Dakota Energy Coop, Inc. v. East River Electric Power Coop., Inc.

75 F.4th 870
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 28, 2023
Docket22-1884
StatusPublished

This text of 75 F.4th 870 (Dakota Energy Coop, Inc. v. East River Electric Power Coop., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dakota Energy Coop, Inc. v. East River Electric Power Coop., Inc., 75 F.4th 870 (8th Cir. 2023).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 22-1884 ___________________________

Dakota Energy Cooperative, Inc.

Plaintiff - Appellant

v.

East River Electric Power Cooperative, Inc.

Defendant - Appellee

Basin Electric Power Cooperative

Intervenor Defendant - Appellee

------------------------------

Next Generation Cooperative Alliance; Geoffrey F. Heffernan; Jeremy D. Weinstein

Amici on Behalf of Appellant(s) ____________

Appeal from United States District Court for the District of South Dakota - Southern ____________

Submitted: November 15, 2022 Filed: July 28, 2023 ____________

Before BENTON, KELLY, and ERICKSON, Circuit Judges. ____________ KELLY, Circuit Judge.

Dakota Energy Power Cooperative, Inc., a member of East River Electric Power Cooperative, Inc., sought to withdraw from East River and to terminate the parties’ long-term power contract so that it could purchase electricity from another source. When East River resisted, Dakota Energy sued for anticipatory breach of contract and sought a declaratory judgment providing that it had a contractual right to withdraw from East River by way of a buyout. The district court 1 granted summary judgment in favor of East River, and Dakota Energy appeals.

I.

Dakota Energy is a South Dakota-based electric distribution cooperative that provides electricity to its rural consumer-members. East River is a South Dakota generation and transmission cooperative that purchases electricity wholesale and then resells it to its members, including Dakota Energy.

When Dakota Energy became a member of East River in 1995, the two parties entered into a long-term power supply agreement known as a wholesale power contract (WPC). The WPC provides that

East River shall sell and deliver to [Dakota Energy] and [Dakota Energy] shall purchase and receive from East River, all electric power and energy which [Dakota Energy] shall require to serve all of [its] electric loads, to the extent that East River shall have such power and energy and facilities available.

The WPC describes the “terms, conditions, and rates for the furnishing of electric power” under the agreement and explains that the rates paid by Dakota Energy will be used to cover, among other things, “the cost of the operation and maintenance”

1 The Honorable Lawrence L. Piersol, United States District Judge for the District of South Dakota. -2- of East River’s “transmission system”; the “cost of related services”; the cost of maintaining “reasonable margins and reserves”; and the “principal and interest payments” on East River’s “indebtedness.” As relevant here, the WPC further provides that it “shall remain in effect” until December 31, 2075, and “thereafter until terminated by either Party giving to the other not less than six months’ written notice of its intention to terminate.”2 No provision in the WPC expressly allows for termination prior to this 2075 end date.

By joining East River, Dakota Energy also agreed to comply with the former’s Bylaws. Those Bylaws provide that “[e]ach member shall purchase from [East River] all electric power and energy required by the member to serve all its electric loads,” subject to limited exceptions not relevant here. The Bylaws also allow a member to “withdraw from membership upon compliance with such equitable terms and conditions as the Board of Directors may prescribe, provided, however, that no member shall be permitted to withdraw until it has met all contractual obligations to the Cooperative.”

In 2018, Dakota Energy, having become dissatisfied with the rising cost of the electricity it was purchasing, sought to withdraw from East River. Dakota Energy’s board of directors accordingly passed a resolution directing management to work with East River to determine “the amount East River would charge for Dakota Energy to ‘buy out’ of” the WPC. East River ultimately declined Dakota Energy’s request for a buyout number, however, explaining in a March 2019 letter that the WPC “do[es] not contain any provision permitting” Dakota Energy “to buy- out of its” contractual obligations.

Dakota Energy subsequently sued East River in South Dakota state court, alleging an anticipatory breach of the member-withdrawal provision in East River’s Bylaws. Dakota Energy also sought a declaration that the Bylaws permitted it to

2 The WPC was originally supposed to remain in effect until December 31, 2038, but Dakota Energy and East River agreed to extend the WPC’s term to 2058 in 2006, and then to 2075 nine years later. -3- withdraw from East River on “equitable terms and conditions” and to “discharge” its obligations under the WPC before the end of that agreement’s term in 2075. East River removed the case to federal court and asserted in a counterclaim that it was “entitled to a declaration” that its Bylaws “do not permit Dakota Energy to withdraw before fulfilling its obligations under the WPC” and that the WPC, in turn, “does not allow for early termination.” The district court granted summary judgment to East River, concluding in relevant part that the WPC unambiguously requires Dakota Energy to purchase electricity exclusively from East River until December 31, 2075, and that “no separate provision” in the WPC or East River’s Bylaws “provides for” the “early withdrawal” that Dakota Energy sought. Dakota Energy now appeals. 3

II.

We review the district court’s grant of summary judgment de novo, including its interpretation of South Dakota contract law. 4 Johnson Reg’l Med. Ctr. v. Halterman, 867 F.3d 1013, 1016 (8th Cir. 2017). Summary judgment is appropriate if, after viewing the record in the light most favorable to the non-moving party and making all reasonable inferences in its favor, there remains “no genuine issue of material fact and the moving party is entitled to judgment as a matter of law.”

3 Dakota Energy also appeals the district court’s decision to allow Basin Electric Power Cooperative to intervene in this case pursuant to Federal Rule of Civil Procedure 24. Dakota Energy argues that Basin lacked standing to intervene because it has not shown the requisite injury in fact. See United States v. Metro. St. Louis Sewer Dist., 569 F.3d 829, 833 (8th Cir. 2009) (“In our circuit, a party seeking to intervene must establish Article III standing in addition to the requirements of Rule 24.”). Yet the record indicates that Basin, which generates and sells electricity to East River, would sell less of that electricity if East River were to lose one of its members—here, Dakota Energy. And that “[r]isk of direct financial harm establishes injury in fact” for standing purposes. Nat’l Parks Conservation Ass’n v. EPA, 759 F.3d 969, 975 (8th Cir. 2014). We therefore affirm the district court’s grant of Basin Electric’s motion to intervene. 4 The parties agree that South Dakota law governs this case. -4- Hairston v. Wormuth, 6 F.4th 834, 840–41 (8th Cir. 2021) (quoting McPherson v. O’Reilly Auto., Inc., 491 F.3d 726, 730 (8th Cir. 2007)); see Fed. R. Civ. P. 56(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James McPherson v. O'Reilly Automotive, Inc.
491 F.3d 726 (Eighth Circuit, 2007)
Poeppel v. Lester
2013 S.D. 17 (South Dakota Supreme Court, 2013)
In Re the Dissolution of Midnight Star Enterprises, L.P.
2006 SD 98 (South Dakota Supreme Court, 2006)
Pauley v. Simonson
2006 SD 73 (South Dakota Supreme Court, 2006)
Ziegler Furniture & Funeral Home, Inc. v. Cicmanec
2006 SD 6 (South Dakota Supreme Court, 2006)
Lillibridge v. Meade School District 46-1
2008 SD 17 (South Dakota Supreme Court, 2008)
Detmers v. Costner
2012 S.D. 35 (South Dakota Supreme Court, 2012)
Swiden Appliance & Furniture, Inc. v. National Bank of South Dakota
357 N.W.2d 271 (South Dakota Supreme Court, 1984)
Berkley Regional Specialty Insurance Co. v. Dowling Spray Service
2015 SD 35 (South Dakota Supreme Court, 2015)
Johnson Regional Medical Cntr. v. Dr. Robert Halterman
867 F.3d 1013 (Eighth Circuit, 2017)
Nycoca Hairston v. Christine Wormuth
6 F.4th 834 (Eighth Circuit, 2021)
Midwest Medical Solutions, LLC v. Exactech U.S., Inc.
21 F.4th 1002 (Eighth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
75 F.4th 870, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dakota-energy-coop-inc-v-east-river-electric-power-coop-inc-ca8-2023.