Decker Construction Co. v. Wesex Corporation

CourtDistrict Court, S.D. Ohio
DecidedMay 19, 2023
Docket2:18-cv-00727
StatusUnknown

This text of Decker Construction Co. v. Wesex Corporation (Decker Construction Co. v. Wesex Corporation) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Decker Construction Co. v. Wesex Corporation, (S.D. Ohio 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

DECKER CONSTRUCTION CO., : : Plaintiff, : : Case No. 2:18-cv-00727 v. : : WESEX CORPORATION, et al., : : Chief Judge Algenon L. Marbley Defendants, : : v. : : Magistrate Judge Elizabeth P. Deavers GREGORY KOLEDIN, et al., : : Third-Party Defendants. :

OPINION & ORDER This matter is before this Court on Third-Party Plaintiff CCL Label, Inc.’s (“CCL”) Notice of Filing Affidavits in Support of Damages. (ECF No. 121). For the reasons stated below, this Court enters JUDGMENT for CCL, which is entitled to recover from Defendants, jointly and severally. Defendants Wesex Corporation and Gregory Koledin are ORDERED to pay to CCL $422,865 in damages, $217,903.64 in attorneys’ fees, and $12,047.26 in costs. This award is subject to post-judgment interest at the federal statutory rate. I. BACKGROUND Third-Party Plaintiff CCL hired Wesex Corporation (“Wesex”), whose President and CEO was Gregory Koledin, to perform design and construction services of a new production and office facility in New Albany, Ohio (“the project”). (ECF No. 9, ¶ 11). Wesex was obligated to “perform all design and construction services, and provide all material, equipment, tools and labor” necessary for the completion of the facility, per the parties’ Design-Builder Agreement (“Agreement”). (Id. ¶¶ 11–12). Importantly, the Agreement required Wesex to submit to CCL fully executed lien waivers from Wesex and all subcontractors, sub-subcontractors, laborers, and material suppliers, which covered all work paid as a result for the previous month’s application for payment. (Id. ¶ 15; ECF No. 9-3 ¶ 6.1.2). Wesex also was required to represent with each Application for Payment that the title to all work would pass to the owner free and clear of all

claims, liens, encumbrances, and security interests upon Wesex’s receipt of payment. (Id. ¶ 16; ECF No. 9-3 ¶ 6.1.4). Accordingly, Wesex was obligated to complete its work for CCL in a way that would not exceed the agreed contract price and would be free and clear of mechanics’ liens by Wesex, as well as its subcontractors, sub-subcontractors, laborers, and material suppliers. (ECF No. 9, ¶ 17). The Agreement also obligated Wesex to defend and indemnify CCL against any claims or mechanics’ liens brought against CCL or the project, including to obtain a release of any such claims or mechanics’ liens within three days. (Id. ¶ 18). If Wesex failed to comply, the Agreement gave CCL the right to discharge the lien or claim and hold Wesex liable for the costs and expenses incurred. (Id.).

Each month, Wesex submitted an Application for Payment, which represented that it had covered the work performed by its subcontractors and the like. (Id. ¶¶ 22, 25). Wesex, however, was not paying its subcontractors, sub-subcontractors, laborers, and material suppliers with CCL’s funds, but instead, paid itself nearly $1,000,000 in excessive, submitted affidavits falsely stating that Wesex had paid all of its subcontractors accordingly and that CCL was not exposed to any risk of claims, lawsuits, or liens. (Id. ¶¶ 26, 28–29, 40). Numerous subcontractors and the like asserted claims against the CCL and recorded mechanics’ liens. (Id. ¶ 39). Wesex also filed a mechanics’ lien against the facility in July 2018. (Id. ¶ 41). That same month, Plaintiff Decker Construction Co., a subcontractor on the project, filed a lawsuit, alleging a claim of unjust enrichment against CCL. (Id. ¶ 39; ECF No. 1). CCL filed its answer to the complaint and simultaneously filed a Third-Party Complaint against the Individual Defendants and a Crossclaim against Wesex. (ECF No. 9). CCL requested an entry of default on September 9, 2018 against Wesex and Mr. Koledin. (ECF Nos. 25–26). Default was promptly entered by the Clerk. (ECF No. 29). During the course of this litigation, mail to Mr.

Koledin has been returned as undeliverable. (ECF Nos. 89, 91, 98–100, 103). CCL sought a default judgment against Wesex and Mr. Koledin pursuant to Rule 55 of the Federal Rules of Civil Procedure for: (1) breach of contract; (2) fraud; (3) the remedy of piercing the corporate veil against Defendants; (4) slander of title; and (5) declaratory relief in the form of a judgment as it related to the mechanics’ lien filed by Wesex against CCL. (ECF No. 116). This Court granted default judgment against Defendants for all counts on September 8, 2021. (ECF Nos. 117; 118). Initially, CCL requested a damages hearing, but following CCL’s request to vacate the hearing and submit affidavits in support of damages instead, this Court vacated the hearing and CCL submitted a notice and affidavits in support of the damages sought. (ECF Nos. 119; 120;

121). Therefore, the issue of CCL’s damages is ripe for review. II. STANDARD OF REVIEW Having found default judgment proper, this Court must determine the appropriate measure of damages. Rule 55(b)(2) permits a court to conduct an evidentiary hearing to determine damages but does not require one. See Vesligaj v. Peterson, 331 Fed. App’x 351, 354–55 (6th Cir. 2009). A court’s determination of damages in a default judgment depends on whether the damages are calculable or liquidated. If the damages are calculable or liquidated, then the court will award the calculable damages to the plaintiff without an evidentiary hearing because the facts establishing the damage are not distinct from the facts establishing liability. See United States v. Di Mucci, 879 F.2d 1488, 1497-98 (7th Cir. 1989) (stating that an evidentiary hearing is not required if the damages are liquidated or can be definitively calculated from evidence and that in such cases the same facts establish the need for liability as well as damages); Barnes v. Abraham, Inc., No. 2:17- CV-279, 2017 WL 5714091 at *2 (S.D. Ohio Nov. 28, 2017) (quoting United States v. Parker- Billingsley, No. 3:14-CV-307, 2015 WL 4539843, at *1 (S.D. Ohio Feb. 10, 2015)) (“A court may

determine damages without holding an evidentiary hearing if the damages are ‘capable of ascertainment from definite figures contained in the documentary evidence or in detailed affidavits.’”). However, if the damages are unliquidated, the default judgment establishes only that the defendant is liable, and the plaintiff must prove damages. See Antoine v. Atlas Turner, Inc., 66 F.3d 105, 110 (6th Cir. 1995) (quoting Fehlhaber v. Fehlhaber, 681 F.2d 1015, 1026 (5th Cir. 1982)). Typically, such cases will necessitate the court holding an evidentiary hearing where the court can evaluate the plaintiff’s claims for damages, and the defendant can respond to such claims. See Id. at 110-11 (citing Greyhound Exhibitgroup, Inc. v. E.L.U.L. Realty Corp., 973 F.2d 155, 158 (2d. Cir. 1992)).

III. ANALYSIS Plaintiffs seek four types of monetary compensation: (1) compensatory damages; (2) attorneys’ fees; (3) costs incurred as a result of Wesex’s and Koledin’s fraud and breach of contractual duty to indemnify CCL; and (4) post-judgment interest. (ECF No. 121 at 3). Plaintiffs have provided evidence establishing the calculability of their damages, and thus this Court can determine the appropriate damages without an evidentiary hearing. See Ironworkers Dist. Council of Southern Ohio v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Decker Construction Co. v. Wesex Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/decker-construction-co-v-wesex-corporation-ohsd-2023.