Dana Ltd. v. Sypris Technologies, Inc.

2015 Ohio 5311
CourtOhio Court of Appeals
DecidedDecember 18, 2015
DocketL-15-1058
StatusPublished

This text of 2015 Ohio 5311 (Dana Ltd. v. Sypris Technologies, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dana Ltd. v. Sypris Technologies, Inc., 2015 Ohio 5311 (Ohio Ct. App. 2015).

Opinion

[Cite as Dana Ltd. v. Sypris Technologies, Inc., 2015-Ohio-5311.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT LUCAS COUNTY

Dana Limited Court of Appeals No. L-15-1058

Appellee Trial Court No. CI0201401138

v.

Sypris Technologies, Inc. DECISION AND JUDGMENT

Appellant Decided: December 18, 2015

*****

J. Daniel Sharp, Cary Rodman Cooper, David Rodman Cooper and Margaret J. Lockhart, for appellee.

James P. Silk, Jr., John F. Hartmann and Erica Zolner, for appellant.

PIETRYKOWSKI, J.

{¶ 1} Appellant Sypris Technologies, Inc. (Sypris) appeals the March 4, 2015

judgment of the Lucas County Court of Common Pleas which granted appellee Dana

Limited’s (Dana) motion for judgment on the pleadings or summary judgment on its

complaint for declaratory judgment. The court declared that the July 2013 document at issue was not a binding contract between the parties and, thus, Dana was not required to

submit to arbitration to resolve the dispute. Because we agree that a binding agreement

was not formed, we affirm.

{¶ 2} Sypris and Dana have a business relationship dating back to 2001. Sypris

has supplied Dana with driveline components including axle shafts, gear sets, knuckles,

I-beams, carriers, differential cases, etc., for use in light, medium, and heavy-duty trucks

pursuant to multi-year, sole-sourced contracts. In 2007, the parties entered into a supply

agreement stemming from Dana’s bankruptcy proceedings including litigation and

arbitration involving Sypris. The agreement, which was approved by the bankruptcy

court, was for approximately 2,000 automotive part numbers (approximately 2 million

units per year) to be supplied to Dana through December 31, 2014.

{¶ 3} The agreement provided that the parties, 24 months prior to the expiration of

the contract term, could “negotiate in good faith to enter into an extension of this

agreement for a renewal period agreed upon by the parties.” The agreement also

provided that Dana, “on or after July 1, 2013,” could enter into long-term contracts for

the parts provided for in the agreement with third parties.

{¶ 4} Pursuant to the agreement, in 2012, the parties began negotiating an

extension. Negotiations continued and on July 2, 2013, the parties reached what was

characterized as a “handshake agreement” with most of the material components agreed

upon. The parties continued working toward a finalized agreement and on July 16, 2013,

a draft agreement was signed which provided:

2. DRAFT-SUBJECT TO FURTHER REVISION

AMENDED AND RESTATED SUPPLY AGREEMENT

This Amended and Restated Supply Agreement (the “Agreement”)

is made effective as of the execution of Exhibit A hereto (the “Effective

Date”), by and between Dana Corporation [handwritten Limited inserted]

(“Dana”) and Sypris Technologies, Inc. (“Sypris”).

{¶ 5} Exhibit A, attached to the body of the agreement stated:

DRAFT-SUBJECT TO FURTHER REVISION

EXHIBIT A- EXISTING PARTS

To be supplied by mutual agreement of the Parties as a precondition

to the effectiveness of this Agreement. If such mutual agreement has not

been reached on or before July 26, 2013, then this Amended and Restated

Agreement shall be deemed null and void, unless separately re-executed,

and the underlying Agreement shall otherwise remain in full force and

effect.

{¶ 6} Also attached was “EXHIBIT B-LENGTH OF WARRANTY FOR LIGHT

DUTY TRUCK PARTS” and “EXHIBIT 1-FIVE YEAR FORECAST” which identically

stated: “To be supplied by mutual agreement of the parties as a precondition to the

effectiveness of this Agreement.”

{¶ 7} With the July 26 expiration of the draft agreement nearing, the parties

attempted to resolve disputes regarding the parts and pricing schedules and whether the

3. agreement would include an additional tube assembly product. Sypris requested an

extension until August 9, 2013; Dana refused to agree to the extension. Pursuant to the

2007 supply agreement, on August 26, 2013, Dana sent Sypris written notice of its

decision not to extend the agreement expiring on December 31, 2014.

{¶ 8} On November 25, 2013, Sypris served Dana a notice of arbitration pursuant

to the 2007 agreement and the July 16, 2013 agreement which contained identical

arbitration clauses. The clauses provided:

27. Dispute resolution. If either party has a dispute with regard to

contractual issues under this Agreement and is unable to successfully

resolve those issues with the other party, the other party shall have the right

to initiate mediation and binding arbitration in accordance with the

following: (i) in the case of mediation, the Model Procedure for Mediation

of Business Disputes of the Center for Public Resources and (ii) in the case

of arbitration, the CPR Rules for Non-Administered Arbitration of Business

Disputes (“CPR”).

{¶ 9} In its request for arbitration, Sypris claimed that Dana breached the July 16,

2013 agreement which was finalized shortly thereafter and failed to act in good faith

regarding negotiations. Sypris sought an award of compensatory damages and costs and

fees.

{¶ 10} On January 17, 2014, Dana commenced this declaratory judgment action

requesting that the court determine that no new contract was formed between Dana and

4. Sypris as a result of the July 2013 draft agreement. Dana attached to its complaint the

2007 supply agreement, the July 16, 2013 draft agreement, and its August 26, 2013 notice

of intent not to renew the supply agreement. In its answer, Sypris agreed that the July 16,

2013 draft agreement “speaks for itself.” Sypris denied, however, that the condition

precedent to its characterization as a binding contract was not met. Regarding Dana’s

request for declaratory judgment, Sypris argued that the question of contract formation

was one for a jury and that “Dana is entitled only to a determination of whether the

July 16 Agreement contains a binding arbitration provision.”

{¶ 11} Sypris asserted a counterclaim for declaratory relief as to whether Dana

was bound to arbitrate Sypris’ claims for breach of the July 16 agreement. Sypris

included a jury demand.

{¶ 12} On October 7, 2014, Dana filed a motion for judgment on the pleading or,

alternatively, a motion for summary judgment. In its motion, Dana argued that the draft

agreement was not binding under Ohio law and, thus, Dana was not bound to the

arbitration provision. In opposition, Sypris contended that the document’s designation as

a draft does not prevent it from a binding agreement on the parties. Sypris further

contended that Dana’s position in the case was inconsistent with it stance in pending

litigation, Dana Ltd. v. Grede Holdings, LLC, Lucas C.P. No. CI0201403963, involving

a similar supply agreement.

5. {¶ 13} A hearing on the motion was held on February 10, 2015. The parties

engaged in extensive arguments regarding their respective positions; the court also posed

several questions.

{¶ 14} On March 4, 2015, with little discussion, the trial court granted Dana’s

motion finding that “Plaintiff is entitled, as a matter of law, to a declaratory judgment that

the July 2013 Document is not a valid and binding contract between the parties * * *.”

This appeal followed with Sypris raising the following assignment of error:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inland Bulk Transfer Co. v. Cummins Engine Co.
332 F.3d 1007 (Sixth Circuit, 2003)
Brown v. Lagrange Dev. Corp.
2015 Ohio 133 (Ohio Court of Appeals, 2015)
Hussein v. Hafner & Shugarman Enterprises, Inc.
890 N.E.2d 356 (Ohio Court of Appeals, 2008)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Graham v. Drydock Coal Co.
667 N.E.2d 949 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)
Williams v. Aetna Finance Co.
83 Ohio St. 3d 464 (Ohio Supreme Court, 1998)
Specht v. Netscape Communications Corp.
306 F.3d 17 (Second Circuit, 2002)
Adams v. Suozzi
433 F.3d 220 (Second Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2015 Ohio 5311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dana-ltd-v-sypris-technologies-inc-ohioctapp-2015.