C.W. Over & Sons, Inc. v. United States

45 Fed. Cl. 502, 1999 U.S. Claims LEXIS 286, 1999 WL 1201411
United States Court of Federal Claims·Decided December 10, 1999·No. No. 98-741C·Published·Cited by 2 cases

Opinion

OPINION

MILLER, Judge.

This contract case is before the court on the parties’ cross-motions for summary judgment as to Count III of the complaint. The issues to be decided are (1) whether the doctrine of the law of the case requires the court to grant plaintiffs motion, (2) whether new work orders styled as modifications to delivery orders retain their character as modifications, and (3) whether there was a mutual mistake of fact which warrants contract reformation. Argument is deemed unnecessary.

FACTS

The facts material to the cross-motions are undisputed. On January 14, 1994, the Maryland Procurement Office of the National Security Agency (the “NSA”) awarded Contract MDA904-94-D-2502 to C.W. Over & Sons, Inc. (“plaintiff’). This firm fixed-price contract was an indefinite delivery, indefinite quantity contract providing for construction and renovation work at Fort George G. Meade, Maryland. The duration of the con[503]*503tract was one year with four one-year options. All but the final option year of the contract were exercised. Only those facts pertinent to the pending cross-motions are reviewed.1

1. Orders and pricing

The contract establishes a formula to set the price of work ordered by the NSA. The contract incorporates by reference a Unit Price Book (“UPB”) to determine the costs of each potential undertaking. A UPB is a comprehensive register of individual construction tasks that have been pre-priced by the Government. The price of a particular task is established by cross-referencing the task performed with the UPB cost entry and multiplying by the relevant coefficient.2 The coefficients thus operate as multipliers in calculating the price that plaintiff is entitled to charge for work performed. At the outset plaintiff was required to provide the NSA with three fixed coefficients—for onsite work during normal working hours, onsite work during other than normal working hours (overtime), and offsite work—for each year of the contract. Although the coefficients changed for each successive year of the contract to account for differing economic conditions, they remained fixed during the year for which each was designated. Plaintiffs proposed coefficients were incorporated into the contract upon award.

The contract also establishes a procedure for ordering new work. The two vehicles employed for this purpose were (1) delivery orders and (2) modifications to delivery orders. Delivery orders were used to initiate separate projects within the contract. Section H.21 of the contract details the process for origination of delivery orders. Specifically, that section mandates that delivery orders reference section H.21 and be issued on DD Form 1155, “Order for Supplies or Services.” In contrast, modifications to delivery orders were used within the context of a specific delivery order to change the scope or content of work previously ordered. .These orders were executed on Standard Form 30 (“SF 30”). Unlike its counterpart for delivery orders, SF 30 made no reference to section H.21. SF 30 also explicitly noted the applicability of Federal Acquisition Regulations (“FAR”) section 52.243-4, 48 C.F.R. § 52.243-4 (1994), titled “Changes,” to its content. FAR § 52.243-4(e) states:

The Contractor must assert its right to an adjustment under this clause within 30 days after (1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of proposal, unless this period is extended by the Government.

Although the contract did establish a procedure for ordering new work, it did not establish a specific process by which the parties would agree on what work was necessary for a particular project. In practice the parties always followed the same basic negotiating steps. After the NSA had identified its project requirements, plaintiff would prepare a proposal that included a listing of the line items necessary for performance. Plaintiff would cross-reference the required line items with the UPB, multiply by the relevant coefficient, and add them to obtain a total price for the project. As was its custom, the NSA would concurrently prepare its own independent cost estimate. When plaintiffs proposal was received, the NSA would review it against its own estimate. The parties would then meet to discuss any discrepancies or outstanding technical issues. Any changes agreed to would be incorporated into plaintiffs proposal. Thereafter, the NSA would issue the appropriate work order consistent with the agreed-to terms.

The work orders implicated by Count III of plaintiffs complaint were developed in precisely the manner describe above. After [504]*504the NSA identified its project requirements, plaintiff prepared proposals. This included listing the line items necessary for performance, inserting appropriate coefficients, and establishing total price. The NSA reviewed the proposals and used plaintiffs coefficients in the final work orders. At no time during the negotiation of any work order did plaintiff propose alternatives or protest the use of the coefficients that it had prepared. Consistent with their negotiations, the work orders at issue, which incorporated the coefficients, were drafted as modifications to delivery orders on SF 30.

2. Procedural history

On February 20, 1998, plaintiff submitted a certified claim to the contracting officer for costs incurred during the course of performance on the contract. On July 20, 1998, the contracting officer denied this claim in its entirety. Plaintiff filed suit seeking review of that decision pursuant to the Contract Disputes Act, 41 U.S.C.A. § 609(a)(1) (West 1987 & Supp.1999).

In its suit plaintiff raised three independent grounds for recovery. Count I of plaintiffs complaint dealt with whether the contract price, as awarded, included all state sales tax on materials. Count II concerned whether plaintiffs performance of work orders under $2,000.00 was beyond the scope of the contract. In Count III of the complaint, plaintiff challenged the use of coefficients for work orders performed during the option years, charging that the NSA often applied the previous year’s coefficient rather than the current year’s. Specifically, plaintiff sought an equitable adjustment in the amount of $6,202.74 under the changes clause of the contract for application of the wrong coefficient on delivery orders 0168, 0198, 0192, 0204, 0193, 0207, 0232, and 0135.

On January 4, 1999, defendant responded to the complaint with a motion for summary judgment. That motion was granted with respect to Count I, but otherwise denied. See C.W. Over & Sons, Inc. v. United States, 44 Fed.Cl. 18 (1999) (order granting in part and denying in part motion for summary judgment). As to Count III, defendant argued that it had, in fact, applied the correct coefficients. The court rejected this contention, see id. at 31-32, inviting plaintiff to move for summary judgment.

On July 7, 1999, plaintiff moved for partial summary judgment with respect to Count III of its complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

C.W. Over & Sons, Inc. v. United States, 45 Fed. Cl. 502, 1999 U.S. Claims LEXIS 286, 1999 WL 1201411 (uscfc 1999).

45 Fed. Cl. 502 (C.W. Over & Sons, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

C.W. Over & Sons, Inc. v. United States
48 Fed. Cl. 342 (Federal Claims, 2000)