De Puy v. Lone Star Dredging Co.

162 S.W.2d 161, 1942 Tex. App. LEXIS 289
CourtCourt of Appeals of Texas
DecidedApril 29, 1942
DocketNo. 11130.
StatusPublished
Cited by4 cases

This text of 162 S.W.2d 161 (De Puy v. Lone Star Dredging Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De Puy v. Lone Star Dredging Co., 162 S.W.2d 161, 1942 Tex. App. LEXIS 289 (Tex. Ct. App. 1942).

Opinion

NORVELL, Justice.

J. DePuy, appellant, contends that the judgment of the trial court awarding Lone Star Dredging Company, the appellee, a recovery of $23,400, upon a jury verdict, should be reversed because the trial court, upon proper motion, failed to set aside certain .findings of the. jury.

DePuy was the general contractor upon the Bay Front Improvement project of the City of Corpus Christi, and agreed to construct a sea wall extending^ from the' Bas-cule Bridge on the' north to Craig Street on the south, some twenty-five city blocks in length along the Corpus Christi Water Front. The wall was to be located approximately parallel with and 600 feet east of Water Street, which then ran north and south along the bay front.- It was provided that the area between the sea wall and Water Street should be. raised in elevation by filling the same with: material dredged from Corpus Christi Bay.

*162 The work relating to the dredging and hydraulic fill required by the general contract was sublet by DePuy to appellee at the same price per cubic yard (8½ cents) as that provided for in the general contract.

Appellee, as plaintiff below, pleaded for a recovery for various amounts, upon thirteen separate items or claims. No issues were submitted upon three of these pleaded items of damages and they were therefore waived. Issues relating to seven additional claims were answered unfavorably to appellee and no recovery allowed therefor. Appellee did not perfect a cross-appeal, nor file cross-assignments of error.

The jury answered issues submitted in connection with three of appellee's claims favorably to it, and the judgment before us is based upon these findings.

The determination of appellant’s contention that the trial court erred in rendering judgment upon each of the sets of issues involved in these three claims is decisive of the appeal, and we need not determine whether or not there was evidence sufficient to justify the submission of those issues which were answered favorably to appellant, i. e., whether or not a peremptory instruction should have been given.

The three items upon which recovery was allowed are (1) $17,250, for the grading of streets, (2) ‘ $1,350, for shifting of the dredge, and (3) $4,800, for a shut-down of the dredge.

We consider first the item of street grading. The jury found that DePuy had instructed appellee to excavate the streets upon the hydraulic fill (Issue 13); that such excavating was extra work, which was defined as being work outside and independent of a contract, something not required or contemplated by the parties in the performance of the contract (Issue 14); that DePuy had agreed to compensate ap-pellee for the excavation of said streets (Issue 15); that appellee has excavated “approximately 24,000 cubic yards” (Issue 16), and that the reasonable cost per cubic yard was 75 cents (Issue 17). The trial court computed the amount of the judgment upon this item on the basis of 23,000 cubic yards in view of the jury’s use of the word “approximately.” We express no opinion as to the correctness of the trial court’s' action in this particular.

As to the completed surface of the hydraulic fill, which was to be placed between the sea wall on the east and Water Street on the west, the plans provided for a splash area (concrete surfaced) about twenty feet in width lying immediately west of the sea wall. The plans also provided for the construction of a two lane roadway (Shoreline Boulevard) running north and south along the bay front, located adjacent to and west of the splash area. Each lane was forty feet in width and they were separated in most places along the course by an area or parkway which generally approximated eighty feet in width. The plans also provided that streets running east and west should be extended from Water Street to Shoreline Boulevard and typical street intersections were shown. The grade of the boulevard and the streets, as shown by the plans, was eight to twelve inches below that of the surrounding areas. Paving of the boulevard and certain intersecting streets was also provided for.

There were obviously two methods of placing the fill so that the surface contour thereof would comply with the plans. The area occupied by the fill could be brought to a relatively uniform grade throughout the entire area and then the parts thereof to be occupied by the boulevard and streets could be excavated so as to bring them to the grade designated in the plans. This method of constructing, placing and finishing the fill seems to be in accordance with appellee’s construction of the sub-contract here involved, that is, appellee contends that his contract only obligated him to bring the fill to a level relatively uniform throughout the area, and that “excavation” for roadways was not a part of his contract and was therefore an “extra.”

On the other hand, the various parts of the hydraulic fill could be brought to specified grades or elevations resulting in the formation of the requisite surface contour, that is, areas not to be occupied by streets could be brought to elevations above street grade by the deposit of additional materials thereon. This seems to be appellant’s theory of the method of placing the fill as contemplated by the provisions of the subcontract.

The contract between appellant and ap-pellee, in part, provides:

“The Sub-contractor agrees to do the dredging of approximately 1,550,856 cubic yards and the hydraulic fill complete as *163 required in the plans and specifications and contract between J. DePuy and the City of Corpus Christi, for the sum of Eight and one-half (.08½) Cents per cubic yard of hydraulic fill in place, which price includes the dredging, removing obstructions in the dredging areas, clearing the site of the hydraulic fill, disposing of material cleared off the work, completion of the hydraulic fill, along with all equipment, tools, labor, materials, extra material for shrinkage, all insurance and bond, and other incidentals necessary to complete the work.
“Payments for the hydraulic fill back of the seawall will be made on or about the 10th of each month on the cubic yards included in the monthly estimates of the Engineers of the City of Corpus Christi under the terms of the contract between J. DePuy and the City of Corpus Christi designating 10% withheld until the completion of the work, and J. DePuy agrees to pay the Sub-contractor immediately upon receipt of his monthly payments from the City of Corpus Christi.”

We have heretofore discussed parts of the plans incorporated in the general 'contract which are applicable to the sub-contract by the reference therein contained. The specifications of the general contract relating to the hydraulic fill which necessarily must be considered a part of the sub-contract provide:

“26.1 General: The hydraulic fill shall be made in accordance with the plans and to the lines and grades established by the Engineer. * * *
“26.8 Depositing Material: Excavated material shall be deposited in accordance with the plans and the grades and lines of the .Engineer; and dredging and filling shall progress in sequence approved by the Engineer. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pasadena Police Officers Ass'n v. City of Pasadena
497 S.W.2d 388 (Court of Appeals of Texas, 1973)
H. B. Zachry Co. v. Ceco Steel Products Corp.
404 S.W.2d 113 (Court of Appeals of Texas, 1966)
King Construction Co. v. W. M. Smith Electric Co.
350 S.W.2d 940 (Court of Appeals of Texas, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
162 S.W.2d 161, 1942 Tex. App. LEXIS 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-puy-v-lone-star-dredging-co-texapp-1942.