De La Vergne Refrigerating Machine Co. v. New Orleans & Western Railroad

26 So. 455, 51 La. Ann. 1733, 1899 La. LEXIS 617
CourtSupreme Court of Louisiana
DecidedMay 15, 1899
DocketNo. 12,961
StatusPublished
Cited by12 cases

This text of 26 So. 455 (De La Vergne Refrigerating Machine Co. v. New Orleans & Western Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De La Vergne Refrigerating Machine Co. v. New Orleans & Western Railroad, 26 So. 455, 51 La. Ann. 1733, 1899 La. LEXIS 617 (La. 1899).

Opinion

The opinion of the court was delivered by

Blanchard, J.

Plaintiff company and a corporation known as the Delta Constr.uction Company, on July 10, 1895, entered into a contract whereby the former obligated itself to construct, erect and deliver to the latter on certain premises in the State of Louisiana two cotton compresses and appurtenances, one a 2,000-ton Bierce press, the other a 4,000-ton Webb press.

The price agreed upon for the two compresses was $80,000, with exchange on New York, a portion of which was to bo paid at the signing of the contract, other portions as the work progressed, and 'the remainder, $32,000, sixty days after completion.

It was stipulated that the Bierce press was to be completed and ready for work 120 days after date of the contract, and the Webb press 150 days thereafter.

A further stipulation embodied the guaranty on part of plaintiff company that the compresses would, when completed, compress 120 [1735]*1735bales of cotton, measuring 28x56, and weighing, approximately, 500 pounds each, in an .hour and twenty-five minutes; and that each of these bales so compressed, measured an hour after compression, would show an average density of thirty pounds per cubic, foot.

The parties to the contract were both New York corporations and the contract was entered into and signed in that State. It was to be executed in Louisiana.

Subsequently, the New Orleans & Western Railroad Company, a Louisiana corporation, succeeded, by transfer and subrogation, to all the rights of the Delta Construction Company in and to the contract.

The Bierce press was constructed and erected within the time agreed on, and with reference to it there is no controversy.'

The Webb press was not constructed within the time agreed on, and at the end of that period, or on December 8, 1895, an important modification of the contract was agreed on between the parties.

It was proposed by the Delta Construction Company and accepted by plaintiff company.

The proposal was the result- of a conversation the parties had had that day (December 3, 1895 ) relative to the delays in completing the compress, and its object was stated to be to settle all questions as to damages caused by the delays. The proposal and its acceptance were in writing and its essential features were these:

“The company (the Delta Construction Company) will pay you $8,000 on account of the original contract on or before December 10, 1895; $8,000 on March 1, 1896; $8,000 on June 1, 1896, and the balance due on said original $80,000, after deducting all previous payments, sixty days after the Webb press is ready to operate and has-been tested accordingly.

“It is distinctly understood that this additional memorandum to the original contract shall not change in any manner, or alter, the guarantee as to the performance of the presses, given by you in said original contract dated July 10, 1895.”

This written modification of the original contract, it will be observed, waived the time limit and damages incident thereto, and permitted the execution of the contract for the erection of the Webb press to. proceed without naming another time or date as to which it should be completed.

However, it is conceded by both parties that, contemporaneously with its execution, an oral agreement was made that the time for the [1736]*1736•completion of the press under the modified contract should be March 1, 1896.

This modification of the contract, as well as the oral agreement as to March 1st for i'ts completion, took place in the City of New Orleans between the representatives of the contracting parties.

The compress was not completed by March 1, 1896. The reasons .assigned for this are that the press (Webb) was of unprecedented size, weight and power, that it was nearly twice as large as any compress that had ever theretofore been ordered, that in consequence special models, moulds and dies for the enormous castings, etc., had to be made, certain parts of the press were compelled to be ordered from foundries and machine works, other than plaintiffs’, having special adaptability, or facilities, for such work, etc.

J3ut, notwithstanding- its non-completion on March 1st, defendant neither put plaintiff in formal default in reference thereto, nor brought suit to annul the contract because of failure to timely complete, nor was complaint on this account made at the time.

Plaintiff proceeded with the work of the press, expending large sums of money in materials and labor.

In April, 1890, defendant company entered into contracts with cotton factors in New Orleans to handle, stqre and compress their cotton for the season of lSSC-I, beginning September 1, 1896. As the result of these contracts, the company handled of that season’s business over 800,000 bales of cotton, of which it compressed over 225,000 bales.

And we find that late in April, 1896, under the belief that four compresses were necessary to equip the company with proper facilities for doing its business, it contracted with W. W. Bierce to construct, two additional compresses oil the premises, to be completed one September 1, 1896, the other October 1, 1896.

All during the months of March and April, and while the contracts with the factors for the delivery of cotton, -and the one with Bierce for the two additional compresses, were being made, plaintiff’s contract •for the Webb press was not interfered with, and this condition of affairs continued down to May 1, 1896, when defendant company wrote plaintiff from their New York office to the effect that advices from their New Orleans office stated the Webb press had not arrived yet, nnd referring to the fact that they (defendant) had already suffered damages through the delay, and that the erecting- of the press would [1737]*1737further interfere with ,the general work and operation of their plant, .admonished plaintiff that unless due diligence was shown in completing the contract, damages would be charged for the delay, or defendant “would refuse to accept the press altogether.”

Plaintiff answered this on the 19th of May to the effect that every effort to complete the press at the earliest possible moment was being made, and it was expected to have it ready for operation before the cotton season opened.

Matters rested thus until June 3, 1896, when defendant wrote again advising that, from the outlook, the completion of the press by A ugust i, 1896, was highly problematical, and stated that unless it was in working order by that time, “we hold you responsible for whatever damages we may suffer from the fact of its non-completion prior to that date.”

Plaintiff replied to this, reiterating that everything possible was being done to complete the press, and that it was confidently expected to have it in operation by August 1, 1896.

It will be observed that both these letters of defendant (of May 11th and June 3rd) had in contemplation the holding of plaintiff responsible in damages for further unreasonable delay in completing the press, and the one of June 3rd, for the first time, intimated August 1st as the time beyond which plaintiff would not -be permitted to go without incurring the penalty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford v. J & J Pallets, Inc.
623 So. 2d 91 (Louisiana Court of Appeal, 1993)
West India Oil Co. v. Sancho Bonet
54 P.R. Dec. 732 (Supreme Court of Puerto Rico, 1939)
Superior Laundry & Cleaners, Inc. v. American Laundry MacHinery Co.
155 So. 186 (Mississippi Supreme Court, 1934)
Hamilton Co. v. Medical Arts Building Co.
135 So. 94 (Louisiana Court of Appeal, 1931)
Rapides Grocery Co. v. Golding
1 La. App. 409 (Louisiana Court of Appeal, 1925)
Keen v. Logan
84 So. 501 (Supreme Court of Louisiana, 1920)
In re New Orleans Milling Co.
263 F. 254 (E.D. Louisiana, 1920)
Borne v. Alexander Hardwood Co.
72 So. 979 (Supreme Court of Louisiana, 1916)
McClendon v. Busch-Everett Co.
70 So. 781 (Supreme Court of Louisiana, 1916)
Lozes v. Segura Sugar Co.
52 La. Ann. 1844 (Supreme Court of Louisiana, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 455, 51 La. Ann. 1733, 1899 La. LEXIS 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-la-vergne-refrigerating-machine-co-v-new-orleans-western-railroad-la-1899.