Davis v. Smith

650 S.W.2d 47, 1983 Tenn. App. LEXIS 557
CourtCourt of Appeals of Tennessee
DecidedFebruary 15, 1983
StatusPublished
Cited by2 cases

This text of 650 S.W.2d 47 (Davis v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Smith, 650 S.W.2d 47, 1983 Tenn. App. LEXIS 557 (Tenn. Ct. App. 1983).

Opinion

OPINION

TODD, Presiding Judge, Middle Section.

This is a suit under T.C.A. § 64-1101 et seq. (66-11-101 et seq.) to enforce a lien upon real estate for $5,734.75 for excavating and grading for the improvement of said real estate. The defense is that on January 15, 1979, at which time the improvement was “100% complete”, the defendant, Thomas E. Smith, IV, filed a notice of completion and that plaintiff failed to notify said defendant of his lien claim within ten (10) days after January 15, 1979. Other defendants are not involved in this appeal.

The Chancellor held that the improvement was not complete on January 15,1979, that the notice of completion was ineffective, sustained plaintiff’s lien claim and awarded an “attachment” to enforce the lien. No question is raised as to the finality of the judgment or the jurisdiction of this Court to entertain an appeal as of right.

Also, no question was raised as to whether the lien of plaintiff was properly preserved by a “suit for attachment” rather than by the issuance and levy of attachment within ninety (90) days after the notice of lien was recorded. See Knoxville Structural Steel Co. v. Jones, 46 Tenn.App. 518, 330 S.W.2d 559 (1959).

The defendant, Thomas E. Smith, IV, has appealed and stated the following issue for review:

Was the improvement “substantially complete” as of the date of filing the Notice of Completion?

T.C.A. § 66-11-143 reads in pertinent part as follows:

Protection from unregistered liens— Notice of completion after improvements — Expiration of certain lien rights. —(a) In order to be protected from lien claims which have not previously been registered as provided in §§ 66-11-111, 66-11-112, and 66-11-117, the owner or purchaser of improved real property may upon completion of the improvement or the demolition thereof register in the office of the register of deeds in the county where the real property or any affected part thereof is located a notice of completion, or the owner or purchaser may require a person or organization with whom he has contracted for the improvements or demolition to do so upon completion of the structure or improvement or demolition.
(d) Any person claiming a lien for labor or materials upon the property described in the notice of completion who has not previously registered his contract as provided in § 66-11-111 or registered a sworn statement as provided in § 66-11-112 or § 66-11-117 shall send by registered or certified mail written notice addressed to the person, firm or organization and at the address designated in the notice of completion for receiving notice of claims, stating the amount of his claim and certifying that the claim does not include any amount owed to the claimant on any other job or under other contract.
Such written notice shall be timely mailed so as to be received by the addressee not more than ten (10) days after the date of the filing of the notice of completion in the register’s office, and if same is not received by the addressee within said time, the lien rights of the claimant shall expire. [Acts 1975, ch. 307, §§ 1-3; T.C.A., §§ 64^-1145 — 64-1147.]

The former owners of the property, Og-nio and Magnuson undertook to construct upon the subject property a two story commercial office building including adjacent grades and paving. Said owners contracted with plaintiff to perform all necessary [49]*49grading, gravelling and paving. After plaintiff had performed the grading and spread gravel and before the paving was installed, the owners sold the property to defendant Smith who undertook to complete the building for occupancy. As stated above, the issue on appeal is whether the construction was complete on January 15, 1979, when defendant Smith filed the notice of completion in the Register’s office. It is conceded that plaintiff did not give defendant statutory notice of lien claim within ten (10) days after January 15, 1979, and that notice of lien was not filed in the Register’s office until March 21, 1979.

Defendant testified that the construction was complete on January 15. However, this testimony is contradicted by the testimony of Larry Henry, a heating and air conditioning contractor, that he contracted with the former owners to install all heating and air conditioning equipment and that Smith, the new owner contracted with him to finish the job; that he ceased work in August, but resumed around the end of December under his agreement with Smith; that, at that time certain duct work, return air crates, gas lines and electrical work were not complete; that the work of completing the heating and air conditioning proceeded continuously until January 20, 1979, and thereafter, but not continuously, until February 2, 1979, the last day on which work was done on heating and air conditioning; that the work done on January 20, 1979, consisted of installing “egg crates,” thermostat covers and four bath ventilators, including opening holes in walls; that the heating and air conditioning was substantially finished on January 20, but problems required return trips thereafter to and including February 2; that other workmen were present on January 20, installing tile; and that, on that date rolls of carpet were on the job to be installed and painters were “touching up” paint work.

The Chancellor did find that, on January 15, 1979, the building was 99.5% complete. Nevertheless, he concluded that the construction was not “complete” within the contemplation of T.C.A. § 66-11-143, above, which provides, “upon completion of the improvement.”

Appellant apparently concedes that the construction was not 100% complete, but insists that “substantial completion” satisfies the requirement of the statute quoted above.

Appellant first relies upon the Chancellor’s finding of 99.5% completion. This Court finds no evidence in the record upon which a mathematical calculation of percentage of completion could be based. Accordingly the expression, “99.5% complete,” as used by the Chancellor is viewed as a colloquialism expressing a general opinion of near but not perfect completion. Moreover, even if the percentage should be mathematically exact, it is not conclusive of the merits of this case. Incompletion of .5% in dollar value or in area is capable of being of sufficient importance to render a construction project incomplete for purposes of the statute in question. Lienors are generally allowed ninety (90) days from the completion of the structure within which to perfect their liens. T.C.A. § 66-11-112. It would not do to interpret said statute to mean “99.5% completion” or “substantial completion,” for lienors would have no accurate standard by which to set the beginning of the ninety (90) day period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
650 S.W.2d 47, 1983 Tenn. App. LEXIS 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-smith-tennctapp-1983.