether the judge made a "clear error of judgment in weighing the factors relevant to the decision ... such that the decision falls outside the range of reasonable alternatives." L.L. v. Commonwealth, 470 Mass. 169, 185 n.27 (2014) (quotation omitted).

2. Questions of law. We first address the defendants' asserted errors of law. The defendants contend that the plaintiffs' G. L. c. 93A demand letter was fatally noncompliant with the statutory requirements. At issue is the reasonableness requirement for demand letters, which calls for the plaintiffs to provide "a written demand for relief, identifying the claimant and reasonably describing the unfair or deceptive act or practice relied upon and the injury suffered." G. L. c. 93A, § 9(3).

In their demand letter, the plaintiffs described the grounds for their claims and requested the defendants return "all the monies [the plaintiffs] have paid you to date, together with compensation for their damages so that they can complete the project, correcting all the defects, re-building it in compliance with state codes, and completing it in its entirety as originally envisioned." That would have amounted to a $387,444 refund, in addition to remedial damages, and the judge noted that "demand for a full refund of the contract price was excessive" before awarding $139,707.08 in damages.

The question before us then is whether a demand letter with an "excessive" request for relief violates the reasonableness requirement of G. L. c. 93A, § 9(3). "The purposes of the [demand] letter are twofold: (1) to encourage negotiation and settlement by notifying prospective defendants of claims arising from allegedly unlawful conduct and (2) to operate as a control on the amount of damages which the complainant can ultimately recover." Spring v. Geriatric Authy. of Holyoke, 394 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

York v. Sullivan
338 N.E.2d 341 (Massachusetts Supreme Judicial Court, 1975)
Solimene v. B. GRAUEL & CO., KG
507 N.E.2d 662 (Massachusetts Supreme Judicial Court, 1987)
ATLANTIC SALMON A/S v. Curran
591 N.E.2d 206 (Massachusetts Appeals Court, 1992)
Commonwealth v. Domanski
123 N.E.2d 368 (Massachusetts Supreme Judicial Court, 1954)
Anthony's Pier Four, Inc. v. HBC ASSOCIATES
583 N.E.2d 806 (Massachusetts Supreme Judicial Court, 1991)
Spring v. Geriatric Authority of Holyoke
475 N.E.2d 727 (Massachusetts Supreme Judicial Court, 1985)
Yorke Management v. Castro
546 N.E.2d 342 (Massachusetts Supreme Judicial Court, 1989)
L.L., a juvenile v. Commonwealth
20 N.E.3d 930 (Massachusetts Supreme Judicial Court, 2014)
Ladd v. Scudder Kemper Investments, Inc.
741 N.E.2d 47 (Massachusetts Supreme Judicial Court, 2001)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
White v. Hartigan
464 Mass. 400 (Massachusetts Supreme Judicial Court, 2013)
Klairmont v. Gainsboro Restaurant, Inc.
465 Mass. 165 (Massachusetts Supreme Judicial Court, 2013)
U.S. Bank National Ass'n v. Schumacher
467 Mass. 421 (Massachusetts Supreme Judicial Court, 2014)
Selmark Associates, Inc. v. Ehrlich
467 Mass. 525 (Massachusetts Supreme Judicial Court, 2014)
Fredericks v. Rosenblatt
667 N.E.2d 287 (Massachusetts Appeals Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
103 N.E.3d 772, 93 Mass. App. Ct. 1107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denapoli-v-hart-massappct-2018.