Delta Mining Corporation v. Big Rivers Electric Corporation

18 F.3d 1398, 1994 U.S. App. LEXIS 4813, 1994 WL 84153
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 17, 1994
Docket93-2070
StatusPublished
Cited by12 cases

This text of 18 F.3d 1398 (Delta Mining Corporation v. Big Rivers Electric Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delta Mining Corporation v. Big Rivers Electric Corporation, 18 F.3d 1398, 1994 U.S. App. LEXIS 4813, 1994 WL 84153 (7th Cir. 1994).

Opinion

*1400 COFFEY, Circuit Judge.

In January 1977, Big Rivers Electric Corporation (“Big Rivers”), a Kentucky electric-power generating cooperative, entered into a 10-year coal-supply contract with a local coal-mining corporation 1 which later merged with the plaintiff, Delta Mining Corporation (“Delta”), an Indiana coal-mining corporation. After the term of the contract had expired, Delta brought this suit alleging a breach of contract and seeking more than $18 million in damages from Big Rivers for its refusal to accept delivery of or pay for roughly % million tons of coal that Delta claimed remained to be shipped under the. contract. After a bench trial, the district court entered judgment in favor of Big Rivers. We affirm.

BACKGROUND

Delta argues that the contract obligated Big Rivers to accept a total of 3,138,000 tons of bituminous coal, although this amount is not specified in the contract. The plaintiff arrived at this figure by adding the tonnage figures listed in the table of scheduled monthly coal deliveries in Section 4 of the contract. The plaintiff established that its total deliveries to Big Rivers during the contract term were 669,957 tons short of the 3,138,000 tons of coal it contends it was entitled to ship. Delta identified three causes of these “undershipments”: (1) Big Rivers reduced its monthly coal requirements by ten percent from 1981 through 1986; (2) both parties invoked the contract’s force majeure clause 2 to suspend certain monthly shipments; and, (3) Delta, especially during the early years of the contract, failed to ship the full amounts of coal it was scheduled to ship each month under, the contract. 3

Because the plaintiff believed the contract was ambiguous, it introduced evidence extrinsic to the contract in an effort to demonstrate that the agreement should be interpreted as requiring Big Rivers to accept Delta’s offer to , “make up” all three categories of undershipments. The trial court determined that the contract was clear and unambiguous and refused to consider Delta’s extrinsic evidence and entered judgment in favor of the defendant Big Rivers.

ISSUES

Delta contends that the district court erred in refusing to find that the contract is ambiguous whether Delta had the right to “make up” (and be compensated for) the three categories of coal that it failed to deliver during the term of the contract: (1) the ten percent undershipments, (2) the force majeure under-shipments, and (3) the contractually unexcused undershipments (“deficiency under-shipments”).

DISCUSSION

The parties agreed to be bound by Kentucky law through application of the contract’s choice-of-law provision. Under Kentucky law, “an ambiguous contract is one capable of more than one different, reasonable interpretation.” Central Bank & Trust Co. v. Kincaid, 617 S.W.2d 32, 33 (Ky.1981). Before concluding that a contractual provision is ambiguous we must read it in light of the complete instrument. See City of Louisa v. Newland, 705 S.W.2d 916 (Ky.1986); International Union of Operating Engineers v. J.A. Jones Const. Co., 240 S.W.2d 49 (Ky.1951) (clause which appears ambiguous cannot be construed in isolation). Only if the trial court finds that the contract is ambigu *1401 ous may the court receive extrinsic evidence “in an effort to determine the intention of the parties.” Kincaid, 617 S.W.2d at 33.

A. The Ten Percent Monthly Adjustments

The parties agree that the following language from Section 4 of the contract gave Big Rivers the option, upon proper notice, of increasing or decreasing the amount of coal it would accept each month by ten percent from the monthly quantities stated in Section 4:

“4. Quantity. The quantities to be supplied by Seller and purchased by Buyer hereunder shall be as listed on the following table, subject to the adjustments provided in this Section_ [table of scheduled monthly tonnage omitted]
Buyer shall give Seller at least 60 days advance notice in writing of quantity requirements for each month, provided that in the absence of such notice Seller shall be required to deliver the monthly tonnage specified above. At time of such notification, Buyer may demand, and Seller shall furnish, as much as one hundred ten percent (110%) or as little as ninety percent (90%) of the monthly requirements listed above and such adjusted tonnage amounts unll become binding upon the Seller and the Buyer_
Monthly requirements, as adjusted in accordance with the terms of the preceding two paragraphs shall be termed Adjusted Monthly Requirements.
Seller shall distribute the shipment of each month’s quantity approximately evenly throughout the month.” (Emphasis' added.)

The plaintiff contends, however, that the above-quoted language does not clearly resolve the question of whether Delta has a right to “make up” any difference that might arise between the annual totals of scheduled monthly tonnage as listed in the contract and the amount of coal actually delivered pursuant to Big Rivers’ Adjusted Monthly Requirements. Delta in an effort to establish that the contract was ambiguous called a number of witnesses. One testified that although he had administered hundreds of coal-supply contracts, he found the above-quoted language in Section 4 “unusual” and “confusing.” Another testified that, based on his experience administering coal-supply contracts for other utilities, he was of the opinion that other utilities frequently enter into contracts in which their ability to make monthly adjustments does not alter their duty to purchase some fixed amount of coal over the term of the contract.

We begin our analysis by noting that the plain language of Section 4 quoted above explains that the contract’s scheduled monthly tonnage figures merely describe the quantity of coal “to be supplied by Seller and purchased by Buyer ... subject to the ad- . justments provided in this Section.” Among the “adjustments provided” is an option granted to the Buyer to reduce its scheduled monthly coal “requirements” by ten percent: “Buyer may demand, and Seller shall furnish ... as little as ninety percent (90%) of the monthly requirements listed [in an accompanying table] and such adjusted tonnage amounts will become binding upon the Seller and the Buyer.” (Emphasis added.)

We are at a loss to understand how Delta can argue that this language is unclear. To accept Delta’s contention that Section 4 is ambiguous would require us to hold that it is “capable of more than one different, reasonable interpretation.” Kincaid,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
18 F.3d 1398, 1994 U.S. App. LEXIS 4813, 1994 WL 84153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delta-mining-corporation-v-big-rivers-electric-corporation-ca7-1994.