Deborah Lonis and Russel Lonis v. Brandon Walton D/B/A Branded Builders

CourtCourt of Appeals of Texas
DecidedSeptember 21, 2023
Docket10-22-00352-CV
StatusPublished

This text of Deborah Lonis and Russel Lonis v. Brandon Walton D/B/A Branded Builders (Deborah Lonis and Russel Lonis v. Brandon Walton D/B/A Branded Builders) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deborah Lonis and Russel Lonis v. Brandon Walton D/B/A Branded Builders, (Tex. Ct. App. 2023).

Opinion

IN THE TENTH COURT OF APPEALS

No. 10-22-00352-CV

DEBORAH LONIS AND RUSSEL LONIS, Appellants v.

BRANDON WALTON D/B/A BRANDED BUILDERS, Appellee

From the 77th District Court Freestone County, Texas Trial Court No. CV20342

MEMORANDUM OPINION

Deborah and Russel Lonis appeal from the trial court's take nothing judgment

rendered after a trial before the court in their suit against contractor Brandon Walton

doing business as Branded Builders. In four issues, the Lonises attack the sufficiency of

the evidence to support the judgment. We affirm. Background

The Lonises bought an older home in November 2017. They knew when they

purchased it that it had obvious foundation issues. Almost a year later, the Lonises hired

Walton to work on their house. Although Walton and his crew did a considerable

amount of work over a period of several months, the foundation continued to move, and

the Lonises experienced additional problems. Eventually they sued Walton for violations

of the Texas Deceptive Trade Practices Act, and for fraudulent inducement, negligence,

negligent misrepresentation, negligent hiring, supervision, and/or management, and

breach of contract.

The parties entered into a "Service Contract" on October 4, 2018, which addresses

foundation repairs as well as some miscellaneous repairs. The "Foundation Repair"

section listed the following tasks to be performed by Walton:

All trash along with existing old gas lines under residence will be completely removed and discarded. "Note gas lines are no longer in use and main gas supply has be [sic] disconnected properly"

Any damaged or rotten lumber will be removed, this includes floor joist [sic], outside main wall beams along with inner floor support beams.

Existing undamaged beams will be reset and cut to fit tight through out [sic] foundation. Some beams may be removed and replaced due to improper cuts or short in lengths, these beams may be used in other areas if needed.

Additional beams will be installed where required for proper support of residence.

An additional 6" x 6" beam will be installed along main load bearing wall, this beam will be attached and secured from one side of residence to other providing required support. New concrete sets will be installed every 6 to 8 feet as required.

Lonis v. Walton Page 2 All outside main wall beams along with inner floor support beams will have both 6" Headlok structural wood screws or 3" x 6" metal mending plates installed at all joints and notches.

Residential home will be raised/lowered as needed throughout foundation to a level point. "Note throughout home small holes may be drilled inside near wall lines with flags providing low and high points. These small holes will be filled when finished." Existing damaged or improper blocking will be removed and discarded. New blocking will be installed correctly where needed.

Some interior doors may need to be adjusted, this is included in the estimate.

The contract contained a provision stating that Branded Builders recommends allowing

the foundation to settle for six months. It also provided that once the foundation has time

to settle Branded Builders will return to make adjustments where needed free of charge.

Further, the contract informed the homeowner that "Branded Builders warranties all

work performed for 10 years. A detailed warranty may be presented upon request."

Finally, the contract proclaims: "Branded Builders is a [sic] Insured and Bonded

Company." The Lonises paid $9,802.20, the agreed upon amount for the services.

Walton and his crew worked at the Lonises' home in October and November 2018.

On November 8, 2018, Deborah signed a document entitled "Satisfactory Agreement"

which states that "all work has been fully completed" and "owner has agreed to final

payment with complete satisfaction of work that was performed" at her home. However,

six weeks later, Deborah saw changes in the home. Believing the home was no longer

level, she contacted Walton. He re-leveled the house in March 2019. At that time,

Deborah signed a Foundation Repair Verification. That document contained the

Lonis v. Walton Page 3 statement: "By residential owner signing this form owner is satisfied with work that has

been completed." Unfortunately, after three or four months, the home displayed

additional signs that the foundation was not level.

Deborah testified that, at that point, Walton told her he "could never get it right,"

and he was not going to do any more work on the house. Deborah testified that she spoke

to another company about repairing the foundation. That company agreed to do the

work for $19,500. She also obtained an estimate of $28,000 to cover all remaining

necessary repairs.

Walton explained that he is a general contractor and has prior experience repairing

foundations. Three months before the Lonises purchased the home, the previous owner

asked him to look at it. Walton enumerated the many defects he saw at that time. He did

not do any work for the previous owner. After the Lonises bought it, he inspected the

house for them. He again described the numerous defects he saw, noting that changes

had been made to the foundation since he had seen it the first time. Notably, the front

left corner was sixteen inches too high.

Walton presented twenty-two photos of the Lonises' home that he took when they

signed the contract, before he started any work. He described the problems illustrated in

the pictures and said the previous owner of the house was responsible for the poor

condition of the house. Walton testified that due to the age and condition of the house,

it could never be leveled. He clarified that "[i]f you can get it within five degrees, ten

Lonis v. Walton Page 4 degrees, you're doing pretty good" but "[t]he house is going to move." He stated that it

would take $40,000 to make this house perfect. But since it would not be reasonable to

spend $40,000 on this house, he discussed with the Lonises that he could make the house

livable, not perfect. He recommended the Lonises have the base foundation repairs

completed and then remove and replace the flooring, subflooring, and floor joists. He

understood that they planned to do a complete renovation.

Walton told the Lonises he could fix the foundation and drafted the agreement.

He testified that he did all tasks listed in the contract under the "Foundation Repair"

heading. He leveled the home and then made adjustments twice after that. After the

work he did, the house was an acceptable quarter of an inch to three-eighths of an inch

out of level. Walton testified that, "I did my work through the limitations and what they

expected me to do." However, he admitted that the contract required him to remove all

damaged wood including floor joists, and all of the floor joists needed to be replaced.

Yet, he explained, he did not remove any floor joists because he would have to remove

the floor, and the Lonises would have to leave the house. He stated that he met industry

standards and that Branded Builders provides a ten-year warranty for all work

performed. He testified that, as long as the Lonises have issues with the work he did on

their foundation, he will come back and fix it "under certain stipulations" in the warranty.

He provided them a copy of the warranty when the work was completed "to give them

an idea of what we do stand behind and what we don't stand behind."

Lonis v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Turtur & Associates, Inc.
146 S.W.3d 113 (Texas Supreme Court, 2004)
Western Investments, Inc. v. Urena
162 S.W.3d 547 (Texas Supreme Court, 2005)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
In Re Doe
19 S.W.3d 249 (Texas Supreme Court, 2000)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Caprock Investment Corp. v. Montgomery
321 S.W.3d 91 (Court of Appeals of Texas, 2010)
Larsen v. Carlene Langford & Associates, Inc.
41 S.W.3d 245 (Court of Appeals of Texas, 2001)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Mead v. Johnson Group, Inc.
615 S.W.2d 685 (Texas Supreme Court, 1981)
Amstadt v. United States Brass Corp.
919 S.W.2d 644 (Texas Supreme Court, 1996)
Prudential Securities, Inc. v. Haugland
973 S.W.2d 394 (Court of Appeals of Texas, 1998)
Defterios v. DALLAS BAYOU BEND, LTD.
350 S.W.3d 659 (Court of Appeals of Texas, 2011)
Plainscapital Bank v. William Martin
459 S.W.3d 550 (Texas Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Deborah Lonis and Russel Lonis v. Brandon Walton D/B/A Branded Builders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deborah-lonis-and-russel-lonis-v-brandon-walton-dba-branded-builders-texapp-2023.