Dave's Excavating, Inc. v. City of New Castle

959 N.E.2d 369, 2012 Ind. App. LEXIS 6, 2012 WL 77641
CourtIndiana Court of Appeals
DecidedJanuary 11, 2012
Docket33A04-1104-PL-199
StatusPublished
Cited by9 cases

This text of 959 N.E.2d 369 (Dave's Excavating, Inc. v. City of New Castle) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dave's Excavating, Inc. v. City of New Castle, 959 N.E.2d 369, 2012 Ind. App. LEXIS 6, 2012 WL 77641 (Ind. Ct. App. 2012).

Opinion

OPINION

NAJAM, Judge.

STATEMENT OF THE CASE

Liberty Mutual Insurance Company (“Liberty Mutual”) appeals two orders en *372 tered by the trial court granting summary judgment in favor of the City of New Castle (“the City”) in its suit against Dave’s Excavating, Inc. (“Dave’s”) on a construction contract and against Liberty Mutual under a performance bond. Liberty Mutual presents four issues for review, which we restate as:

1. Whether the trial court erred when it granted summary judgment in favor of the City on the issue of Dave’s’ liability under the construction contract.
2. Whether the trial court erred when it granted summary judgment in favor of the City on the issue of Liberty Mutual’s liability under the performance bond.
3. Whether the trial court erred when it granted summary judgment in favor of the City and awarded attorney’s fees.

We affirm.

FACTS AND PROCEDURAL HISTORY

On February 9, 2004, the City accepted bids for a sanitation project in the recently annexed McGrew Sanitation Area for a sanitary sewer and watermain extension (“the Project”). The bidders were informed that the engineer’s estimated cost was $1,319,279. Dave’s was the lowest bidder at $983,737.61. 1 On March 5, 2004, the City and Dave’s executed a construction contract for the Project (“the contract”) 2 Liberty Mutual guarantied Dave’s performance with its performance bond (“the performance bond” or “the bond”).

After the Project was underway, Dave’s requested change orders. In one instance, the City allowed Dave’s to use excavated materials as backfill to reduce additional costs arising from the nature of subsurface conditions. Then, on June 17, 2004, Dave’s sent a letter to the engineer “declaring ‘Differing Subsurface Conditions’ in accordance with Section 4.03 of the General Conditions!.]” Appellant’s App. at 140. Dave’s also stated that it was “stop[ping] Work until direction has been received by [sic] the Engineer.” Id. Section 4.03 of the General Conditions provides:

4.03 Differing Subsurface or Physical Conditions
A. Notice: If CONTRACTOR [Dave’s] believes that any subsurface or physical condition at or contiguous to the Site that is uncovered or revealed either:
1. is of such a nature as to establish that any “technical data” on which CONTRACTOR is entitled to rely as provided in paragraph 4.02 is materially inaccurate; or
2. is of such a nature as to require a change in the Contract Documents; or
3. differs materially from that shown or indicated in the Contract Documents; or
4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents;
*373 then CONTRACTOR shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical condition or perform any Work in connection therewith ... notify OWNER and ENGINEER in writing about such condition. CONTRACTOR shall not further disturb such condition or perform any Work in connection therewith ... until receipt of written order to do so.
B. ENGINEER’S Review: After receipt of written notice as required by paragraph 4.03.A, ENGINEER will promptly review the pertinent condition, determine the necessity of OWNER’S obtaining additional exploration or tests with respect thereto, and advise OWNER in writing (with a copy to CONTRACTOR) of ENGINEER’S findings and conclusions.

Appellant’s App. at 490. Dave’s followed its June 17 letter with another letter on June 22, requesting a contract price increase to $1,807,960.73, an eighty-four percent increase, to complete work under the construction contract due to the alleged differing subsurface conditions at part of the Project site.

The Project’s engineer replied by letter dated July 6, informing Dave’s that the engineer was reviewing the claim of differing subsurface or physical conditions. The letter also referred Dave’s to Article 6, Paragraph 18 of the General Conditions, which provides in relevant part that

CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15.04 or as OWNER and CONTRACTOR may otherwise agree in writing.

Appellant’s App. at 503. The engineer’s letter stated further that it was “to serve as [Dave’s] written notice that in accordance with the Contract Documents, Dave’s is not to delay or postpone work on the Project during resolution of [the] claim. Please recommence work immediately.” Id. at 347. Counsel for Dave’s replied on July 7 that “it is not possible for the work to be recommenced until the differing condition issue ha[d] been resolved.” Id. at 348. Dave’s also stated that the engineer’s failure to investigate and propose a change order “renders the City in default of the contract, and allows Dave’s Excavating, Inc. the opportunity to rescind the contract, cease work, and avoid any further liability.” Id. at 348.

The engineer replied on July 9, stating in part:

Please be aware that [neither] we nor the City agree with the interpretation of your legal council [sic] that you can refuse to re-commence work on the project on Monday!,] July 12 as previously agreed. There will be no additional tests or other subsurface investigation provided by the Owner as such investigation was otherwise your responsibility if deemed necessary prior to committing to the Contract Price and Time. ... The City has also advised our office to inform you that they [sic] will consider you in breach of this Contract if you are not present and working on the project at 8:00 a.m. local time on July 12, 2004[,] and will be pursuing your bond as well as other available legal remedies that may be appropriate.

Id. at 146 (emphasis added). Dave’s completed work on the Project in all areas except those related to the change order requests, but the City and Dave’s could not reach an agreement about the change orders based on the differing subsurface conditions claim.

*374 On July 15, the engineer sent notice to Dave’s and Liberty Mutual that the City was considering declaring Dave’s in default on the construction contract. That letter also requested a meeting within fifteen days in accordance with paragraph 3.1 of the performance bond. On July 19, the City’s Board of Works and Safety voted to declare the Project an emergency and to solicit bids from other contractors to complete the Project. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
959 N.E.2d 369, 2012 Ind. App. LEXIS 6, 2012 WL 77641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daves-excavating-inc-v-city-of-new-castle-indctapp-2012.