DCX-CHOL Enterprises, Inc.

Armed Services Board of Contract Appeals·Decided October 11, 2016·No. ASBCA No. 58742·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) DCX-CHOL Enterprises, Inc. ) ASBCA No. 58742 ) Under Contract No. N00104-05-C-FA80 )

APPEARANCE FOR THE APPELLANT: James S. DelSordo, Esq. Argus Legal, LLC Manassas, VA

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Abram D. Burnett, III, Esq. Assistant Counsel NAVSUP Weapon Systems Support Mechanicsburg, PA

OPINION BY ADMINISTRATIVE JUDGE HARTMAN ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT

Appellant seeks conversion of the termination of its contract for default to a termination for the convenience of the government. Appellant asserts that it is entitled to summary judgment because the Department of the Navy (Navy) waived the delivery schedule for its contract when it failed to deliver and continued to perform the contract in reliance on that waiver with the Navy's knowledge, thereby precluding termination of its contract for default absent establishment of a new delivery schedule. The Navy asserts that appellant has not established either of the elements necessary for a waiver and that there are questions of material fact precluding grant of appellant's motion for summary judgment.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In September of 2005, the Navy awarded Contract No. N00104-05-C-FA80, for submarine "stuffing tubes" (also referred to as "hull penetrators") to appellant, DCX-CHOL Enterprises, Inc. (DCX) (R4, tab 4). Stuffing tubes are classified as "Level I/SUB SAFE" materials because the use of incorrect or defective material could create a high probability of failure resulting in serious personnel injury, loss of life, loss of vital shipboard systems, or loss of the ship itself (see R4, tab 2 at 57). By bilateral contract Modification No. P00020 dated 18 October 2012, the parties agreed to extend the remaining contract delivery date to 15 February 2013 (R4, tab 56). By email dated 24 January 2013, Lea Demirovic, a Navy contract specialist located in Mechanicsburg, Pennsylvania, asked DCX for its delivery schedule for the remainder of the units under the contract (R4, tab 60 at 2). Four days later, by email dated 28 January 2013, Tom Shafer of DCX responded that "I am working on this and will get back to you later today" (id.). On 12 February 2013, Ms. Demirovic responded to Mr. Shafer that "I haven't received anything from you yet" and "[p]lease let me know what's the status" (id.). Two days later, on Thursday, 14 February 2013, one day before the specified delivery date, Mr. Shafer replied to Ms. Demirovic as follows:

I apologize for not getting back to you but I was trying to get delivery answers. We are still missing components from our supplier for the Plasma Coating process. I have been told these parts should be at our facility next week. If the parts do come in and are acceptable, I am looking at an additional 4 weeks for in-house processing. I would estimate the delivery the week of March 25, 2013. I will keep you informed of our progress next week.

(Id. at 1) On Tuesday, 19 February 2013, the day after the President's Day holiday, Ms. Demirovic advised Mr. Shafer by email that "[y]our contract is currently delinquent" and "[i]n order to consider your extended delivery date of 03/25/13, we would need consideration." After Ms. Demirovic did not receive a response to her 19 February 2013 email within 2 days, she sent a 21 February 2013 email to both Mr. Shafer and Cory Gamberg of DCX stating again "subject contract is currently delinquent," "[y]our attention to this matter is greatly appreciated," and "[p]lease respond at your earliest convenience." (Id., tab 63 at 2)

Ms. Demirovic received no response from DCX to her 21 February 2013 email during the following 12 days. The Navy's contracting officer (CO), Richard Fry, then sent DCX a "show cause" letter dated 5 March 2013 stating:

Since you have failed to perform Contract No. NOO 104-05-C-F A80 within the time required by its terms, the Government is considering terminating the contract under the provisions for default of this contract. Pending a final decision in this matter, it will be necessary to determine whether your failure to perform arose from causes beyond your control and without fault or negligence on your part.

Accordingly, you are given the opportunity to present, in writing, any facts bearing on the question ... within 10 days after receipt of this notice. Your failure to present any

2 excuses within this time may be considered as an admission that none exist. Your attention is invited to the respective rights of the Contractor and the Government and the liabilities that may be invoked if a decision is made to terminate for default.

Any assistance given to you on this contract or any acceptance by the Government of delinquent goods or services will be solely for the purposes of mitigating damages, and it is not the intention of the Government to condone any delinquency or to waive any rights the Government has under the contract. [Emphasis added]

(R4, tab 61)

By letter dated 14 March 2013, Michael Jamison, vice president ofDCX, responded to the CO's show cause letter as follows:

The delay on contract NOO 104-05-C-FA80 is due to delays that occurred during the outside processing of the hull penetrator bodies. There were two groups of parts that where [sic] sent out for the outside processing.

Group 1 Parts were sent out for Gold plating of contacts.... On January 29, 2013 the approved parts were then sent to another vendor to have the non-conductive coating applied.... These parts were received at [DCX] on February 27, 2013.

Group 2 These parts [were] a group of assemblies that [were] returned for repair due to a debonding issue that occurred on an earlier shipment of assemblies. During the rework process of these returned parts ... , it was determined the non-conductive coating was being removed during the rework. These assemblies [were] sent back to the original vendor for removal of the non-conductive coating and the re-application of the non-conductive coating. The last batch of these parts were signed off by the government inspector on February 21, 2013.

To complete the manufacturing process on both Group 1 and Group 2, the ... processes include wiring of the body,

3 rubber molding, electrical testing, hydro-static testing and special packaging including the "Level- I" contract data requirements.

[DCX] will ready for shipment no later than May 8, 2013. The Level 1 inspection will be notified 2 weeks prior to the ship date to make arrangements for travel.

(R4, tab 62)

After reviewing the response from DCX, Ms. Demirovic prepared a 10-page memorandum dated 11 April 2013 for Jodene R. Watkins, deputy director of the Critical Requirements Contracting Department, proposing the DCX contract be terminated for "default." Ms. Demirovic stated in her memorandum:

The contractor ha[ s] continuously failed to meet the scheduled delivery dates of the First Article Test Report ("FAT report") and material. Originally, DCX failed to submit its FAT report and to get it approved before 09/18/06 and consequently missed delivery dates on 09/18/06 and on 10117/06. On 11/14/06, a bilateral modification with consideration, P00008, was issued to extend FAT report delivery date to 11130/06 and to extend incremental deliveries of the material with a final delivery date on 06115/07.

On 12/01/06, the PCO sent a show cause notice to DCX because DCX failed to submit the report on time. As a new Level 1 supplier, DCX was given another opportunity and a bilateral modification with consideration, P00009 extended the FAT report delivery date to 3/1/07 and final material delivery date was extended to 12/11/07.

Free access — add to your briefcase to read the full text and ask questions with AI

DCX-CHOL Enterprises, Inc., (asbca 2016).

DCX-CHOL Enterprises, Inc. (DCX-CHOL Enterprises, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related