Deltic Timber Corp. v. Great Lakes Chemical Corp.

2 F. Supp. 2d 1192
District Court, W.D. Arkansas·Decided April 3, 1998·No. Civil No. 95-1090·Published·Cited by 2 cases

Opinion

MEMORANDUM OPINION

BARNES, District Judge.

This lawsuit was filed by Deltic Timber Corporation (Deltic) on November 3, 1995. In essence, the complaint alleges unlawful taking and displacement by Great Lakes Chemical Corporation (Great Lakes) of bromine-rich brine from Deltic properties, and compensation is sought on grounds of trespass, conversion, and unjust enrichment (quasi-contract) and restitution.1 Following the commencement of this action, portions of the brine rights claimed by Deltic were purchased by its former parent company, Murphy Oil Co., Inc., as well as Murphy Exploration & Production, (hereinafter, jointly referred to as Murphy). Murphy was therefore added as a plaintiff to this case by the second amended complaint.

A trial of this matter was held on December 3-10, 1997, and at the conclusion of testimony the Court took the case under advisement. Post-trial briefs were submitted by both sides. This Court has carefully considered the testimony and exhibits introduced at trial, and the following constitutes the Court’s findings of fact and conclusions of law.

I. BACKGROUND

Great Lakes is a diversified specialty chemicals company which manufactures various chemicals and products utilizing bromine. The Smackover Lime Formation, found in Union and Columbia Counties in South Arkansas, contains substantial reserves of valuable bromine-rich brine. This brine is commonly extracted through a method using two (2) types of wells. Production wells remove the bromine-rich brine from the Smackover Formation, and “disposal” or “injection” wells return the brine back into the formation after the bromine has been extracted.

Both parties acknowledged that injection wells are used not only as a means of disposing of that brine which has been processed of its bromine (“spent brine”), but also as a means of enhancing recovery of the bromine-rich brine underground (“virgin brine”). Through the strategic placement of injection wells, virgin brine is pushed ahead by injected, spent brine towards production wells. This process, known as “secondary recovery” or “waterflooding,” results in the production of more virgin brine than would be realized through production wells alone (“production by depletion”). The operation continues until the spent brine reaches production wells, thereby diluting the virgin brine to such an extent that production is no longer economically feasible.

In this instance, Great Lakes placed its wells in a “modified line drive.” Injection wells were placed in an imperfect horizontal line in order to. displace virgin brine towards a roughly parallel line of producing wells to the north. However, as noted by the testimony of Dr. William Cobb and other reservoir engineers, injection wells inject brine in all directions.2 Thus, when Great Lakes ex[1195]*1195panded its area of operations by adding production wells to the south of its injection wells in 1994 and 1995, brine was displaced towards producing wells both to the north and south of Great Lakes’s line of injection wells. This southward expansion brought Plaintiffs lands into the area between Great Lakes’s injection and production wells (the “recycling area”). Plaintiffs seek recovery for any virgin brine taken from these lands, as well as for brine taken from lands lying outside of, but adjacent to, the recycling area.

II. DISCUSSION

This case marks the fourth time in which suit has been brought by a plaintiff alleging that the bromine-rich brine underneath its lands have been affected by the recovery operations of a brine producer. The resulting case law in this area has been dynamic.

In Budd v. Ethyl Corp., 251 Ark. 639, 474 S.W.2d 411 (1971), the Arkansas Supreme Court was faced with a plaintiff alleging damages to two separate tracts of land. As to virgin brine allegedly drained from lands lying outside of, but adjacent to, an area bounded by injection wells, the Court held that the law of capture denied recovery. Budd at 412 (citing Osborn v. Ark Territorial Oil & Gas Co., 103 Ark. 175, 146 S.W. 122 (1912)). In doing so, the Court noted that the law of capture had not been “comnullified by the statute which permits the Oil and Gas Commission to bring about compulsory unitization in oil and gas fields.” Budd, 474 S.W.2d at 413. The Court applied a different analysis to lands lying within the recycling area, however, and denied recovery on the basis of an inadequate interest in the brine allegedly drained. Id. at 412-413 (noting the ownership of merely a leasehold interest).

In Young v. Ethyl Corp. 521 F.2d 771 (8th Cir.1975) (hereinafter Young I), the Eighth Circuit applied Arkansas law to allow recovery for brine displaced from a tract of land located within a brine producer’s recycling area. The Court noted the separate analysis afforded such lands in Budd, supra, and held that the law of capture was inapplicable because: (1) the plaintiffs virgin brine would not have been displaced but for the increase in pressure supplied by the producer’s injection wells; and (2) using a waterflood process to force minerals under one’s neighbor’s lands to migrate to production wells when they would not have otherwise done so amounts to an abuse of correlative rights. Young I at 774.

This holding was later adopted by the Arkansas Supreme Court in Jameson v. Ethyl Corp., 271 Ark. 621, 609 S.W.2d 346 (1980). In refusing to extend the law of capture to brine displaced through secondary recovery processes, the Jameson court noted that such processes were “obviously necessary” for the efficient, maximum recovery of bromine-rich brine. Jameson, 609 S.W.2d at 349. However, the Court pointed out that some balance was needed between the continued production of a valuable natural resource and the effect of waterflooding upon the brine rights of neighboring landowners. Seizing upon the rationale of Young I, supra, as well as recently enacted Arkansas legislation providing for the unitization of brine fields, the Court allowed damages for brine which would not have been displaced but for the producer’s injection wells. Id. at 351. Damages were not afforded for brine which would have been merely drained by the use of supply wells alone (“depletion”), rather than as a result of removal which “had occurred due to the added differential pressures.” Id. at 349.3

The ease at hand is the first to include allegations that a Plaintiffs brine rights were affected subsequent to the enactment of Act 937 of 1979. Ark.Code Ann. § 15-76-301 et seq. The Act, which establishes unitization procedures for brine production in an attempt to balance the interests of landowners and brine producers, was essential to the rule of law espoused in Jameson, supra. In resolving this matter, the Court has considered this legislation in addition to the aforementioned case law.

A. Brine Extracted From Lands Outside the Recycling Area

Free access — add to your briefcase to read the full text and ask questions with AI

Deltic Timber Corp. v. Great Lakes Chemical Corp., 2 F. Supp. 2d 1192 (W.D. Ark. 1998).

2 F. Supp. 2d 1192 (Deltic Timber Corp. v. Great Lakes Chemical Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Deltic Timber Corp. v. Great Lakes Chemical Corp.
2 F. Supp. 2d 1192 (W.D. Arkansas, 1998)