Dalton Moran Shook Inc. v. Pitt Development Co.

440 S.E.2d 585, 113 N.C. App. 707, 1994 N.C. App. LEXIS 209
CourtCourt of Appeals of North Carolina
DecidedMarch 1, 1994
Docket923SC1272
StatusPublished
Cited by11 cases

This text of 440 S.E.2d 585 (Dalton Moran Shook Inc. v. Pitt Development Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dalton Moran Shook Inc. v. Pitt Development Co., 440 S.E.2d 585, 113 N.C. App. 707, 1994 N.C. App. LEXIS 209 (N.C. Ct. App. 1994).

Opinion

*710 MARTIN, Judge.

I.

Defendants have moved to dismiss plaintiffs appeal on the grounds that it is from an interlocutory order and is premature. Where an order of summary judgment disposes of fewer than all claims between all parties the order is interlocutory and, ordinarily, is not immediately appealable. Love v. Moore, 305 N.C. 575, 578, 291 S.E.2d 141, 144 (1982); Veazy v. Durham, 231 N.C. 357, 57 S.E.2d 377, reh’g denied, 232 N.C. 744, 59 S.E.2d 429 (1950). The trial court’s summary judgment in this case is an interlocutory order because it only disposed of plaintiff’s claims against defendants Wachovia and' Hill and did not dispose of plaintiff’s claims against the other defendants.

There are, however, two instances in which an interlocutory order may be appealed. First, a trial judge may enter a final judgment as to one or more but fewer than all of the claims or parties in a case, which is immediately appealable even though the litigation is not complete as to all claims or all parties, if the trial judge makes an express finding that there is no just reason for delay. N.C. Gen. Stat. § 1A-1, Rule 54(b) (1990); Industries, Inc. v. Insurance Co., 296 N.C. 486, 251 S.E.2d 443 (1979); Brown v. Brown, 77 N.C. App. 206, 334 S.E.2d 506 (1985), disc. review denied, 315 N.C. 389, 338 S.E.2d 878 (1986). In this case, the trial court made no such finding, so no appeal is available under Rule 54(b). Second, an interlocutory order not appealable under Rule 54(b) may nevertheless be appealed pursuant to G.S. § 1-277 and G.S. § 7A-27(d) which permit an appeal of an interlocutory order which (1) affects a substantial right, or (2) in effect determines the action and prevents a judgment from which appeal might be taken, or (3) discontinues the action, or (4) grants or refuses a new trial. An appeal of an interlocutory order is permitted under the “substantial right” exception of the two statutes when the interlocutory ruling deprives the appellant of a substantial right which may be lost or prejudiced if not reviewed prior to final judgment. Faircloth v. Beard, 320 N.C. 505, 358 S.E.2d 512 (1987).

Our Supreme Court has held that the right to avoid the possibility of two trials on the same issues can be a substantial right so as to warrant an immediate appeal under G.S. § 1-277 and G.S. § 7A-27(d). Green v. Duke Power Co., 305 N.C. 603, 290 S.E.2d 593 (1982). Plaintiff contends that its claims against Wachovia and *711 Hill involve issues of fact common to its claims against the other defendants and that if this appeal is dismissed, separate trials will be required to determine the identical issues. We agree.

Generally, a party supplying materials or labor, including professional design or surveying services, pursuant to a contract with the owner of real property for the making of improvements thereon, may obtain a lien on the property so improved to secure payment of debts for the materials furnished, labor done or professional services rendered. N.C. Gen. Stat. § 44A-8. To perfect such a lien, the lien must be filed in the county where the property is located within 120 days from the last furnishing of labor, services or materials. N.C. Gen. Stat. § 44A-12. An action to enforce the lien must be instituted within 180 days of the last furnishing of materials or labor. N.C. Gen. Stat. § 44A-13. The priority of a materialman’s lien is determined according to the date of the first furnishing of labor, etc., at the site of the improvement. N.C. Gen. Stat. § 44A-10.

Thus, to enforce its lien against the several defendants, plaintiff must establish with regard to each, that it: (1) furnished architectural and engineering services pursuant to a contract with the property owner for which it has not been fully compensated, (2) filed its lien within 120 days of the last furnishing of such services, and (3) filed its action to enforce the lien within 180 days of the last furnishing of such services. The foregoing issues are identical with respect to each defendant because plaintiff performed its services pursuant to a single contract with Pitt.

In addition, should plaintiff successfully enforce its lien against more than one defendant, the lien must be apportioned among the several defendants. In Dail Plumbing v. Roger Baker & Assoc., 64 N.C. App. 682, 308 S.E.2d 452 (1983), disc. review denied, 310 N.C. 152, 311 S.E.2d 296 (1984), the plaintiff contracted with the owner of a multi-unit office condominium project to provide plumbing equipment, materials and labor for construction of the project. The owner did not pay the plaintiff the entire amount due. The owner then sold one of the condominium units. The plaintiff filed a lien and a suit to enforce the lien. The owner filed bankruptcy and the plaintiff sought to enforce the lien for the full balance owed against the single unit which had been sold. We held that where the separate units were owned by different parties, the plaintiff’s “blanket lien” should be apportioned among the units based upon the proportionate share of labor and materials furnished *712 to each unit, and its proportionate part of labor and materials furnished to the common area, under the contract that is the subject of the lien. Id.; see also, Chadbourn v. Williams, 71 N.C. 444 (1874); 68 A.L.R.3d 1300, 1303.

In the present case, plaintiff furnished architectural and engineering services for the entire shopping center project. Which of these services are attributable to an individual defendant’s property and which are attributable to common areas are issues common to plaintiff’s claims against each defendant which should be determined in a single proceeding. Thus, dismissal of the present appeal might prejudice plaintiff’s right to avoid separate trials involving the identical issues. Therefore, defendants’ motion to dismiss plaintiff’s appeal is denied.

II.

We now consider the propriety of summary judgment in favor of defendants Wachovia and Hill. Those defendants asserted, as a defense to plaintiff’s suit to enforce its lien against that portion of the property conveyed to Wachovia by the foreclosure deed, that the doctrine of instantaneous seisin operated to subordinate plaintiff’s lien to Wachovia’s deed of trust.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Exum v. Exum
Court of Appeals of North Carolina, 2014
Tands, Inc. v. Coastal Plains Realty, Inc.
686 S.E.2d 164 (Court of Appeals of North Carolina, 2009)
In Re Gilmer
416 B.R. 187 (M.D. North Carolina, 2009)
Dw Flowe & Son, Inc. v. CDC, LLC
654 S.E.2d 83 (Court of Appeals of North Carolina, 2007)
West Durham Lumber Company v. Meadows
635 S.E.2d 301 (Court of Appeals of North Carolina, 2006)
Capps v. NW Sign Industries of North Carolina, Inc.
614 S.E.2d 552 (Court of Appeals of North Carolina, 2005)
RSN Properties, Inc. v. Jones
609 S.E.2d 498 (Court of Appeals of North Carolina, 2005)
Lovelace v. City of Shelby
570 S.E.2d 136 (Court of Appeals of North Carolina, 2002)
Phillips v. Restaurant Management of Carolina, L.P.
552 S.E.2d 686 (Court of Appeals of North Carolina, 2001)
Allen v. Sea Gate Ass'n, Inc.
460 S.E.2d 197 (Court of Appeals of North Carolina, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
440 S.E.2d 585, 113 N.C. App. 707, 1994 N.C. App. LEXIS 209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dalton-moran-shook-inc-v-pitt-development-co-ncctapp-1994.