Delaware Riverkeeper Network v. United States Army Corps of Engineers

869 F.3d 148, 2017 WL 3611780, 85 ERC (BNA) 1021, 2017 U.S. App. LEXIS 16102
CourtCourt of Appeals for the Third Circuit
DecidedAugust 23, 2017
Docket17-1506
StatusPublished
Cited by6 cases

This text of 869 F.3d 148 (Delaware Riverkeeper Network v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware Riverkeeper Network v. United States Army Corps of Engineers, 869 F.3d 148, 2017 WL 3611780, 85 ERC (BNA) 1021, 2017 U.S. App. LEXIS 16102 (3d Cir. 2017).

Opinion

OPINION OF THE COURT

SMITH, Chief Judge.

Tennessee Gas Pipeline Co. (“Tennessee Gas”) submitted applications to several federal and state agencies seeking approval to build an interstate pipeline project. One such agency is the United States Army Corps of Engineers, 1 which administers certain provisions of the Clean Water Act. The Corps issued a permit approving the project. The petitioners, Maya van Rossum and Delaware Riverkeeper Network (collectively, “Riverkeeper”), challenge that decision on the ground that the Corps acted arbitrarily and capriciously by rejecting a “compression” alternative.

We conclude that the Corps considered the compression alternative but rejected it for reasons supported by the record. While the compression alternative would disturb less land, its impact would be mostly permanent. The pipeline project would disturb more land, but its impact would be mostly temporary. In making a policy choice between those environmental tradeoffs, the agency’s discretion was at its apex. We will therefore deny the petition for review.

I

A

At issue is the Orion Project — 12.9 miles of pipeline looping 2 that would transport an additional 135,000 dekatherms per day of natural gas through Pennsylvania. Approximately 99.5% of the new pipeline would run alongside existing pipelines. According to Riverkeeper, construction will *152 lead to deforestation, destruction of wetland habitats, and other forms of environmental damage. Riverkeeper asserts that such damage can-be avoided by building or upgrading a compressor station, “Compressor stations ... us[e] gas- and electric-powered turbines to increase the pressure and rate of flow at given points along the pipeline’s route.” Del. Riverkeeper Network v. Sec’y Pa. Dep’t of Envtl. Prot., 833 F.3d 360, 369 (3d Cir. 2016). Building or upgrading a compressor station would increase the amount of natural gas transported through existing pipelines and thus avoid any need to build pipeline looping. 3

Contrary to Riverkeeper’s concerns, the agencies concluded that the Orion Project would result in “minimal”' and “temporary” environmental impact. Of the 12.9 miles of pipeline looping, fewer than 2 miles would cross wetlands or waterbodies. The pipeline would be buried 2-3 feet beneath the ground, and all disturbed areas would be restored to their original elevations and contours with no net loss of wetlands. However, nearly five acres of forested wetlands would be de-forested and converted into emergent wetlands. The compression alternative, by contrast, would require constructing one or more permanent fixtures — causing permanent' deforestation as well as light, air, sound, and greenhouse gas pollution.

With that initial background in mind, we next set forth a brief overview of the administrative scheme and then describe how that process unfolded in this case.

B

Under the Natural Gas Act of 1938, the Federal Energy Regulatory Commission (“FERC”) is the “lead agency” for evaluating interstate pipeline projects. 16 U.S.C. § 717n(b). As part of that role, FERC performs a technical environmental analysis pursuant to the National Environmental Policy Act (“NEPA”). Id.

NEPA requires FERC to take a “hard look” at the environmental impact of the proposed project'. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). If the project involves a “major Féderal action” that would “significantly affect[ ] the quality of the' human environment,” FERC must prepare a detailed Environmental Impact Statement. 42 U.S.C. § 4332(C). Otherwise, FERC need only prepare a concise Environmental Assessment. 40 C.F.R. §§ 1501.3,1501.4,1508.13.

' As a condition of FERC’s approval, the applicant is required to obtain any additional state or federal licenses required by law. For example, because the Orion Project would discharge “dredged or fill material” into the “waters of the • United States,” Tennessee Gas was required to obtain a permit under Section 404 of the Clean Water- Act. 33 U.S.C. §§ 1344(a), 1362(7).

The United States Army Corps of Engineers reviews applications for Section 404 permits. In doing so, the Corps applies the so-called Section 404 Guidelines (“the Guidelines”) issued by the Environmental Protection Agency. See 33 C.F.R. § 320.4. See generally Coeur Alaska, Inc. v. Se. Alaska Conservation Council, 557 U.S. 261, 129 S.Ct. 2458, 174 L.Ed.2d 193 (2009). Among other things, the Corps may not issue a permit where there is a “practicable alternative” with less adverse impact on the aquatic ecosystem, “so long as the *153 alternative does not have other significant adverse environmental consequences.” 40 C.F.R. § 230.10(a).

In performing its alternatives analysis, the Corps may rely on the environmental report prepared by FERC pursuant to NEPA, The agencies memorialized their cooperative relationship in a 2005 Memorandum of Understanding, which states that the Corps will “use the FERC record to the maximum extent practicable and as allowed by law.... [T]he Corps will give deference, to the maximum extent allowed by law, to the project purpose, project need, and project alternatives that FERC determines to be appropriate for the project.” JA 39. 4

o'..

1. Tennessee Gas’s application. On October 9, 2015, Tennessee Gas submitted an application to FERC for approval of the Orion Project. Its application included an Environmental Report, which discussed and rejected compression alternatives. Tennessee Gas explained that building compressor stations would require Tennessee Gas “to obtain approximately 40-acres per site (total of 80 acres).” JA 408. Building compressor stations would also require “permanent vegetation clearing from the area in order to install permanent access roads, fencing, buildings and other appurtenance equipment,” and would create “light pollution, and. noise impacts and may also become a source of [greenhouse gas] emissions.” Id. But with the Orion Project, “the new [right-of-way] will be allowed to re-vegetate to minimize and mitigate possible environmental impacts.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
869 F.3d 148, 2017 WL 3611780, 85 ERC (BNA) 1021, 2017 U.S. App. LEXIS 16102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-riverkeeper-network-v-united-states-army-corps-of-engineers-ca3-2017.