Deal v. Craven

266 S.W. 426, 1924 Tex. App. LEXIS 813
CourtCourt of Appeals of Texas
DecidedJune 19, 1924
DocketNo. 8522. [fn*]
StatusPublished
Cited by1 cases

This text of 266 S.W. 426 (Deal v. Craven) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deal v. Craven, 266 S.W. 426, 1924 Tex. App. LEXIS 813 (Tex. Ct. App. 1924).

Opinion

GRAVES, J.

M. M. Craven had a contract with Fort Bend county for the construction of 13 miles of public road, and on July 27, 1920, he sublet 5 miles of such construction, except as to the culvert and bridge work thereon, to Cliff Deal under the following written contract between them:

“The State of Texas, County of Fort Bend.
“This agreement, made and entered into by and between M. M. Craven, of Harris county,. Tex., hereinafter termed the contractor and Cliff Deal, of Wharton county, Tex., hereinafter termed subcontractor, witnessetli:
“That, whereas the contractor has heretofore entered into a contract with the duly authorized officials of Fort Bend county, Tex., to do certain road work for the county, and contractor 'and subcontractor has agreed to subcontracting some of such work upon the hereinafter set out terms and conditions, but it being distinctly understood and agreed that the work to be done shall comply with the terms and specifications of the original contract, and this contract is made subject to such original terms and conditions of the original contract.
“The work to be performed hereunder is to be a dirt road in Fort Bend county, beginning at a point about one-west of town of Rosenberg in said county, and terminating at a point 5 miles west from the starting point as per the plans covering said road, said road is known as Highway No.-.
“The work to be done hereunder is to be in strict compliance with the original contract between contractor and the county, to be done in a good workmanship manner, and to be subject to the inspection, approval, and acceptance of the county engineer of Fort Bend county, whose decision on all questions arising out of the performance of such work to be binding upon the parties hereto.
“The subcontractor agrees to finish the entire work contracted for herein within a period of one hundred and twenty-five (125) working days from the 27th day of July, 1920, and all of the dirt work shall be at the price of twenty-seven (27) cents per cubic yard for straight hauls, overhaul shall be paid at the price of 3% cents per cubic yard.
“The subcontractor further agrees to do all work on out fall ditches that might come within the points covered by this contract at the price of twenty-seven (27) cents per cubic yard.
“Payments shall be made upon monthly estimates furnished on such work by the engineer to the contractor; less 10 per cent, of the work accepted by the engineer; which 10 per cent, is to be withheld by the contractor and paid to the subcontractor when subcontract has been completed, inspected, approved, and accepted by the county engineer.
“Should the subcontractor, through default on his part, fail to complete the work herein contracted for within the time prescribed so as to be finally accepted by the engineer of Fort Bend county, and if through such failure the contractor should be penalized under his contract with the county of Fort Bend, then in such event the subcontractor agrees to reimburse the contractor for any sum of money he has to rightfully pay to the county of Fort Bend, and, should the subcontractor, after-starting the work contracted for, refuse to carry on the work, then all money withheld by the contractor for him on the estimates shall be forfeited by the subcontractor as liquidated damages to the contractor. However, this provision does not deny to the contractor the right to elect to sue for any damages such breach may cause him. And subcontractor agrees, should it become' necessary for the contractor to enforce the collection of any sum of money under this contract, to pay all necessary expenses, including a reasonable attorney’s fee for the enforcement of such claim or claims.
*427 “In witness whereof the parties hereto have signed their names in duplicate originals on this the 27th day of July, 1920.
“M. M. Craven.
“OlifE Deal.”

In this suit Deal as plaintiff sued Craven as defendant, alleging that he had constructed the 5 miles of the road so undertaken by him in at least substantial compliance with the requirements of the quoted contract; that he had done under it work of the total value of $17,592.83, consisting of “14,355 cubic yards of outfall ditch excavation within points covered by said contract at 27 cents per cubic yard aggregating the sum of $3,-875.85, 50,502 cubic yards of borrow and roadway excavation at 27 cents per cubic ,yard, aggregating the sum of $13,635.54, 2,-327 cubic yards of overhaul at 3%, cents per cubic yard, aggregating the sum of $81.44, the total amount of and for the work done by plaintiff for defendant under the terms of said contract, $17,592.83”; that he had received from Craven $14,597.45, and that there was duo him under the contract a balance of $2,995.43, for which sum he asked for a judgment against the defendant.

Craven answered the suit, denying that Deal had complied either with their subcontract or with the terms of the contract between Craven and Eort Bend county, or with the plans and specifications he had undertaken to work by. He then alleged that Deal had, on January 8, 1921, abandoned the work in an incomplete condition, and that he •himself, defendant, Craven, had been required by the county engineer of the county to go back on the road and complete it, and after doing that, to maintain it until it had been finally accepted by the county engineer, and that he had done this at a total cost to him of $3,892.39, and that, after allowing the plaintiff, Deal, a credit of what he would have been entitled to had he performed this work under their contract, a total of $2,800.72, which included $1,618.80 as 10 per cent retained by Craven on the work actually done by Deal up to the time he abandoned the undertaking there was left a balance of $1,091.61 in defendant’s favor, for which he asked judgment against plaintiff, Deal, by way of counterclaim; also praying for $500 attorney’s fees which he claimed under the section of the subcontract providing that, should it become necessary for Craven to enforce the collection of any sum of -money thereunder, Deal would pay all necessary expenses, including reasonable attorney’s fees for the enforcement of such claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deal v. Craven
277 S.W. 1046 (Texas Commission of Appeals, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
266 S.W. 426, 1924 Tex. App. LEXIS 813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deal-v-craven-texapp-1924.