Dempsey v. Schawacker

41 S.W. 1100, 140 Mo. 680, 1897 Mo. LEXIS 271
CourtSupreme Court of Missouri
DecidedJuly 17, 1897
StatusPublished
Cited by10 cases

This text of 41 S.W. 1100 (Dempsey v. Schawacker) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dempsey v. Schawacker, 41 S.W. 1100, 140 Mo. 680, 1897 Mo. LEXIS 271 (Mo. 1897).

Opinions

Macfarlane, J.

This is an action on a quantum meruit for work done and materials furnished in the construction by plaintiffs for defendant, of a livery stable in the city of St. Louis, and for a mechanics’ lien on the property for $2,748.12, the balance claimed to be due.

Defendant pleaded a special contract under which plaintiff undertook to furnish the material and construct the building in question for the sum of $8,369, and charges an abandonment of the work without cause before completion, and asked judgment for $3,267 as damages for breach of the contract. He also sets up a counterclaim for $3,267, the amount he charges he was [684]*684required to pay above the contract price, to complete the building. He also pleads the payment of a number of mechanics’ liens held by subcontractors and material men against plaintiffs as contractors, and the property of defendant.

Plaintiff by reply denies the voluntary abandonment of the contract, but charges that they y^ere unable to perform it on account of the continued interference by defendant with the work and their employees, and on account of the failure and refusal of defendant to pay stipulated sums as they became due.

The case was sent to a referee who took the evidence and reported to the court his conclusions of law and fact.. After carefully considering each controverted item in the accounts of the parties and passing upon them separately, the referee made the following summary of his conclusions:

RECAPITULATION.
Finding for plaintiff's work covered by contract.. *... $9,285 80
For extra work. 468 97
Total.$9,754 77
FINDINGS FOR DEFENDANTS.
Amount paid plaintiffs or their orders during progress of work.$ 5,722 19
Amount paid subcontractors’ judgments. 3,462 77
Amount paid to finish work. 1,986 41
Attorney’s fee. 300 00
Total.$11,471 37
‘‘Inasmuch, however, as I have found that plaintiffs were not justified in abandoning the work, they can not recover beyond the contract price, which is $8,369.”

By allowing them the contract price, plus extras, and charging them with payments made to them, to satisfy the subcontractors’ judgments, and what it cost [685]*685to finish the building, and attorney’s fees in McLaughlin ease, the true state of the account is arrived at as follows:

FINAL FINDINGS FOR PLAINTIFFS.
Dor work done under contract price.. $8,369 00
Dor extra work... 468 97
Total.$8,837 97
FINDINGS FOR DEFENDANTS.
Paid to plaintiff’s order.$ 5,722 19
Subcontractors’ judgments . 3,462 77
To finish building.,. 1,986 41
Attorney’s fee. 800 00
Total.$11,471 37
Add interest on judgments as found, ante. 1,008 84
Total. $12,480 21
Excess allowed defondant. 3,642 34
“I accordingly recommend that judgment be entered in favor of defendant for the sum of three thousand, six hundred and forty-two dollars and thirty-four cents ($3,642.34), with interest from November 20, 1893, at six (6) per cent and costs.”

Exceptions to the report, covering nearly every special finding of the referee, and controverting the conclusions reached, were filed by plaintiffs. These were considered by the court and overruled, the report was thereupon approved and judgment rendered in accordance therewith. Plaintiffs appeal.-

I; Plaintiffs make serious complaint to the finding of the referee that they were not justified in abandoning the work from any interference, or other act or omission on the part of the defendant, yet they do not claim that the finding in that particular was not supported by substantial evidence. A large part of the brief of counsel is devoted to a consideration of questions of fact.

[686]*686The report of the referee shows a very fair and thorough consideration of the case made, and all his conclusions of fact are well sustained by the evidence. The report, and the findings of fact clearly stated therein, were reviewed by the circuit court upon the most explicit exceptions thereto made by plaintiffs, and the report was approved and confirmed.

The conclusions of a referee on questions of fact in law cases, and the confirmation thereof by the circuit court, stand in the nature of special findings, and if supported by substantial evidence will not be reviewed on appeal. Frans v. Dictrick, 49 Mo. 95; Berthold v. O’Hara, 121 Mo. 88.

It is true the referee considered, separately, each act of alleged interference with the work on the part of defendant, and found it insufficient to authorize an abandonment, but did not expressly sum up their united effect, that is, whether all taken together were .sufficient, yet we must assume, from the general conclusion that “plaintiffs were not justified in abandoning the work/’ that the entire evidence was considered.

II. The referee finds that certain changes in the order of the work and in the specifications were insisted upon and required by defendant but that plaintiffs, at the time, made no objection to the changes and did not quit work on account of them. Plaintiff insists that evidence of a waiver was not admissible under the pleadings.

The question under the pleading is whether plaintiff had good cause to abandon the work. The ground for the abandonment is stated in the reply of plaintiff, which is the last pleading required or allowed by the code. Defendant is therefore entitled to introduce any competent evidence in rebuttal of that offered in support of the reply. We think it was competent, therefore, for defendant to prove that plaintiff consented, at [687]*687'the time, to the interferences complained of as grounds for quitting the work.

But the referee expressly finds that plaintiff abandoned the work for the reason that defendant refused to make payments for certain amounts claimed at the time to be due. We must take this finding of fact as conclusive upon us.

III. The contract provides for the payment of installments as the work progressed. The first and second, consisting of $2,800, were paid as they respectively became due. The third installment of $2,500 was overpaid by $422.14. The fourth installment was for $1,000, deducting from which the over-payment of the third left $577.86 due. This balance defendant refused to pay. The last installment of $2,069 is made payable under the contract on the. completion of the work.

Plaintiffs gave a bond for the faithful performance of the contract and for the payment of all mechanics’ liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Henke Const. Co.
157 F.2d 13 (Eighth Circuit, 1946)
Laughlin v. Boatmen's National Bank
189 S.W.2d 974 (Supreme Court of Missouri, 1945)
Stentor Electric Mfg. Co. v. Klaxon Co.
30 F. Supp. 425 (D. Delaware, 1939)
Baker v. Keller
198 P. 1014 (California Court of Appeal, 1921)
Spencer v. Collins
104 P. 320 (California Supreme Court, 1909)
Freygang v. Vera Cruz & P. R.
154 F. 640 (Fourth Circuit, 1907)
Citizens National Bank v. Donnell
94 S.W. 516 (Supreme Court of Missouri, 1906)
Central Bank v. Thayer
82 S.W. 142 (Supreme Court of Missouri, 1904)
Ryans v. Hospes
67 S.W. 285 (Supreme Court of Missouri, 1902)
Laycock v. Parker
79 N.W. 327 (Wisconsin Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
41 S.W. 1100, 140 Mo. 680, 1897 Mo. LEXIS 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dempsey-v-schawacker-mo-1897.