Daisy J., Inc. v. First Bank & Trust Co.

50 Va. Cir. 596, 1998 Va. Cir. LEXIS 402
CourtWashington County Circuit Court
DecidedOctober 30, 1998
StatusPublished
Cited by2 cases

This text of 50 Va. Cir. 596 (Daisy J., Inc. v. First Bank & Trust Co.) is published on Counsel Stack Legal Research, covering Washington County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daisy J., Inc. v. First Bank & Trust Co., 50 Va. Cir. 596, 1998 Va. Cir. LEXIS 402 (Va. Super. Ct. 1998).

Opinion

By Judge Charles H. Smith, Jr.

I have completed my review of the file in this case which has been submitted to me for disposition on the defendant’s Motion for Summary Judgment. The court heard arguments of counsel on the motion on July 28, 1998, and took the matter under advisement. I have reviewed the pleadings and exhibits, the memoranda of counsel, and authorities cited therein and considered same in light of counsel’s arguments made at the hearing. In consideration of all of which, the court finds as follows.

The plaintiff filed this three-count motion for judgment against the defendant on April 12,1996, seeking damages for alleged breach of contract, breach of fiduciary duty, and negligence. The suit arises out of a lending agreement between the plaintiff and defendant executed on April 26,1995, wherein the defendant agreed to lend the plaintiff a sum not to exceed $420,000.00 to be used by the plaintiff for the construction of a commercial building. The terms of the loan called for multiple advances to be made to the plaintiff “upon inspection and satisfactoiy process of construction.” The loan carried interest at 9.5% with interest payments commencing May 26,1995, through November of 1995, with 59 payments of principal and interest in the amount of $4,454.59 each, commencing November 26, 1995. Prior to the execution of this loan agreement, the plaintiff had entered into a construction agreement with Rocky Creek Constructors on April 4, 1995, for the construction of this commercial building. The contract between plaintiff and Rocky Creek Constructors, the general contractor, called for six progression [597]*597payments during construction totaling $363,000.00. The general contractor received six draws between April and August of 1995, totaling $289,600.00. Five of these draws, totaling $253,400.00, were made directly by the defendant to the general contractor. Only one of the draws, for $36,200.00, was made to the general contractor by the plaintiff, in April of 1995. On October 19,1995, the general contractor apparently went to the defendant and demanded its final payment. The plaintiff contends that the defendant, upon inspecting the property and discovering that it was not near completion, refused the payment and the general contractor walked off the job. The plaintiff contends that this left it with a construction project with about $125,000.00 worth of work accomplished for which the general contractor had been paid $289,600.00, and which, according to an estimate received from another contractor, would take another $264,780.00 to complete.

The plaintiff contends that the language utilized in the loan agreement, placed in there by the defendant, which conditioned advances “upon inspection and satisfactory process of construction” imposed a contractual responsibility upon the defendant to make on-site inspections of the construction before making advances on the loan. The plaintiff contends the defendant breached its contract in failing to do so. The plaintiff further contends that the defendant breached a fiduciary relationship that existed between it and the defendant. The plaintiff contends this fiduciary duty arose by virtue of the defendant’s becoming the plaintiff’s agent for the purpose of inspecting progress and making advancements of plaintiff’s money to the general contractor instead of to the plaintiff. The plaintiff contends the defendant insisted upon this arrangement. The plaintiff contends that defendant did not obtain its approval for these direct disbursements. The final count of the motion for judgment sounds in tort and alleges the defendant negligently breached its duty to the plaintiff to use ordinaiy care to inspect the progress of the construction before making advancements of its loan funds to the general contractor.

The defendant has moved for summary judgment on the basis of the pleadings and exhibits. The exhibits include the loan agreement, the construction contract, some of plaintiff’s answers to interrogatories, copies of loan notices, cancelled checks, etc. The defendant contends it is entitled to summary judgment on the basis of these documents since no material fact is genuinely in dispute. The defendant contends that the breach of contract claim is without merit since the only document signed by anyone is the loan agreement which was signed only by the plaintiff. That loan agreement, the defendant contends, detailed only the obligations by the plaintiff to the defendant. The defendant invokes the provisions of the Statute of Frauds on [598]*598this issue which requires such agreements to be in writing and signed by the person to be charged in order to be enforceable against that person. (§ 11-2(9) of the Code.) The Statute of Frauds notwithstanding, the defendant contends it would be absurd to enforce the provision conditioning future advancements “upon inspection and satisfactory process of construction” upon it since the bank undertook no obligations or responsibilities concerning inspection of the construction process. As to the contention that loan advancements were made by the bank to the general contractor without the knowledge and consent of the plaintiff, the defendant points to plaintiffs answers to interrogatories where it admitted the authenticity of the “Notices of Loan Payment Due” which were regularly received and paid by the plaintiff. Essentially, the defendant argues that the plaintiff knew, or should have known, of the progress of its construction project since it continued to make regular payments according to the loan notices, which increased incrementally with each one and failed to make any complaint about the advancements until the last advance was refused by the bank and the general contractor walked off the job. In support of its motion on the breach of contract, the defendant relies upon the Virginia Supreme Court case of Brauer v. NationsBank, 251 Va. 28 (1996). In that case, the Supreme Court sustained the trial court’s granting of summary judgment in a case wherein the bank had approved the advancement of funds under a line of credit for purposes not indicated on the loan agreement. In affirming the trial court’s grant of summary judgment, the Supreme Court noted that the language within the loan agreement imposed no legal duty on the bank to monitor or insure that the loan proceeds were used for the purposes specified in the grid note.

As to the claims for breach of fiduciary duty and negligence, the defendant contends that there was no fiduciary relationship between the plaintiff and the defendant and that there was no duty owed by the defendant to the plaintiff which would support a claim for negligence. The defendant cites the Virginia Supreme Court case of Deal's Administrator v. Merchants and Mechanics Savings Bank, 120 Va. 297 (1917), and the decision of the Circuit Court of the City of Hampton in the case of Aldrich v. Old Point National Bank, 35 Va. Cir. 545 (1993), in support of its position. The defendant further points to decisions from appellate courts in other jurisdictions which have refused to impose a fiduciaiy duty upon a lender. The defendant contends that this was a typical creditor-debtor relationship in which the defendant undertook no duty at all to the plaintiff other than to lend the funds and pay them in a manner specified by the plaintiff. The defendant further points to numerous compelling public policy arguments against the imposition of any duty on lenders in such circumstances.

[599]*599As counsel are aware, we start with the basic proposition reiterated time and again by the Supreme Court that summary judgment is not favored and should not be granted lightly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Muir v. Navy Federal Credit Union
529 F.3d 1100 (D.C. Circuit, 2008)
Comeaux v. First Union National Bank
55 Va. Cir. 181 (Richmond County Circuit Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
50 Va. Cir. 596, 1998 Va. Cir. LEXIS 402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daisy-j-inc-v-first-bank-trust-co-vaccwashington-1998.