Davis v. City of Okmulgee

1935 OK 654, 50 P.2d 315, 174 Okla. 429, 1935 Okla. LEXIS 1262
CourtSupreme Court of Oklahoma
DecidedJune 11, 1935
DocketNo. 23853.
StatusPublished
Cited by7 cases

This text of 1935 OK 654 (Davis v. City of Okmulgee) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. City of Okmulgee, 1935 OK 654, 50 P.2d 315, 174 Okla. 429, 1935 Okla. LEXIS 1262 (Okla. 1935).

Opinion

PER CURIAM.

The plaintiffs in error will be referred io as plaintiffs and defendant in error will be referred to as defendant, the order in which they appeared in the trial court.

This is an action brought by plaintiffs against the defendant for damages alleged to have been caused by acts of defendant during the time plaintiffs were constructing a dam for defendant under a written contract.

The plaintiffs set out general allegations in their second amended petition and seven distinct causes of action. The defendant filed a demurrer to each separate cause of action, and set out as the ground for each demurrer that the alleged cause of action does not state facts sufficient to constitute a cause of action in favor of plaintiffs and against said defendant.

The court sustained the demurrer to each cause of action. The plaintiffs elected to stand upon their pleadings and the court dismissed the case. Prom the ruling of the ■court, the plaintiffs have appealed.

The plaintiffs filed a second amended petition in this action in which they make general allegations that they entered into a written contract with the defendant by the terms of which plaintiffs agreed to construct a storage dam for water, which contract was according to certain detailed plans and specifications furnished by said defendant.

The plaintiffs allege in said second amended petition that all work required to be performed by them under said contract has been completed and all material required under said contract to be furnished by them was duly furnished, and that plaintiffs have fully performed and discharged each, every, and all obligations incumbent upon them to be done and performed under the terms of said contract, and that the engineer for the defendant figured the compensation to which the plaintiffs were entitled according to the terms of the contract, which compensation was found to be $38,221.34, and was agreed to by the plaintiffs and the defendant, which sum was paid by the defendant; that said payment covered the work performed and material furnished at the prices stipulated in the contract and no more; that no sum was added and no compensation given or received for or on account of any of the claims hereinafter set forth; that the plaintiffs were at the time claiming to be entitled to certain damages from the defendant by reason of the matters and things hereinafter set forth, which claims were at the time well known to the defendant and its board of city commissioners.

That at the time of the aforesaid payment the defendant required the plaintiffs to execute and deliver to it the receipt hereinafter mentioned before it would make said payment, and because of said requirement the plaintiffs did execute and furnish a receipt to the defendant in words and figures, as follows:

“We do hereby acknowledge receipt of your check as treasurer of the city of Ok-mulgee, state of Oklahoma, in the sum of $38,221.34, which is in full and complete payment of the work done by the firm of A. A. Davis & Company under its contract with the city of Okmulgee of the state of Oklahoma, dated May 4, 1926, for the construction of the earth dam at Lake Okmul-gee. This is in full settlement of the work set forth and contained in said contract and includes all extra work which was performed by us.”

The plaintiffs then allege that said receipt was not intended to and did not cover any of the unliquidated claims for damages hereinafter mentioned; that the defendant was so advised at the time of said payment and prior thereto, and that within a few days thereafter the defendant was also informed in writing in a letter addressed to the mayor and city commissioners of Ok-mulgee, Okla., under date of September 30, 1927, as follows:

“We have received payment on the final estimate on the dam job and signed the receipt per your request and demands, all which, as you know, is not in accordance with our contract. * * *
“We will shortly bill you for damages caused us by delays and negligence upon the part of the city. We would thank you to furnish us the revised plans as requested.”

After making the foregoing general alie-. gations in their second amended petition, the plaintiffs allege seven specific causes of action, adopting all the general allegations as a part of each cause of action.

First Cause of Action: That defendant required plaintiffs to begin work on the dam at the bed of the stream, when in fact the proper and economical method of performing said work was to begin at or near the *431 western end of said dam, and that defendant had neglected to procure ownership or right of possession of land over which a public highway was constructed and certain pipe lines were laid which caused delay in completing the dam.

Second Cause of Action: That plaintiffs were required by defendant to procure.dirt and clay for dam from distant points instead of from pits nearest the point where such material was to be placed in said dam, and that obtaining dirt and clay from more distant points increased the cost of construction.

Third Cause of Action: That said defendant would not permit plaintiff to mix concrete at night and that the proper and economical method of mixing and laying concrete was either during the day or nighr and refusal to permit mixing concrete at night increased the eos.t of construction.

Fourth Cause of Action; That the defendant arbitrarily caused the plaintiffs to mix certain concrete for use in constructing of said dam too dry and that by reason thereof plaintiffs were required by defendant to repair and resurface said work done and that the repairing and resurfacing greatly increased the cost of performing said work.

Fifth Cause of Action: That defendant arbitrarily required the plaintiffs to reinforce the core wall of said dam with steel bars and so-called dowels and to drill holes in certain sections of said concrete already in place and to grout said dowels in place in said holes and that same was not provided for in the plans and specifications and that said additional work greatly increased the cost of performing said concrete work.

Sixth Cause of Action: That there was a natural drainage extending from a northern and northwesterly direction to the location of the dam and the channel carried water from the drainage area of approximately 40 square miles, and that this area was covered with trees, shrubs, brush, and undergrowth of various kinds, and that the defendant cut down trees, shrubs, brush, and undergrowth and failed to destroy the • same, and the same was carried by runoff water from the rainfall into the intake tower and tunnel constructed by plaintiff, thereby stopping the flow of water and forcing it back so that it. flooded the work being done by plaintiff and washed out a large part of it, washed away and destroyed concrete forms, etc., and this happened on several occasions and by reason thereof caused great delay and increased cost of construction.

Seventh Cause of Action: That by reason of the additional cost of construction the dam as set out in the first six causes of action in the sum of $111,439.12, and that plaintiffs are entitled to recover 15 per cent, of said amount as provided in the contract for extra work required by defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammer v. Old American Insurance Company
1970 OK CIV APP 9 (Court of Civil Appeals of Oklahoma, 1970)
Cheney v. Rucker
381 P.2d 86 (Utah Supreme Court, 1963)
Murray v. Link Oil Company
1960 OK 166 (Supreme Court of Oklahoma, 1960)
Holt v. Jones
1952 OK 375 (Supreme Court of Oklahoma, 1952)
Gibson v. Mendenhall
1950 OK 276 (Supreme Court of Oklahoma, 1950)
Hoyt v. Carey
1939 OK 336 (Supreme Court of Oklahoma, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
1935 OK 654, 50 P.2d 315, 174 Okla. 429, 1935 Okla. LEXIS 1262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-city-of-okmulgee-okla-1935.