Dana Ltd. v. Sypris Technologies, Inc.
Opinion
IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT
LUCAS COUNTY
Dana Limited Court of Appeals No. L-15-1058 Appellee Trial Court No. CI0201401138 v. Sypris Technologies, Inc. DECISION AND JUDGMENT Appellant Decided: December 18, 2015
*****
J. Daniel Sharp, Cary Rodman Cooper, David Rodman Cooper and Margaret J. Lockhart, for appellee.
James P. Silk, Jr., John F. Hartmann and Erica Zolner, for appellant.
*****
PIETRYKOWSKI, J.
{¶ 1} Appellant Sypris Technologies, Inc. (Sypris) appeals the March 4, 2015 judgment of the Lucas County Court of Common Pleas which granted appellee Dana Limited’s (Dana) motion for judgment on the pleadings or summary judgment on its complaint for declaratory judgment. The court declared that the July 2013 document at issue was not a binding contract between the parties and, thus, Dana was not required to submit to arbitration to resolve the dispute. Because we agree that a binding agreement was not formed, we affirm.
{¶ 2} Sypris and Dana have a business relationship dating back to 2001. Sypris has supplied Dana with driveline components including axle shafts, gear sets, knuckles, I-beams, carriers, differential cases, etc., for use in light, medium, and heavy-duty trucks pursuant to multi-year, sole-sourced contracts. In 2007, the parties entered into a supply agreement stemming from Dana’s bankruptcy proceedings including litigation and arbitration involving Sypris. The agreement, which was approved by the bankruptcy court, was for approximately 2,000 automotive part numbers (approximately 2 million units per year) to be supplied to Dana through December 31, 2014.
{¶ 3} The agreement provided that the parties, 24 months prior to the expiration of the contract term, could “negotiate in good faith to enter into an extension of this agreement for a renewal period agreed upon by the parties.” The agreement also provided that Dana, “on or after July 1, 2013,” could enter into long-term contracts for the parts provided for in the agreement with third parties.
{¶ 4} Pursuant to the agreement, in 2012, the parties began negotiating an extension. Negotiations continued and on July 2, 2013, the parties reached what was characterized as a “handshake agreement” with most of the material components agreed upon. The parties continued working toward a finalized agreement and on July 16, 2013, a draft agreement was signed which provided:
DRAFT-SUBJECT TO FURTHER REVISION AMENDED AND RESTATED SUPPLY AGREEMENT This Amended and Restated Supply Agreement (the “Agreement”)
is made effective as of the execution of Exhibit A hereto (the “Effective Date”), by and between Dana Corporation [handwritten Limited inserted]
(“Dana”) and Sypris Technologies, Inc. (“Sypris”).
{¶ 5} Exhibit A, attached to the body of the agreement stated:
DRAFT-SUBJECT TO FURTHER REVISION EXHIBIT A- EXISTING PARTS To be supplied by mutual agreement of the Parties as a precondition to the effectiveness of this Agreement. If such mutual agreement has not been reached on or before July 26, 2013, then this Amended and Restated Agreement shall be deemed null and void, unless separately re-executed, and the underlying Agreement shall otherwise remain in full force and effect.
{¶ 6} Also attached was “EXHIBIT B-LENGTH OF WARRANTY FOR LIGHT DUTY TRUCK PARTS” and “EXHIBIT 1-FIVE YEAR FORECAST” which identically stated: “To be supplied by mutual agreement of the parties as a precondition to the effectiveness of this Agreement.”
{¶ 7} With the July 26 expiration of the draft agreement nearing, the parties attempted to resolve disputes regarding the parts and pricing schedules and whether the agreement would include an additional tube assembly product. Sypris requested an extension until August 9, 2013; Dana refused to agree to the extension. Pursuant to the 2007 supply agreement, on August 26, 2013, Dana sent Sypris written notice of its decision not to extend the agreement expiring on December 31, 2014.
{¶ 8} On November 25, 2013, Sypris served Dana a notice of arbitration pursuant to the 2007 agreement and the July 16, 2013 agreement which contained identical arbitration clauses. The clauses provided:
27. Dispute resolution. If either party has a dispute with regard to contractual issues under this Agreement and is unable to successfully resolve those issues with the other party, the other party shall have the right to initiate mediation and binding arbitration in accordance with the following: (i) in the case of mediation, the Model Procedure for Mediation of Business Disputes of the Center for Public Resources and (ii) in the case of arbitration, the CPR Rules for Non-Administered Arbitration of Business Disputes (“CPR”).
{¶ 9} In its request for arbitration, Sypris claimed that Dana breached the July 16, 2013 agreement which was finalized shortly thereafter and failed to act in good faith regarding negotiations. Sypris sought an award of compensatory damages and costs and fees.
{¶ 10} On January 17, 2014, Dana commenced this declaratory judgment action requesting that the court determine that no new contract was formed between Dana and
Sypris as a result of the July 2013 draft agreement. Dana attached to its complaint the 2007 supply agreement, the July 16, 2013 draft agreement, and its August 26, 2013 notice of intent not to renew the supply agreement. In its answer, Sypris agreed that the July 16, 2013 draft agreement “speaks for itself.” Sypris denied, however, that the condition precedent to its characterization as a binding contract was not met. Regarding Dana’s request for declaratory judgment, Sypris argued that the question of contract formation was one for a jury and that “Dana is entitled only to a determination of whether the July 16 Agreement contains a binding arbitration provision.”
{¶ 11} Sypris asserted a counterclaim for declaratory relief as to whether Dana was bound to arbitrate Sypris’ claims for breach of the July 16 agreement. Sypris included a jury demand.
{¶ 12} On October 7, 2014, Dana filed a motion for judgment on the pleading or, alternatively, a motion for summary judgment. In its motion, Dana argued that the draft agreement was not binding under Ohio law and, thus, Dana was not bound to the arbitration provision. In opposition, Sypris contended that the document’s designation as a draft does not prevent it from a binding agreement on the parties. Sypris further contended that Dana’s position in the case was inconsistent with it stance in pending litigation, Dana Ltd. v. Grede Holdings, LLC, Lucas C.P. No. CI0201403963, involving a similar supply agreement.
{¶ 13} A hearing on the motion was held on February 10, 2015. The parties engaged in extensive arguments regarding their respective positions; the court also posed several questions.
{¶ 14} On March 4, 2015, with little discussion, the trial court granted Dana’s motion finding that “Plaintiff is entitled, as a matter of law, to a declaratory judgment that the July 2013 Document is not a valid and binding contract between the parties * * *.” This appeal followed with Sypris raising the following assignment of error:
The trial court erred in determining as a matter of law that Appellant Sypris Technologies, Inc. (“Sypris”) and Appellee Dana Limited (“Dana”)
did not form a contract for arbitration on or about July 16, 2013.
{¶ 15} In Sypris’ sole assignment of error, it contends that the trial court erred because issues of fact regarding whether a contract was formed precluded summary dismissal of the case. Sypris’ position is that the July 16 agreement was intended to be binding on the parties. Conversely, Dana asserts that the clear language of the draft agreement demonstrates that it was subject to revisions, was missing key components and, thus, was not binding on the parties.
Free access — add to your briefcase to read the full text and ask questions with AI
2015 Ohio 5311 (Dana Ltd. v. Sypris Technologies, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.