Del-AWARE Unlimited, Inc. v. Commonwealth, Department of Environmental Resources

508 A.2d 348, 96 Pa. Commw. 361, 1986 Pa. Commw. LEXIS 2103
CourtCommonwealth Court of Pennsylvania
DecidedApril 15, 1986
DocketAppeals, Nos. 2240 C.D. 1984, 2114 C.D. 1984 and 2072 C.D. 1984
StatusPublished
Cited by9 cases

This text of 508 A.2d 348 (Del-AWARE Unlimited, Inc. v. Commonwealth, Department of Environmental Resources) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Del-AWARE Unlimited, Inc. v. Commonwealth, Department of Environmental Resources, 508 A.2d 348, 96 Pa. Commw. 361, 1986 Pa. Commw. LEXIS 2103 (Pa. Ct. App. 1986).

Opinion

Opinion by

President Judge Crumlish, Jr.,

For our consideration and disposition herein are various challenges to the resolution by the Environmental Hearing Board (EHB) of disputes surrounding the permits required to construct facilities to supply water for cooling a nuclear generating station in Limerick, [364]*364Montgomery County, Pennsylvania, and meeting the citizens’ requirements of Bucks and Montgomery Counties.

Again, we recognize that this construction has inspired widespread public discussion and disagreement. See Sullivan v. County of Bucks, 92 Pa. Commonwealth Ct. 213, 499 A.2d 678 (1985). Nonetheless, we are obliged and intend to confine our consideration to the merits of the legal issues presented.

As we wrote in Sullivan, the purpose of the Point Pleasant water diversion project (project) is to construct a system by which Delaware River water could be withdrawn by the Point Pleasant Pumping Station (pumping station) and pumped through a combined transmission main to the Bradshaw Reservoir and Pump House where (1) water for public use by Bucks and Montgomery Counties would travel through the north branch transmission main, discharge into the North Branch Neshaminy Creek and flow along the creek to the north branch water treatment plant where it would be pumped, in part, to the North Penn (NP) and North Wales (NW) Water Authorities and (2) supplemental cooling water for the Limerick nuclear generating station, owned by the Philadelphia Electric Company (PECO), would be pumped through the east branch transmission main, discharge into the East Branch Perkiomen Creek and flow along the creek to the Perkiomen Pump House where it would be withdrawn and pumped to Limerick. Supplemental cooling water is necessary because PECO is denied access to Schuylkill River water for several months each year.1

[365]*365The Department of Environmental Resources (DER) granted all permits necessary to commence construction. Del-AWARE Unlimited, Inc. (Del-AWARE), appealed this decision to EHB. Friends of Branch Creek, Inc. (Friends of Branch Creek), then intervened.2 Although EHB upheld DERs decision in part, it remanded to DER requiring (1) National Pollutant Discharge Elimination System (NPDES) permits for diversion of water from the Delaware River into the North Branch Neshaminy and East Branch Perkiomen Creeks, (2) that the need for the project be balanced against the impact of erosion on the receiving streams if the velocities in the streams cannot be reduced to 2.0 feet per second (fps) and (3) that PECOs permit be conditioned on a cutoff when the water flows measured at the Bucks Road Gauge exceed 125 cubic feet per second (cfs).3

Our scope of review of an EHB decision is limited to a determination of whether an error of law has been committed, constitutional rights have been violated or any findings of feet are unsupported by substantial evidence. Einsig v. Pennsylvania Mines Corp., 69 Pa. Commonwealth Ct. 351, 452 A.2d 558 (1982).

No. 2240 C.D. 1984

Del-AWARE appeals that portion of the EHB order4 upholding DERs grant of various permits5 to PECO [366]*366and the Neshaminy Water Resources Authority (NWRA).

Del-AWARE first contends that EHB violated its constitutional due process right to a full, fair and impartial hearing6 by curtailing its presentation of evidence [367]*367on aesthetic impact, alternative water supplies and adverse environmental effects merely to insure the hearing examiners timely departure from the Board.7 It argues that the hearing examiner improperly excluded the direct testimony of seven of its witnesses.8 However, our review of the record reveals substantial evidence to support EHB’s conclusion that this proffered testimony was either cumulative, speculative or irrelevant and, therefore, had no likelihood of causing it to alter the findings of feet in its adjudication.9 We therefore hold [368]*368that EHB did not abuse its discretion by limiting DelAWAREs presentation of such evidence. 25 Pa. Code §21.90.10 See abo Geders v. United States, 425 U.S. 80 (1976) (trial judge may refuse to allow cumulative, repetitive or irrelevant testimony). It also argues that EHB improperly cut short the testimony of one of its rebuttal witnesses, excluded that of another and denied its oral and written motions for reopening and rebuttal. However, we hold that, in rejecting Del-AWAREs proffered rebuttal, EHB did not abuse its discretion by excluding this rebuttal evidence because it could have been presented during the case in chief. See Downey v. Weston, 451 Pa. 259, 301 A.2d 635 (1973).11

[369]*369Secondly, Del-AWARE contends that DER failed to adequately consider the pumping stations impact on the natural, scenic, historic and aesthetic features12 of the [370]*370Delaware Canal (canal)/Roosevelt State Park (park) and surrounding Point historic district (historic district).

Del-AWARE asserts that DER must explicitly find an “overriding public necessity” for allowing the intake pipeline to cross under the Commonwealth-owned canal.13 It argues that this was not done because DER (1) at most made an implicit finding of necessity, (2) incorrectly assumed that the conclusion that the canal must be crossed was inherent in its initial decision to approve the project and (3) foiled to inquire as to (a) alternative locations or (b) methods to minimize the pumping stations intrusiveness. We reject these arguments. The relevant statutes14 merely require that DER determine [371]*371that a service line is (1) necessary for public service and (2) at least reasonably required to cross Commonwealth land, before it grants a right-of-way through Commonwealth lands. Moreover, we discern nothing to indicate that DERs determination must take the form of an explicit finding. It appears from the record that (1) DER did not err by declining to consider alternative locations for the pipeline because, given the location of the property on which the pumping station would be built, there were no logical/feasible alternatives and (2) the initial approval of the project by DER necessarily involved a right-of-way across the canal. More conclusively, however, our review of the record reveals substantial evidence in support of EHB’s conclusion that DERs finding, that the intake pipeline was necessary and was reasonably required to cross Commonwealth land, was implicit in its decision to grant the right-of-way. Finally, we hold that EHB reasonably concluded that construction of the intake will not adversely affect the canal and that the right-of-way will involve minor patch-up work which would cause no permanent deleterious effect to Commonwealth land.15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hatchard v. Department of Environmental Resources
612 A.2d 621 (Commonwealth Court of Pennsylvania, 1992)
O'Connor v. Pennsylvania Public Utility Commission
582 A.2d 427 (Commonwealth Court of Pennsylvania, 1990)
Neshaminy Water Resources Authority v. 0.754 Acres of Land on Swauger Road
6 Pa. D. & C.4th 426 (Bucks County Court of Common Pleas, 1990)
Del-AWARE Unlimited, Inc. v. Commonwealth
551 A.2d 1117 (Commonwealth Court of Pennsylvania, 1988)
David v. Philadelphia Electric Co.
535 A.2d 729 (Commonwealth Court of Pennsylvania, 1988)
Del-AWARE Unlimited, Inc. v. Pennsylvania Public Utility Commission
513 A.2d 593 (Commonwealth Court of Pennsylvania, 1986)
DEL-AWARE UN., INC. v. PennDER.
508 A.2d 348 (Commonwealth Court of Pennsylvania, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
508 A.2d 348, 96 Pa. Commw. 361, 1986 Pa. Commw. LEXIS 2103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/del-aware-unlimited-inc-v-commonwealth-department-of-environmental-pacommwct-1986.