D & M Carriers LLC v. M/V Thor Spirit

586 F. App'x 564
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 20, 2014
Docket13-13280
StatusUnpublished
Cited by2 cases

This text of 586 F. App'x 564 (D & M Carriers LLC v. M/V Thor Spirit) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & M Carriers LLC v. M/V Thor Spirit, 586 F. App'x 564 (11th Cir. 2014).

Opinion

ON PETITION FOR REHEARING

PER CURIAM:

The previous opinion issued in this case, D & M Carriers LLC v. M/V Thor Spirit, No. 13-13280, 2014 WL 4667333 (11th Cir. Sept. 22, 2014), is hereby VACATED. In its place we issue this revised opinion. The petition for rehearing is otherwise DENIED.

This appeal arises out of a dispute concerning the overland transport of a 57-foot yacht. Inan Taptik, a citizen and resident of Turkey, contracted with Able Boat Transport, LLC to have the yacht transported from Missouri to Florida. Unknown to Taptik, Able Boat then subcontracted with D & M Carriers to transport the boat. Because of a variety of unforeseen circumstances, D & M was able to haul the boat only to Georgia, and it did so at a cost that was well above the amount Taptik had agreed to pay in his contract with Able Boat.

Seeking to recover the costs it incurred, D & M filed suit in federal court asserting three claims: an in rem claim against the yacht, a breach of contract claim against

*566 Able Boat, and a breach of contract claim against Taptik. 1 After conducting a bench trial, the district court entered judgment in favor of Taptik and the vessel. This is D & M’s appeal.

I.

In 2011 Taptik purchased through a telephone auction a 57-foot Viking Sport Cruiser yacht — the Thor Spirit — that was located in Table Rock, Missouri. 2 On March 24, 2011, he entered into an agreement with Able Boat to have the yacht transported from Missouri to Fort Lauder-dale, Florida. The contract provided that Able Boat would transport the vessel for a flat fee of $16,500, but it incorrectly noted that the boat had an overall height of only 13 feet 6 inches. On March 25, 2011, Able Boat entered into a carrier contract with D & M to transport the boat from Missouri to Florida. D & M agreed to haul the boat for a flat fee of $10,750. That agreement was premised on the assumption that the boat was no taller than fourteen feet.

On March 29, 2011, D & M truck driver Rocky Clark arrived with his tractor-trailer at the marina in Missouri where the Thor Spirit was located. Taptik was also present at the marina. Because Taptik did not speak any English, his employee and translator, Murat Varol, was with him. Clark introduced himself to Varol and handed him his D & M business card. Varol believed that Clark worked for Able Boat because Taptik’s contract stated that Able Boat would transport the boat and Able Boat’s managing partner had told Varol and Taptik that “his driver [was] coming to pick up the boat.” While they were at the marina, Taptik never spoke to Clark or anyone else from D & M.

After the marina staff loaded the Thor Spirit onto his trailer, Clark realized that the yacht was not 13 feet 6 inches tall, as stated in the contracts, but was instead 17 feet 7 inches tall. The true height of the boat had a substantial impact on Clark’s planned route because any load taller than 17 feet could not travel on the interstate. Based on the new height, Clark had to take a much longer and more circuitous route to Florida. He also had to hire escorts, conduct route surveys in several states, and obtain over-sized load permits for each state he would be passing through.

Because of the changed circumstances, on April 5, 2011, Able Boat modified its contracts with Taptik and D & M. Taptik agreed to pay a flat rate of $38,000 to Able Boat for its services, although the modified contract also provided that the final cost could be as low as $36,000 “depending on regulation during transport.” Able Boat also modified its contract with D & M. That contract provided that D & M would transport the boat to Florida for $28,000 plus the cost of any bucket trucks and police escorts that might be needed during transport.

Clark made slow progress because of the height of the Thor Spirit. He could not drive on the interstate and his crew of escorts had to lift more than 20,000 power lines, tree limbs, and streetlights over the course of the trip. He travelled only 90 to 120 miles per day instead of his usual pace of 400 miles per day. He was also delayed waiting for permits to travel through various states with his load. When he at *567 tempted to bring the boat into Florida, the state’s department of transportation refused to give him permission to travel on the state’s highways. As a result, Able Boat directed Clark to deliver the boat to St. Mary’s, Georgia. It then notified Tap-tik and Varol that the boat could not enter Florida and that it would be brought to St. Mary’s. 3

After Able Boat directed Clark to deliver the boat to St. Mary’s, D & M and Able Boat began discussing the extensive costs that D & M had incurred to pay for bucket trucks and escorts along its route. Taptik and Varol were not included in those discussions about the additional charges. On May 12, 2011, Able Boat submitted a bill to Taptik for all of the charges incurred by D & M, which came to $85,839.81. Neither Taptik nor Varol ever agreed to pay additional fees or costs above the $38,000 that had been agreed to in the modified contract with Able Boat.

D & M repeatedly sought payment from Able Boat for the extra costs Clark had incurred during transportation. Able Boat agreed to pay $35,097.81 and to split with D & M the cost of a route survey; however, Able Boat never paid D- & M the promised amount. Instead, D & M received only $17,122. In an attempt to recover the full costs it had incurred, D & M filed a complaint in the Southern District of Florida seeking to establish a maritime lien on the Thor Spirit. 4 D & M contended that it was entitled to a maritime lien on the Thor Spirit because it had provided “necessaries” to the vessel by transporting it to Georgia. 5 D & M also asserted breach of contract claims against Taptik and Able Boat.

The district court held a bench trial on the claims asserted against the Thor Spirit and Taptik. It dismissed the breach of contract claim against Taptik based on improper service of process. The court also concluded that D & M was not entitled to a maritime lien on the Thor Spirit because it had failed to prove that it had provided necessaries to the yacht “on the order of the owner or a person authorized by the owner.” See 46 U.S.C. 31342(a).

II.

As an initial matter, we must determine whether we have jurisdiction to consider D & M’s appeal even though its claim in this case against Able Boat has not yet been resolved. “Ordinarily ... an order adjudicating fewer than all the claims in a suit, or adjudicating the rights and liabilities of fewer than all the parties, is not a final judgment from which an appeal may be taken.” Lloyd Noland Found., Inc. v. Tenet Health Care Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hargus v. Ferocious & Impetuous, LLC
66 V.I. 785 (Virgin Islands, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
586 F. App'x 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-m-carriers-llc-v-mv-thor-spirit-ca11-2014.