Custom Performance v. AM Industrial

CourtCourt of Appeals of South Carolina
DecidedJuly 24, 2024
Docket2022-000348
StatusUnpublished

This text of Custom Performance v. AM Industrial (Custom Performance v. AM Industrial) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Custom Performance v. AM Industrial, (S.C. Ct. App. 2024).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Custom Performance Engineering, Inc., Respondent- Appellant,

v.

AM Industrial Group, LLC, Appellant-Respondent.

Appellate Case No. 2022-000348

Appeal From Spartanburg County J. Derham Cole, Circuit Court Judge, Shannon Metz Phillips, Master-in-Equity

Unpublished Opinion No. 2024-UP-275 Heard June 12, 2024 – Filed July 24, 2024

AFFIRMED

Carmen Vaughn Ganjehsani and Robert Wilder Harte, both of Richardson Plowden & Robinson, PA, of Columbia, for Appellant-Respondent.

Adam Crittenden Bach and Emily R. Godwin, both of Tonnsen Bach, LLC, of Greenville, for Respondent-Appellant. PER CURIAM: This is a cross-appeal from the Master-in-Equity's damages award to Custom Performance Engineering, Inc. (Custom Performance) on its breach of contract action against AM Industrial Group, LLC (AMI) following the circuit court's denial of AMI's motion to set aside an entry of default. On appeal, AMI argues (1) the circuit court erred in denying its motion to set aside the entry of default because good cause existed to set it aside; and (2) the master erred in its damages award because Custom Performance failed to meet its burden for establishing lost profits damages and failed to adduce evidence in support of portions of its other purported damages. On cross-appeal, Custom Performance argues the master erred in holding Custom Performance was not entitled to cover damages. We affirm.

1. AMI argues the circuit court erred in denying its motion to set aside the entry of default. We disagree. See Richardson v. P.V., Inc., 383 S.C. 610, 614, 682 S.E.2d 263, 265 (2009) ("The decision whether to set aside an entry of default or a default judgment lies solely within the sound discretion of the [circuit] court."); id. ("The [circuit] court's decision will not be disturbed on appeal absent a clear showing of an abuse of that discretion."); In re Estate of Weeks, 329 S.C. 251, 259, 495 S.E.2d 454, 459 (Ct. App. 1997) ("An abuse of discretion . . . occurs when the judge issuing the order was controlled by some error of law or when the order, based upon factual, as distinguished from legal conclusions, is without evidentiary support."); Stark Truss Co. v. Superior Constr. Corp., 360 S.C. 503, 510, 602 S.E.2d 99, 102 (Ct. App. 2004) ("Rule 55(c), [of the South Carolina Rules of Civil Procedure (SCRCP)], allows the circuit court to set aside an entry of default 'for good cause shown.'" (quoting Rule 55(c))); Williams v. Vanvolkenburg, 312 S.C. 373, 375, 440 S.E.2d 408, 409 (Ct. App. 1994) ("Whether good cause is established is within the sound discretion of the [circuit] court."); Sundown Operating Co. v. Intedge Indus., Inc., 383 S.C. 601, 607, 681 S.E.2d 885, 888 (2009) ("This standard requires a party seeking relief from an entry of default under Rule 55(c) to provide an explanation for the default and give reasons why vacation of the default entry would serve the interests of justice."); id. at 609, 681 S.E.2d at 889 (rejecting the petitioner's argument "that it should be granted relief from the entry of default because it should not be held responsible for the negligence of its insurance agent in failing to answer the complaint" and holding the argument was without merit "as the law is clear that an attorney or insurance company's misconduct is imputable to the client"); Dixon v. Besco Eng'g, Inc., 320 S.C. 174, 178-79, 463 S.E.2d 636, 638-39 (Ct. App. 1995) (affirming the circuit court's finding that the defendant's misunderstanding of a deadline did not constitute good cause to set aside the entry of default). We hold the circuit court did not abuse its discretion in finding AMI did not show good cause to excuse the default. AMI's insurer's negligence is imputed to it. In addition, there is no indication in the record AMI reached out to Custom Performance to inquire about the extended deadline for the answer or to request additional time after the insurer denied coverage. We therefore affirm the circuit court's denial of AMI's motion to set aside the entry of default.

2. AMI argues the master erred in its award of damages to Custom Performance because Custom Performance failed to meet its burden for establishing lost profits damages and failed to produce evidence in support of its other purported damages. We disagree. See Austin v. Specialty Transp. Servs., Inc., 358 S.C. 298, 310, 594 S.E.2d 867, 873 (Ct. App. 2004) ("The trial judge has considerable discretion regarding the amount of damages."); id. at 311, 594 S.E.2d at 873 (stating the appellate court's "task in reviewing a damages award is not to weigh the evidence, but to determine if there is any evidence to support the damages award"); S.C. Fed. Sav. Bank v. Thornton-Crosby Dev. Co., 310 S.C. 232, 234-35, 423 S.E.2d 114, 115 (1992) (stating that in order for a party to recover lost profits as a result of a breach of contract, the party seeking damages must prove (1) the profits "have been prevented or lost as a natural consequence of the breach of contract;" (2) the lost profits were reasonably "within the contemplation of the parties at the time the contract was made as a probable result of a breach of it"; and (3) the lost profits with reasonable certainty, as they cannot be "conjectural or speculative" (quoting Drews Co. v. Ledwith-Wolfe Associates, 296 S.C. 207, 213, 371 S.E.2d 532, 535-36 (1988))); Moore v. Moore, 360 S.C. 241, 255-56, 599 S.E.2d 467, 474-75 (Ct. App. 2004) ("The law does not require absolute certainty of data upon which lost profits are to be estimated, but all that is required is such reasonable certainty that damages may not be based wholly upon speculation and conjecture, and it is sufficient if there is a certain standard or fixed method by which profits sought to be recovered may be estimated and determined with a fair degree of accuracy." (quoting Beck v. Clarkson, 300 S.C. 293, 298-99, 387 S.E.2d 681, 684 (Ct. App. 1989))). Custom Performance owner Joseph Adams testified Custom Performance lost revenue when several of its customers cancelled their contracts because Custom Performance was unable to fill their orders. He stated Custom Performance expected profit margins of 2.5 times the cost for the BMW purchase order because it was high volume mass manufacturing and 3.5 times the costs on the other contracts.1 Calculating the numbers on the stand, Adams testified the lost

1 In the post-hearing documents Custom Performance submitted the following purchase orders: (1) Saleen Automotive dated October 9, 2020 for $144,590.60; (2) Blow-By-Blow Racing dated April 2, 2021 for $125,235; and Purem by Eberspaecher (BMW) dated August 26, 2021 for $197,835. profits totaled $257,680.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beck v. Clarkson
387 S.E.2d 681 (Court of Appeals of South Carolina, 1989)
Sundown Operating Co. v. Intedge Industries, Inc.
681 S.E.2d 885 (Supreme Court of South Carolina, 2009)
Williams v. Vanvolkenburg
440 S.E.2d 408 (Court of Appeals of South Carolina, 1994)
Richardson v. P v. Inc.
682 S.E.2d 263 (Supreme Court of South Carolina, 2009)
Wilder Corp. v. Wilke
497 S.E.2d 731 (Supreme Court of South Carolina, 1998)
Stark Truss Co. v. Superior Construction Corp.
602 S.E.2d 99 (Court of Appeals of South Carolina, 2004)
Moore v. Moore
599 S.E.2d 467 (Court of Appeals of South Carolina, 2004)
Austin v. Specialty Transportation Services, Inc.
594 S.E.2d 867 (Court of Appeals of South Carolina, 2004)
In Re Estate of Weeks
495 S.E.2d 454 (Court of Appeals of South Carolina, 1997)
Dixon v. Besco Engineering, Inc.
463 S.E.2d 636 (Court of Appeals of South Carolina, 1995)
South Carolina Federal Savings Bank v. Thornton-Crosby Development Co.
423 S.E.2d 114 (Supreme Court of South Carolina, 1992)
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
762 S.E.2d 693 (Supreme Court of South Carolina, 2014)
In the Matter of the Care and Treatment of Campbell
830 S.E.2d 14 (Supreme Court of South Carolina, 2019)
Life of Georgia Insurance v. Bolton
509 S.E.2d 488 (Court of Appeals of South Carolina, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Custom Performance v. AM Industrial, Counsel Stack Legal Research, https://law.counselstack.com/opinion/custom-performance-v-am-industrial-scctapp-2024.