D.A. McCosker Construction v. Dept. of Water Resources CA3

CourtCalifornia Court of Appeal
DecidedMarch 6, 2023
DocketC089969
StatusUnpublished

This text of D.A. McCosker Construction v. Dept. of Water Resources CA3 (D.A. McCosker Construction v. Dept. of Water Resources CA3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.A. McCosker Construction v. Dept. of Water Resources CA3, (Cal. Ct. App. 2023).

Opinion

Filed 3/6/23 D.A. McCosker Construction v. Dept. of Water Resources CA3 NOT TO BE PUBLISHED California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA THIRD APPELLATE DISTRICT (Sacramento) ----

D.A. MCCOSKER CONSTRUCTION et al., C089969

Plaintiffs and Appellants, (Super. Ct. No. 34-2017- 00209945-CU-PT-GDS) v.

DEPARTMENT OF WATER RESOURCES,

Defendant and Appellant.

The Department of Water Resources (DWR) and D.A. McCosker Construction Co., doing business as Independent Construction Company (ICC), entered into a contract for the construction of a reservoir near the City of Livermore. After ICC completed the project, DWR sought to avoid paying ICC on the ground that ICC was an unlicensed contractor at the time of the project. It based its argument on the Contractors’ State

1 License Law (Bus. & Prof. Code, § 7000 et seq.),1 which provides that a contractor may not maintain any action to recover compensation for “the performance of any act or contract” unless it was duly licensed “at all times during the performance of that act or contract.” (§ 7031, subd. (a).) ICC and its surety, Fidelity & Deposit Co. of Maryland (Fidelity), successfully sought relief against DWR in arbitration—the required forum under the parties’ agreement. The arbitrator rejected DWR’s claim that ICC was unlicensed and awarded ICC over $5,000,000 in damages. But a trial court later vacated the arbitrator’s award, agreeing with DWR that ICC lost its license after it began the project. The court based its conclusion on sections 7068 and 7068.1. Section 7068 allows a corporation, like ICC, to qualify for a contractor’s license through a “responsible managing employee” who has the necessary experience and knowledge to qualify for a contractor’s license in his or her own right. Section 7068.1, in turn, in the trial court’s reading, requires a corporation’s responsible managing employee to exercise direct supervision and control over all the corporation’s construction operations. Applying this interpretation of section 7068.1, the trial court concluded that ICC violated this statute because its responsible managing employee failed to directly supervise and control the project in this case. It further concluded that ICC’s license was automatically invalidated at the time this violation occurred, leaving ICC unlicensed during the project. On ICC’s and Fidelity’s appeal, we reverse. The trial court premised its conclusion on the wrong version of section 7068.1. At the time of trial, the statute required a responsible managing employee to “be responsible for exercising that direct supervision and control of his or her employer’s or principal’s construction operations to secure compliance with” state licensing laws. (Former § 7068.1; Stats. 2013, ch. 180,

1 Undesignated statutory references are to the Business and Professions Code.

2 § 1.) The trial court relied on this language in its decision. But at the time of the project, the relevant timeframe here, the statute read a little differently. It required the responsible managing employee to “be responsible for exercising that direct supervision and control of his or her employer’s or principal’s construction operations as is necessary to secure full compliance with” state licensing laws. (Former § 7068.1, italics added; Stats. 2006, ch. 106, § 2.) The “as is necessary” language is important. It shows that a responsible managing employee’s obligation to exercise direct supervision and control depends on the facts, refuting the trial court’s conclusion that a responsible managing employee must always exercise direct supervision and control over the corporation’s construction operations. We will remand the matter to the trial court for further consideration under the applicable version of the statute. BACKGROUND I The Dyer Project The McCosker family formed D.A. McCosker Construction Co. over 80 years ago. For the last 20 years, Brian McCosker (Brian) has served as its president and Kevin McCosker (Kevin) has been its designated “responsible managing employee” within the meaning of section 7068—a statute providing that a corporation can qualify for a contractor’s license through a “responsible managing employee” who has the requisite knowledge and experience to hold a contractor’s license in his or her own right. (§ 7068, subd. (b)(3).) Kevin began serving as D.A. McCosker Construction Co.’s responsible managing employee starting in 2001. In 2009, DWR and D.A. McCosker Construction Co., doing business as ICC, entered into a contract for the construction of a project known as the Dyer Reservoir, South Bay Aqueduct Enlargement (the Dyer project). ICC, which served as the project’s general contractor, completed the project three years later in 2012. Brian oversaw the project. Kevin, although kept informed of the project, had no involvement with it.

3 According to the Contractors State License Board’s records, D.A. McCosker Construction Co. was a licensed general contractor during the whole of the Dyer project. II First Arbitration Proceeding Several months after the project’s completion, ICC and Fidelity (collectively, ICC) filed a complaint against DWR in arbitration—the required forum for disputes under the parties’ agreement and the State Contract Act (Pub. Contract Code, § 10100 et seq.). (See Pub. Contract Code, § 10240.) ICC also joined several of its subcontractors, including Monterey Mechanical Co., in the suit. ICC alleged it was owed additional compensation for performing work above that required in the parties’ contract. It also alleged that DWR improperly deducted liquidated damages from the amounts it owed ICC and that, after DWR’s deduction of these amounts led to ICC’s subcontractors (including Monterey Mechanical Co.) not getting paid, DWR withheld further payments from ICC. ICC sought over $12,000,000 in damages. DWR afterward filed a cross-complaint against ICC, alleging it was entitled to deduct an additional $1,905,000 in liquidated damages because ICC untimely completed the project. It also contended ICC’s claims failed for three reasons relevant to this appeal. First, it alleged that ICC failed to exhaust the administrative remedies described in the parties’ contract. Second, it argued that ICC’s damages calculation was flawed because its damages expert, Gene Lash, relied on hearsay for his conclusions. And third, after the close of evidence in the arbitration proceedings, it asserted that Kevin was a “sham” responsible managing employee and did not supervise the Dyer project. Based on this last argument, DWR argued that ICC’s license was invalid and that, as a result, DWR was entitled to recover all amounts it had paid ICC for the Dyer project. The arbitrator ruled largely in ICC’s favor. Starting with DWR’s arguments, he found none of them persuasive. He found ICC sufficiently exhausted the administrative procedures described in the parties’ contract. He found Lash relied on documents that

4 were admissible under the business records exception to the hearsay rule. And he indicated that Kevin was a legitimate responsible managing employee who worked for ICC, had been its responsible managing employee for years, and helped manage ICC. Turning to ICC’s claims, the arbitrator found DWR owed ICC additional funds for certain costs incurred, improperly deducted liquidated damages, and improperly withheld payments. After accounting for prejudgment interest and certain costs, he awarded ICC over $5,000,000 in damages. III First Trial Court Proceeding ICC and DWR later filed competing petitions with the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiCampli-Mintz v. County of Santa Clara
289 P.3d 884 (California Supreme Court, 2012)
Rayii v. Gatica CA2/3
218 Cal. App. 4th 1402 (California Court of Appeal, 2013)
Foreman & Clark Corp. v. Fallon
479 P.2d 362 (California Supreme Court, 1971)
Werner v. Southern California Associated Newpapers
216 P.2d 825 (California Supreme Court, 1950)
Evangelatos v. Superior Court
753 P.2d 585 (California Supreme Court, 1988)
Waters v. Bourhis
709 P.2d 469 (California Supreme Court, 1985)
Judson Pacific-Murphy Corp. v. Durkee
301 P.2d 97 (California Court of Appeal, 1956)
Moore v. Powell
70 Cal. App. 3d 583 (California Court of Appeal, 1977)
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co.
115 P.3d 41 (California Supreme Court, 2005)
Haworth v. Superior Court of Los Angeles County
235 P.3d 152 (California Supreme Court, 2010)
South Coast Framing, Inc. v. Workers' Compensation Appeals Board
349 P.3d 141 (California Supreme Court, 2015)
People v. Banks
351 P.3d 330 (California Supreme Court, 2015)
Ball v. Steadfast-BLK
196 Cal. App. 4th 694 (California Court of Appeal, 2011)
Ahdout v. Hekmatjah
213 Cal. App. 4th 21 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
D.A. McCosker Construction v. Dept. of Water Resources CA3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/da-mccosker-construction-v-dept-of-water-resources-ca3-calctapp-2023.