Darin & Armstrong, Inc. v. United States Environmental Protection Agency

431 F. Supp. 456, 23 Cont. Cas. Fed. 81,620, 9 ERC 1337, 1976 U.S. Dist. LEXIS 14447
CourtDistrict Court, N.D. Ohio
DecidedJune 24, 1976
StatusPublished
Cited by5 cases

This text of 431 F. Supp. 456 (Darin & Armstrong, Inc. v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Darin & Armstrong, Inc. v. United States Environmental Protection Agency, 431 F. Supp. 456, 23 Cont. Cas. Fed. 81,620, 9 ERC 1337, 1976 U.S. Dist. LEXIS 14447 (N.D. Ohio 1976).

Opinion

*458 MEMORANDUM AND OPINION

MANOS, District Judge.

On May 20, 1976 the plaintiff, Darin & Armstrong, Inc. [hereinafter Darin], initiated this action under 5 U.S.C. §§ 701-706 to obtain judicial review of a final order 1 issued by the Regional Administrator of the United States Environmental Protection Agency, Region V [hereinafter EPA] concerning a bid protest prosecuted by defendant Blount Brothers, Incorporated [hereinafter Blount], 2 and to enjoin the Cleveland Regional Sewer District [hereinafter CRSD] from implementing the EPA’s ruling. At the same time that Darin filed the complaint it moved the court for a temporary restraining order and a preliminary injunction enjoining the CRSD from implementing the EPA’s ruling. The court granted Darin’s motion for a temporary restraining order on May 20, 1975, pursuant to Fed.R.Civ.P. 65(b). 3 On May 28, 1976 the court ordered a consolidation of the merits of Darin’s appeal with Darin’s request for a preliminary injunction, and the court extended the temporary restraining order to permit the parties to submit briefs on the merits of the appeal. 4 After all the briefs were filed, Darin and the CRSD stipulated to an extension of the temporary restraining order. 5

I.

FACTUAL BACKGROUND

On May 12, 1975 the EPA awarded a construction grant, denominated EPA Project No. C390051-02, to the CRSD under 33 U.S.C. § 1251, et seq., for 75% of the cost of a proposed wastewater treatment facility for the west side of Cleveland. The estimated cost of the total project was $87,000,000 of which EPA would pay $65,000,000, provided that CRSD’s procurement procedure met the requirements of 40 C.F.R. § 35.936, et seq., and that the construction of the project commenced within a year and a half from the date of the grant. 6

After receiving the grant the CRSD formally advertised for bids from prospective general contractors including Darin and Blount. The CRSD’s original Invitation For Bids [IFB] required the general contractor to whom the contract is awarded to perform 42% of the total contract with his own forces and to sublet no more than 58% of the contract to subcontractors. 7 The first bids from general contractors were received by CRSD on August 14, 1975, and it determined that Blount was the apparent low bidder. 8 A protest was made to the CRSD by Darin and others charging that Blount’s bid was non-responsive to the IFB. The protesters argued, inter alia, that the IFB required each bidder to fully detail in *459 the “List of Proposed Subcontracts” 9 [LPS-1] all work which Blount expected to subcontract. The protesters also argued that the “List of Subcontracts” [LPS-1] was the only document in which a bidder could state a comprehensive list of subcontracted work. 10

After the first opening of bids Blount, in its brief before the CRSD, argued that the IFB demanded bidders to demonstrate compliance with the 42% requirement in the “List of Proposed Subcontractors ” [LPS-2], which was to be filed subsequent to the opening of bids. In the alternative, Blount argued that its failure to show compliance with the subcontracting limitation in the LPS-1 form which was attached to its bid was a mere informality, which did not substantially affect the bid, and was therefore waivable by CRSD. Blount argued:

“It is obvious from the bid documents that the primary purpose in obtaining the subcontract information is to determine that the general contractor will perform at least 42% of the contract work. That determination cannot be made from the list of ‘Proposed Subcontracts (items of work),’ [LPS-1] but can only be made from the list of ‘Proposed Subcontractors’ [LPS-2] with prices which are due within 72 hours . . . . In any event, if the listing ‘proposed subcontracts’ was an informality, which Blount denies, it is obviously one which the district can and should waive.” 11

The record currently before this court does not indicate whether Blount’s August, 1975 analysis of the terms of the IFB was accepted or rejected by either CRSD or EPA. The protest to the CRSD’s determination that Blount was the apparent low bidder on the first solicitation for bids resulted in CRSD’s rejection of all bids, and that decision was sustained by EPA in November, 1975. 12

Subsequently CRSD readvertised for general contractors, and a second set of bids were received on February 3,1976, at which time the CRSD, without awarding the contract, determined that the three apparent low bidders were:

Darin $67,300,000

Blount $68,537,000

Joint Venture $68,963,000 13

Blount immediately protested to CRSD 14 that Darin’s bid was nonresponsive to the IFB, on the theory that it failed to properly show compliance with the 42% no-subcontracting requirement. Blount argued, in total contravention of its earlier position, 15 that the Listing of Prospective Subcontracts [LPS-1] was the only place where the IFB permitted a bidder to show compliance with the 42% rule and that Darin’s LPS-1 failed to make the requisite showing. Despite the supplementary document which Darin filed with CRSD on February 18,1976, showing that its bid was calculated to conform to the 42% of no-subcontracting restriction, 16 Blount argued that Darin’s second bid was unresponsive.

The CRSD reviewed the bid documents and on March 8, 1976, it rejected Blount’s protest expressly finding that the IFB permitted an apparent low bidder to demon *460 strate compliance with the 42% no-subcontracting rule by reference to its additional submissions to the CRSD. 17 The rejection of Blount’s protest came after the general counsel to CRSD 18 and the project director 19

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stewart v. US Ex Rel. Dept. of Agriculture
639 F. Supp. 2d 1190 (D. Oregon, 2009)
Sovereign Const. Co., Ltd. v. City of Philadelphia
439 F. Supp. 692 (E.D. Pennsylvania, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
431 F. Supp. 456, 23 Cont. Cas. Fed. 81,620, 9 ERC 1337, 1976 U.S. Dist. LEXIS 14447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/darin-armstrong-inc-v-united-states-environmental-protection-agency-ohnd-1976.