D.A. NOLT, INC. v. THE PHILADELPHIA MUNICIPAL AUTHORITY

CourtDistrict Court, E.D. Pennsylvania
DecidedMay 28, 2020
Docket2:18-cv-04997
StatusUnknown

This text of D.A. NOLT, INC. v. THE PHILADELPHIA MUNICIPAL AUTHORITY (D.A. NOLT, INC. v. THE PHILADELPHIA MUNICIPAL AUTHORITY) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.A. NOLT, INC. v. THE PHILADELPHIA MUNICIPAL AUTHORITY, (E.D. Pa. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA D.A. NOLT, INC., : Plaintiff : CIVIL ACTION : THE PHILADELPHIA MUNICIPAL No. 18-4997 AUTHORITY, et al., . : Defendants : MEMORANDUM PRATTER, J. say oo The parties dispute whether the liquidated damages provision included in a construction contract was itself constructed on a base of reasonable forecast of actual damages. The City of Philadelphia and the Philadelphia Municipal Authority seek to enforce a $10,000 per diem liquidated damages provision based only on their project director’s recollections of pre-estimates of probable actual damages that had been used to set provisions in other construction contracts negotiated and written decades ago. General contractor D.A. Nolt, Inc. moves for partial summary judgment and seeks to dismiss the defendants’ claim for liquidated damages. For the reasons discussed below, the Court grants Nolt’s motion. BACKGROUND The City, through the Philadelphia Municipal Authority,! sought to relocate the Philadelphia Police Department’s headquarters to 4601 Market Street. The relocation required a renovation project that was scheduled to be completed in three construction phases. The City contracted Nolt, a general contractor, to complete $13,473,817.02 worth of work on the building

The City assigned its rights under the contract at issue to the Philadelphia Municipal Authority but remained involved in the daily operations of the project as the municipal authority’s representative and agent. For ease of reference, this Memorandum refers to the defendants collectively as “the City.”

façade and roof improvements during the project’s second phase. However, the project fell through when Mayor James Kenney announced that the police headquarters would be relocated elsewhere. According to Nolt, the City failed to pay Nolt for some of the work it completed prior to the cessation of the project,2 allegedly resulting in damages in excess of $2,564,329.37.3 Accordingly, Nolt brought this suit against the City. The City, in turn, raised a counterclaim

asserting that Nolt breached the contract by allegedly delaying the project for 255 days. Although the City primarily argues that it incurred nearly $2.7 million in actual damages due to Nolt’s alleged breach, it alternatively asserts that Nolt owes the City $2.55 million pursuant to a $10,000 per diem liquidated damages provision in the contract. Nolt’s motion takes aim at the City’s effort to enforce the liquidated damages provision. A. Liquidated Damages Provision The project manual consists of the City’s Standard Contract Requirements for Public Works Contracts and the City’s Special Contract Requirements. In pertinent part, the City’s Standard Contract Requirements state:

If, for reasons other than those stated above, any portion of the work remains uncompleted after the Contract date specified for its completion, notwithstanding Substantial Completion of the work, the Project Manager shall deduct from payments due the Contractor, as liquidated damages an amount per diem, according to the following schedule:

2 Nolt’s work included miscellaneous asbestos abatement, masonry façade restoration, structural steel, window replacement, and roof removal and replacement. 3 Nolt also alleges that it was forced to remain on the project for longer than necessary due to various delays caused by the City (namely, the City making changes to the project and failing to timely review documents). According to Nolt, it completed work at an accelerated pace and an increased rate because the City denied Nolt’s extension requests for additional time to complete the work. The City counters that Nolt’s own doing delayed the project, not the modifications the City made to the project. Contract Value Agreed Delay Damages Per Diem $0-$100,000 $250 $100,001-$500,000 $500 $500,001-$1,000,000 $750 Over $1,000,000 $1,000

These per diem delay damages are assessed as agreed liquidated damages because the Parties have considered the difficulty of determining the City’s actual damages and agreed that computation of the City’s actual damages is impossible . . . .

Pl.’s Ex. 3 at § 26(f) (Doc. No. 24-6). The Special Contract Requirements modified the standard schedule as follows: Contract Value Agreed Delay Damages Per Diem $0-$100,000 $250 $100,001-$500,000 $500 $500,001-$1,000,000 $1,000 Over $1,000,000 $10,000

Id. at 12.F (emphasis added). Thus, the modification increased the per diem damages for contract values greater than $1,000,000 from $1,000 to $10,000. Because Nolt’s contract value exceeded $1,000,000, the $10,000 per diem liquidated damages provision applies here. B. Pedro Pinto’s Deposition Testimony Nolt’s arguments initially focused on the deposition testimony of Pedro Pinto, a professional civil engineer employed as a project manager and Philadelphia Municipal Authority representative. Mr. Pinto testified that although he was part of the process to increase the per diem amount from $1,000 to $10,000, he did not perform any analysis to forecast the daily amount of liquidated damages for the project, and he was unaware of anyone else who performed such an analysis. C. James Lowe’s Declaration and Deposition Testimony In defending against Nolt’s motion, the City relies on the declaration of James Lowe, the Project Director for the City of Philadelphia’s Department of Public Property. In his declaration, Mr. Lowe stated that he finalized and executed the City’s contract with Nolt, including the $10,000 per diem liquidated damages provision. According to Mr. Lowe, the City determined that the $10,000 per diem provision “was accurate based on an analysis of projects of similar scope and magnitude.” Lowe Decl. at ¶ 6 (Doc. No. 28-2). The liquidated damages provisions for these prior projects were based on calculations which had estimated daily costs to the City in the event

of any delays in those projects. In his declaration, Mr. Lowe also states that the City determined that it would be difficult to determine actual damages for breaching the contract at the time the parties entered into the Nolt contract, and that the City intended the $10,000 liquidated damages amount to cover any damages it may incur if Nolt breached the contract. After the City submitted Mr. Lowe’s declaration to the Court, Nolt deposed Mr. Lowe. When questioned about his declaration, Mr. Lowe testified that he “believe[d]” that his department, “back in the [1990s],” considered “some relative costs that [it] might incur” regarding prior large-scale projects “that had some detention component[s].” Lowe Dep. at 226:18-24; 227:13-14 (Doc. No. 40-1). Specifically, the earlier projects Mr. Lowe referenced included the

Curran Fromhold Correctional Facility, the Riverside Women’s Correctional Facility, and the Philadelphia Youth Center. Mr. Lowe testified that these projects each cost more than $70 and $100 million. Mr. Lowe believes that the analyses for at least two of these projects could have factored in probable rental costs for housing inmates at other locations. Because these past contracts were entered into and performed before he began working for the City, Mr. Lowe had not personally requested or analyzed the calculations that had been completed to prepare the liquidated damages provision included in those contracts. Mr. Lowe stated that he could not locate any documentation detailing the earlier analyses conducted to formulate the liquidated damages provisions included in the past contracts. LEGAL STANDARD A court can grant a motion for summary judgment “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” FED. R. CIV. P. 56(a). An issue is “genuine” if there is a sufficient evidentiary basis on which a reasonable jury could return a verdict for the non-moving party. Kaucher v. Cnty. of Bucks, 455

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Betts v. New Castle Youth Development Center
621 F.3d 249 (Third Circuit, 2010)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Palmieri v. Partridge
853 A.2d 1076 (Superior Court of Pennsylvania, 2004)
Holt's Cigar Co. v. 222 Liberty Associates
591 A.2d 743 (Superior Court of Pennsylvania, 1991)
Pantuso Motors, Inc. v. Corestates Bank
798 A.2d 1277 (Supreme Court of Pennsylvania, 2002)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
Hanrahan v. Audubon Builders, Inc.
614 A.2d 748 (Superior Court of Pennsylvania, 1992)
Meyer-Chatfield v. Century Business Servicing, Inc.
732 F. Supp. 2d 514 (E.D. Pennsylvania, 2010)
A. Scott Enterprises v. City of Allentown, Aplt.
142 A.3d 779 (Supreme Court of Pennsylvania, 2016)
Calabro v. Department of Aging
689 A.2d 347 (Commonwealth Court of Pennsylvania, 1997)
Laughlin v. Baltalden, Inc.
159 A.2d 26 (Superior Court of Pennsylvania, 1960)
In re Milbourne
557 B.R. 376 (E.D. Pennsylvania, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
D.A. NOLT, INC. v. THE PHILADELPHIA MUNICIPAL AUTHORITY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/da-nolt-inc-v-the-philadelphia-municipal-authority-paed-2020.