David Miolen v. Doug Saffles

CourtCourt of Appeals of Tennessee
DecidedApril 12, 2019
DocketE2018-00849-COA-R3-CV
StatusPublished

This text of David Miolen v. Doug Saffles (David Miolen v. Doug Saffles) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Miolen v. Doug Saffles, (Tenn. Ct. App. 2019).

Opinion

04/12/2019 IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 21,2019 Session

DAVID MIOLEN ET A.L. V.DOUG SAFFLES ET AL.

Appeal from the Circuit Court for Bradley County No. V-13-894 Lawrence H.Puckett, Judge

No. E2018-00849-00A-R3-CV

Plaintiffs David Miolen and Ann Miolen, husband and wife, hired contractor Doug Saffles to install, on the backyard of the plaintiffs' property, a pool, additional water features, a bathhouse, outdoor kitchen and fireplace, and a large amount of stone pavers and stairs. Because their home was on a sloping hillside, the work involved moving a lot of earth and building two retaining walls to support the project. When the work was about 90% done, plaintiffs became dissatisfied and ordered defendant off the site. They sued him for breach of contract, negligence in failing to perform in a good and workmanlike manner, misrepresentation, and violation of the Tennessee Consumer Protection Act, Tenn. Code Ann. § 47-18-101 et seq. (Supp. 2018). Defendant counterclaimed for unpaid work. The trial court held that defendant violated the TCPA by misrepresenting that both walls had been engineered by a professional engineer, and by charging plaintiffs $10,000 in "engineering" expenses that were not incurred by an engineer. The court awarded plaintiffs $68,974 in compensatory damages and assessed treble damages for the TCPA violation, plus plaintiffs' costs and attorney's fees. The total amount of $232,285.31 was offset by a judgment in defendant's favor on his counterclaim in the amount of$12,061.75. As calculated in our opinion, the net award to plaintiffs is reduced to $127,727.56. The trial court's judgment, as modified, is affirmed.

Tenn. R. App.P.3 Appeal as of Right; Judgment of the Circuit Court Affirmed as Modified; Case Remanded

CHARLES D. SUSANO, JR., J., delivered the opinion of the court, in which D. MICHAEL SWINEY,C.J., and JOHN W.MCCLARTY,J.,joined.

Douglas M. Cox, Chattanooga, Tennessee, for the appellants, Doug Saffles, individually and dba Saffles Dozer Service, LLC.

Joshua H. Jenne, Cleveland, Tennessee, for the appellees, David Miolen and Ann Miolen.

-I- OPINION

I.

On September 18, 2012, defendant submitted to the plaintiffs two "budget proposals." One was for "site work" and "retaining walls" with eight line items that totaled $104,000. The other proposal was for a "new water feature and amenities" with twelve line items totaling $115,665. The parties agreed, and the trial court found, that these two proposals formed the contractual agreement between the parties. The proposal for the retaining walls included a line item for "engineering" in the amount of $10,000. The "water feature" proposal included 2,500 square feet of stone pavers at a charge of $25,625.

Dennis N. Gore, a professional engineer and registered land surveyor, conducted a survey and developed a set of preliminary sketches for the project. The sketches are prominently marked "FOR REVIEW ONLY" and "NOT FOR CONSTRUCTION." Gore testified that the purpose of the sketches was "to give you a rough idea of how much it was going to cost." He charged $1,000 for the survey and sketches, which was paid directly by plaintiffs. This was in addition to and not included in the parties' agreement as reflected in the two budget proposals.

The sketches indicate that two retaining walls would be required. The larger of the two, the "lower wall,"' was further away from the house than was the "upper wall." The lower wall was estimated to be about 1,600 square feet and 14 feet high at its highest point. The top of the lower wall marks the end of the outside entertainment space in the back yard; beyond it is a downward-sloping wooded area. The roughly 900 square foot upper wall is slightly more than four feet tall at its highest point. It contains some steps to the entertainment space.

The following photographs are designed to assist the reader in understanding the facts of this case. Figure 1 is an early picture of the pool area under construction. The upper wall is shown in the top right hand corner of the photograph. The lower wall under construction is shown in the far left of Figure 1. Figure 2 shows a portion of the completed lower wall. Figure 3 shows a portion of the completed upper wall. Figure 4 is a picture ofthe completed outside entertainment space.

The parties referred to the two walls as the "lower wall" and the "upper wall." We will use the parties' nomenclature. -2- Fig,ure 1

Figure 2

-3- Figure 3

Figure 4

-4- Defendant asked Gore to prepare an estimate of how much he would charge to engineer the two walls. Gore submitted a one-page estimate captioned "Engineering/survey proposal for Dr. David Miolen." It proposes a charge of$5,000 for "retaining wall design" for the upper wall, and the same amount for the lower wall, for a total of $10,000. Significantly, defendant did not further utilize Gore's engineering services, but he did present Gore's proposal to plaintiffs and requested a $10,000 payment. Plaintiffs wrote defendant a $5,000 check on the spot, and later paid the remaining $5,000 after receiving an invoice from defendant.

Defendant hired professional engineer William Lamb to prepare plans and specifications for the lower wall. Lamb charged $1,200 for his plans. Defendant testified that in constructing the lower wall, he deviated from the plans in certain regards, substituting materials in some instances. He further stated that any changes he made resulted in either the functional equivalent of what was called for in Lamb's plans, or a better and stronger alternative. Several years after the lower wall was completed, Lamb inspected it and conducted a complete geotechnical and structural analysis. He certified that the lower wall was stable, safe, and functioning as intended.

While the project was ongoing, plaintiffs decided they wanted to significantly expand it. Regarding the additional work and materials requested, the trial court found as follows:

The project expanded in scope at the direction of[plaintiffs], including but not limited to, the existing patio under the deck which was changed from concrete to pavers, the addition of the kitchen, the location of the fireplace, the extension of the upper retaining wall behind the kitchen and fireplace, the addition of the stairs from the pool deck to the driveway, the location ofthe pool equipment room, and the expansion ofthe pool paver deck.

There is no written agreement addressing these additional items. Both parties testified that they agreed plaintiffs would pay for the additional stone pavers at a rate of eight dollars per square foot.

Plaintiffs experienced problems with the upper wall, including erosion and drainage issues. When it rained, water would pour out ofjoints in the wall and pool on the paved entertainment area below. Dissatisfied with defendant's work on the upper wall, plaintiffs hired Fischer Landscaping to demolish and replace the upper wall and the stairs leading from the house to the pool area, at a cost of$40,174.

Plaintiffs were also unhappy with the material that defendant used to fill the joints between stone pavers. They thought that the joints should be filled with impermeable

-5- polymeric sand instead of the material used. Defendant testified that the entire drainage system for the pool area depended on water being able to drain through the permeable joints, so the use of polymeric sand would not be feasible. The disagreement over the paving system became heated, and plaintiffs ordered defendant off the property when the project was mostly but not entirely complete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Audio Visual Artistry v. Stephen Tanzer
403 S.W.3d 789 (Court of Appeals of Tennessee, 2012)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
COLUMBUS MEDICAL SERVICES, LLC v. Thomas
308 S.W.3d 368 (Court of Appeals of Tennessee, 2009)
Tucker v. Sierra Builders
180 S.W.3d 109 (Court of Appeals of Tennessee, 2005)
Wilson v. Esch
166 S.W.3d 729 (Court of Appeals of Tennessee, 2004)
Murfreesboro Medical Clinic, P.A. v. Udom
166 S.W.3d 674 (Tennessee Supreme Court, 2005)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
Vantage Technology, LLC v. Cross
17 S.W.3d 637 (Court of Appeals of Tennessee, 1999)
Cloud Nine, LLC v. Whaley
650 F. Supp. 2d 789 (E.D. Tennessee, 2009)
Hennessee v. Wood Group Enterprises, Inc.
816 S.W.2d 35 (Court of Appeals of Tennessee, 1991)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
David Miolen v. Doug Saffles, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-miolen-v-doug-saffles-tennctapp-2019.