Decker Precision Machining, Inc. v. Go Grease It d/b/a G2It LLC

Court of Appeals of Iowa·Decided August 5, 2020·No. 19-0753·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 19-0753

Filed August 5, 2020

DECKER PRECISION MACHINING, INC., Plaintiff-Appellee,

vs.

GO GREASE IT d/b/a G2IT LLC, Defendant-Appellant.

Appeal from the Iowa District Court for Dubuque County, Michael J.

Shubatt, Judge.

A manufacturing start-up appeals from a district court decision that held it liable for breach of contract for failing to pay for custom parts. AFFIRMED.

Kenneth R. Munro of Munro Law Office, P.C., Des Moines, for appellant.

Todd J. Locher of Locher & Davis, PLC, Farley, for appellee.

Considered by Doyle, P.J., and Tabor and Schumacher, JJ.

SCHUMACHER, Judge.

This breach-of-contract case arises as a result of a dispute over parts supplied by a precision machining company to a manufacturing start-up for use in a prototype grease applicator. Central to the proposed device’s operation was a pneumatic system, characterized by a short cylindrical piston fitting tightly within a cylindrical tube. The fit of these two parts was critical to the functioning of the prototype applicator, but when the manufacturer’s hydraulic engineer received the finished parts, he discovered the piston did not fit the tube.

The manufacturer refused to pay for the entirety of the parts, highlighting the mismatched fit of the piston and tube. The manufacturer also alleged tardiness of delivery and various defects in other parts. The precision machining company sued for breach of contract and was awarded damages of $19,798.11 following a bench trial. The manufacturer appealed, arguing analytical flaws and inconsistent factual findings left the decision unsupported by substantial evidence. We affirm. Background and Procedural History Go Grease It (GGI) is a manufacturing start-up. In 2016, under the leadership of Mike Ryan, GGI sought to develop a new type of grease applicator that could transfer bulk lubricants, oils, and greases into reusable cartridges for use in various applications. GGI hired Cole Weber, a hydraulic engineer living in Minnesota, to spearhead the project. Wanting to build a prototype, Ryan and Weber contracted with Decker Precision Machining, Inc. (DPM) in the fall of 2016 for the production of parts for the applicator.1 Throughout the course of dealing,

1DPM had completed prototypes for GGI in 2015 using the same tubing supplied by GGI.

DPM was represented by Randy Decker and Marty Koppes in emails and telephone consultations. The parties began exchanging quotes and purchase orders on October 31, 2016, and DPM commenced the machining of parts. Production was slowed by the need for clarification on prints. The purchase orders sent by GGI typically contained a term requiring order completion within three to eight weeks. GGI put the project on hold at one point. In a January 30, 2017 email, Ryan relayed the following to Decker and Koppes: “Please do not expend any more effort on any of these parts[.] After my last phone call with Marty and being informed of your continuing work backlog and further delay in delivery I need to reassess my options for getting parts[.]”

However, despite this email, the relationship continued. According to Decker’s testimony, Ryan telephonically relayed to Decker on February 9, 2017, “Guess what? We’re going to go ahead and go with this project again. It’s not on hold. We’re going to go with it. I agree with your quotes. The problem is I need them in two weeks.” Decker replied that he could not deliver the parts in that time frame to which Ryan responded, “You will get them done. Just do your best.” A final purchase order was sent on February 9, 2017, which asserted that order completion was required between February 17 and February 21. To save on shipping costs, GGI requested that all parts ship at the same time. DPM sent all the parts in two shipments, totaling over one hundred parts of over forty different types. The parts were shipped to Indiana, where Weber had resided since February. They arrived on February 22, 2017, and February 27, 2017.

Weber testified that after receipt of the parts he learned that two critical parts did not fit together. Specifically, these parts were a short Delrin

(polyoxymethylene) black cylinder that would serve as a piston and an eleven-inch length of polycarbonate that would serve as a reservoir for bulk liquids. The piston was designed with grooves in its outer edge so O-rings could be affixed. With the O-rings attached, the piston would create a seal against the inner wall of the cylindrical reservoir and give life to a pneumatic system. The pressurization of this system was crucial to the device’s function, and the lack of fit was therefore fatal to the device’s proposed function.

In a February 24, 2017 email, Weber informed DPM of the lack of fit:

Randy & Marty, As Marty and I discussed on the phone, there is some discrepancy on the polycarbonate tubes that I am investigated [sic].

Either ID/OD tolerances are not met from the supplier or the concentricity is not good enough to fit these delrin top and bottom cap grooves.

Could you please quote me for turning down the ID of the reservoir piston and widening the grooves of the top and bottom caps of the 140 oz reservoir (qty 3 of each). Attached are the revised prints.

If I decide to go this route[,] I will send you the parts back with one of the polycarbonate tubes to ensure fit.

DPM did not receive further communication from GGI and did not receive the parts back. In a March 28, 2017, letter to DPM, Ryan alleged that DPM had breached its contract with GGI. The message calculated total damages to GGI of $71,306.00, which included claims for Weber’s and Ryan’s wages while waiting for the parts, overhead, lost patent life, lost time to market, and “[a]dditional costs to get working parts.” The damages calculation subtracted $21,567.78 for the “Decker Invoice” and listed a balance due to GGI of $49,738.22.

Negotiations over payment for the parts and GGI’s alleged damages proceeded no further. Weber discarded all the relevant parts sometime in June or July 2017 when he moved into a new house. GGI never paid for the parts.

DPM filed a petition in November 2017 seeking damages for breach of contract and open account. GGI responded with a counterclaim for the damages Ryan had outlined in the March 28 letter. GGI also raised the affirmative defense that DPM was in breach of contract was therefore barred from bringing an action for damages. The matter was heard at a bench trial on January 22, 2019.

The district court found that DPM proved it performed on the contract and that GGI breached. The court entered judgment in favor of DPM in the amount of $19,798.11 on the breach-of-contract claim. GGI’s counterclaim was denied and dismissed. GGI appealed the award to DPM. Standard of Review “When a district court’s ruling is challenged for lack of substantial evidence, we view the evidence in the light most favorable to the judgment.” Frank Millard & Co. v. Housewright Lumber Co., 588 N.W.2d 440, 441 (Iowa 1999) (citing Tim O’Neill Chevrolet, Inc. v. Forristall, 551 N.W.2d 611, 614 (Iowa 1996)).

The district court’s findings of fact have the effect of a jury verdict and are binding on us if supported by substantial evidence. Evidence is substantial when a reasonable mind would accept it as adequate to reach the same findings. Evidence is not insubstantial merely because it would have supported contrary inferences.

Hendricks v. Great Plains Supply Co., 609 N.W.2d 486, 490 (Iowa 2000) (citations omitted). “We will liberally construe the district court’s findings to uphold, rather than defeat, the result reached.” Frank Millard, 588 N.W.2d at 441.

Discussion On appeal, GGI argues the trial court’s decision is based on facts that are impossible and is therefore not supported by substantial evidence. GGI takes issue with the district court’s findings, which gave weight to Decker’s testimony despite the lack of fit between the parts that DPM machined and shipped to GGI.

Free access — add to your briefcase to read the full text and ask questions with AI

Decker Precision Machining, Inc. v. Go Grease It d/b/a G2It LLC, (iowactapp 2020).

Decker Precision Machining, Inc. v. Go Grease It d/b/a G2It LLC (Decker Precision Machining, Inc. v. Go Grease It d/b/a G2It LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tim O'Neill Chevrolet, Inc. v. Forristall
551 N.W.2d 611 (Supreme Court of Iowa, 1996)
State v. Stoen
596 N.W.2d 504 (Supreme Court of Iowa, 1999)
Frank Millard & Co. v. Housewright Lumber Co.
588 N.W.2d 440 (Supreme Court of Iowa, 1999)
Hendricks v. Great Plains Supply Co.
609 N.W.2d 486 (Supreme Court of Iowa, 2000)
State v. Langlet
283 N.W.2d 330 (Supreme Court of Iowa, 1979)