Deal Development Co. v. Amarillo Concrete Contractors, Inc.

554 S.W.2d 294, 1977 Tex. App. LEXIS 3255
CourtCourt of Appeals of Texas
DecidedJuly 28, 1977
Docket5728
StatusPublished
Cited by6 cases

This text of 554 S.W.2d 294 (Deal Development Co. v. Amarillo Concrete Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deal Development Co. v. Amarillo Concrete Contractors, Inc., 554 S.W.2d 294, 1977 Tex. App. LEXIS 3255 (Tex. Ct. App. 1977).

Opinion

OPINION

JAMES, Justice.

This is a suit for breach of a construction contract. Pursuant to a jury verdict the trial court entered judgment for Plaintiff-Appellee, after allowing a counterclaim in favor of Defendant-Appellants. We reform and affirm.

Plaintiff-Appellee Amarillo Concrete Contractors, Inc. (hereinafter called “Amarillo”) sued Defendant-Appellants Deal Development Co., a partnership (hereinafter called “Deal”), Equity Builders, Inc., and Kaiser Aetna, a partnership, for damages for breach of a written contract under which Amarillo agreed to complete certain construction work for Deal on an apartment project known as the Brookstone Apartments in Clearwater, Florida. The contract defined the work as “furnish all labor, materials, and equipment necessary to complete all foundations and flatwork.” The contract price of $280,981.21 was increased by a change order for $16,965.00 which added about 10,000 linear feet of interior beams to the foundation, making a total contract price of $297,946.21. Defendant-Appellants asserted a counterclaim to the effect that Amarillo converted $16,965.00 worth of steel belonging to Deal.

The original contract was dated May 25, 1973, and was amended by a change order dated July 20, 1973; however, for purposes of this opinion the total agreement will be hereinafter referred to as the “contract.”

Trial was to a jury which found:

(1)The ending date of “a reasonable period of time” in which Amarillo was to have commenced the actual construction of the foundations on the Brookstone project under its contract with Deal was December 1973.

(2) Before and up to December 1973, Amarillo was ready, willing, and able to commence the actual construction of the foundations on the Brookstone project under its contract with Deal.

(3) At some time during the summer of 1974 before August 29, 1974, Deal instructed Amarillo not to proceed further with its work under the contract.

(4) Under all the circumstances which existed on or before the occasion wherein Deal instructed Amarillo not to proceed, Amarillo had proceeded with due diligence under the contract.

(5) Deal paid Amarillo $22,410.93 pursuant to the contract.

(There was no Special Issue No. 6).

(7) In July 1974, Deal informed Amarillo that Deal had decided to postpone for the indefinite future the commencement of actual construction of the foundations of the Brookstone project.

(8) Up until July 1974 when Deal informed Amarillo that Deal was postponing indefinitely the construction under the contract, Amarillo had proceeded with due diligence under the contract with Deal.

(9) In July 1974, Deal informed Amarillo that Deal would probably not build the Brookstone project.

(10) Under all the circumstances which existed on or before July 1974 wherein Deal informed Amarillo that Deal would probably not build the Brookstone project, Amarillo had proceeded with due diligence under the contract.

(11) As of July 31, 1974, the cost to Amarillo to complete its obligations under the contract with Deal was $248,126.96.

(12) Amarillo actually spent $22,410.93 in performance of its obligations under the contract with Deal.

(13) From October 1973 up through the summer of 1974, Amarillo possessed the capability of performing its construction obligations under the contract.

*296 (14) In November 1974 Deal made demand upon Amarillo to commence work on the Brookstone project.

(15) The jury failed to find that Amarillo’s failure to commence work after the November 1974 demand by Deal constituted a repudiation or abandonment of the contract.

(16) In July 1974 Deal was the owner of the steel in question for the Brookstone foundations.

(17) Amarillo in July 1974 converted such steel to its own use on another project.

(18) The reasonable cash market value of the steel in question in July 1974 at its location in Clearwater, Florida, was $16,-965.00.

(19) The jury failed to find that Amarillo’s converting such steel to its own use constituted notice by Amarillo that it was renouncing or abandoning the Brookstone project.

(20) The jury failed to find that Amarillo by its acts or conduct in 1974 waived its rights to any benefits from the Brookstone project contract.

Pursuant to and in harmony with the jury verdict, the trial court entered judgment in favor of Plaintiff Amarillo against Defendants for $32,854.25 and costs, from which Defendants appeal.

Appellants assert ten points of error challenging the jury’s answer to Special Issue No. 11, saying there is no evidence to support such finding, and that said finding is so against the great weight and preponderance of the evidence as to be manifestly wrong and unjust. As hereinbefore stated, in answer to Special Issue No. 11 the jury found that Amarillo’s cost as of July 31, 1974, to complete its obligations under its contract with Deal, was $248,126.96. Appellants contend that since this jury finding cannot stand, there is no basis upon which Plaintiff Amarillo can establish damages. We are of the opinion that there is ample evidence to support this jury finding in answer to Special Issue No. 11.

This case was tried, and properly so, upon the theory that the Plaintiff’s measure of damages as contractor is the contract price less what it would cost Plaintiff to perform the contract to completion. Carras v. Birge (Dallas 1948) 211 S.W.2d 998, NRE; Wynnewood Development Co. v. Belmares (Eastland 1956) 295 S.W.2d 441, no writ.

Bearing in mind the above rule for Plaintiff’s measure of damages, let us examine the mathematical consequences as the rule applies to the jury’s answers to the applicable special issues: The contract price was undisputedly $280,981.21 plus a change order increasing it by $16,965.00, making a total contract price of $297,946.21. The payments made by Defendant-Appellants to Plaintiff Amarillo on the contract were found by the jury (Special Issue No. 5) to amount to $22,410.93. The contract price less the payments results in a net contract balance of $275,535.28.

The jury found in answer to Special Issue No. 11 that the cost to Amarillo to complete its obligations under the contract and change order was $248,126.96. From this the trial court subtracted the jury’s finding of expenditures made by Amarillo of $22,-410.93 (Special Issue No. 12) to arrive at Amarillo’s unexpended cost of $225,716.03. Then, subtracting the unexpended cost of $225,716.03 from the net contract price of $275,535.28, the court arrived at Plaintiff Amarillo’s gross damages of $49,819.25. From this amount, the trial court subtracted $16,965.00 (same being the value of the steel which the jury found Amarillo converted in answer to Special Issues Nos. 16, 17, and 18), to arrive at Plaintiff Amarillo’s net damage of $32,854.25, which is the amount of the judgment Amarillo was awarded against Defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker & Associates Surveying, Inc. v. Austin
301 S.W.3d 909 (Court of Appeals of Texas, 2010)
Alvarez v. UNION MORTG. CO., INC.
747 S.W.2d 484 (Court of Appeals of Texas, 1988)
Retama Manor Nursing Centers, Inc. v. Cole
582 S.W.2d 196 (Court of Appeals of Texas, 1979)
Wolfman v. J. D. R. Corp.
567 S.W.2d 235 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
554 S.W.2d 294, 1977 Tex. App. LEXIS 3255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deal-development-co-v-amarillo-concrete-contractors-inc-texapp-1977.