Curtis v. Puget Sound Bridge & Dredging Co.

233 P. 936, 133 Wash. 323, 1925 Wash. LEXIS 1195
CourtWashington Supreme Court
DecidedMarch 6, 1925
DocketNo. 19043. Department Two.
StatusPublished
Cited by8 cases

This text of 233 P. 936 (Curtis v. Puget Sound Bridge & Dredging Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtis v. Puget Sound Bridge & Dredging Co., 233 P. 936, 133 Wash. 323, 1925 Wash. LEXIS 1195 (Wash. 1925).

Opinion

Mackintosh, J.

The James Henry Packing plant is situated on the tide flats in the city of Seattle on the west side of Ninth avenue south. One of the buildings is approximately 240 feet square and rests upon 800 piles, and in 1923 it became necessary to raise it four and one-third feet to conform to the newly established grade-on Ninth avenue south. In June the respondents took the contract to make the raise and started work in the first week of that month. The city of Seattle, desirous of changing the grade of Ninth avenue south and filling the street as it was extended over the tide flats, in March, 1923, had entered into a contract with the appellant to do this work. This fill was to be made by sluicing dirt from a hill lying on the opposite side *325 of Ninth avenue south from the Henry plant. When the respondents began work on their contract, there was an open space between the floor joists of the building and the tide flats underneath of an average of five feet, and a good deal of the earth underneath was dry and could be conveniently used by the respondents’ employees in their work in preparing the building to be raised and in the work of raising it. Under the building was a couple of ditches used for the purpose of taking off water which accumulated from various sources, the water from these ditches being emptied by pumps.

The respondents had been prosecuting their work for a few days when water carrying clay from the fill being made in Ninth avenue south began to cover the earth underneath the building. This condition continued until the last day of August when the respondents completed their work, and during that time there were from 18 inches to 30 inches of slime and mud deposited underneath the building by the appellant’s operations, this mess coming up to within two and one-half feet of the floor joists. This condition, the respondents contend, necessitated the use by them of more material than they otherwise would have had to use, delayed their work by reason of the fact that their employees, under the unfavorable conditions, could not do more than one-third to one-fourth of the average day’s work, and resulted in the loss of some of their equipment.

This action was begun against the appellant to recover these damages, and as a co-defendant one Case was joined with the appellant, it being alleged in the complaint that Case was a vice-principal of the appellant and in charge of the work. Recovery is sought upon the ground that the appellant, in carrying out its contract with the city, was negligent in at least two particulars ; namely: that, for the purpose of holding the *326 fill it constructed bulkheads which were defective in that they allowed a portion of the filling material to spread over the ground underneath the Henry plant; and second, that there was negligence in breaking a city water main on Ninth avenue south, which added to the flood underneath the building. After an extended trial which produced about 1,000 pages of statement of facts, the jury returned a verdict for $6,446.55 in favor of the respondents against the appellant, and a verdict discharging Case from liability. The sluicing' company appeals and presents many reasons why the judgment should be reversed.

The first of the reasons suggested is that the release of Case by the jury is, in law, a release of the appellant, and that therefore the motion for judgment notwithstanding the verdict should be granted. In Doremus v. Root, 23 Wash. 710, 63 Pac. 572, 54 L. R. A. 649, the rule was announced, which has been followed in some thirteen or fourteen cases since, that a judgment in favor of the servant, in an action to recover damages for a tort committed by the servant, is a bar to an action against the master to recover damages for the same tort of the servant, and where the servant and the master have been joined in actions of this nature a dismissal of the servant dismisses the master. With this rule of law there can be no quarrel, and were the record indisputably such as would justify the court or a jury in saying that the acts which are relied on as a basis of the respondents’ cause of action were acts committed by Case as a servant or employee of the appellant, the argument of appellant would be conclusive. The record, however, discloses a dispute, and although it is true that the respondents drew their complaint on the theory that Case was the one who, as a representative of the appellant, was guilty of the negligent acts, the testimony introduced alters the situation, and it *327 is upon the testimony in the case and not upon the allegations in the complaint that, under the rules of practice in this court, the issue must be determined. There was testimony, which the jury had a right to believe, that Case was, as described by one of appellant’s witnesses, a fill superintendent only, and that he was under the supervision of other employees and officers of the appellant, and that the principle of respondeat superior is not conclusive in this action, and the jury had a right to believe that the appellant was guilty of negligence independently of any negligence of Case, and under such conditions the release of the employee would not release the master. Jones v. Seattle, 51 Wash. 245, 98 Pac. 743; O’Brien v. American Casualty Co., 58 Wash. 477, 109 Pac. 52; Aldrich v. Inland Empire Tel. & Tel. Co., 62 Wash. 173, 113 Pac. 264; Armack v. Great Northern R. Co., 126 Wash. 533, 219 Pac. 52.

The next reason assigned for the absolute release of the appellant from liability is that the appellant, doing work under the direction of the city officials, was only an employee of the city, and the city in this case acted within its general power for the granting of contracts for street work, and the work was done in accordance with the provisions of the contract and under the supervision of the city officials, who superintended the work, and if damages resulted from no negligence or wrongdoing of the contractor, but from the performance of the contract in the way it is required to be done by the contract, then the contractor was the agent of the city and was not liable to a person injured thereby, who must seek his redress from the city. Dillon, Municipal Corporations (5th ed.), vol. 3, page 1655; Lund v. St. Paul, M. & M. R. Co., 31 Wash. 286, 71 Pac. 1032, 96 Am. St. 906, 61 L. R. A. 506; Potter v. Spokane, 63 Wash. 267, 115 Pac. 176; Wood v. Tacoma, 66 Wash. *328 266, 119 Pac. 859; Casassa v. Seattle, 66 Wash. 146, 119 Pac. 13; Quinn v. Peterson & Co., 69 Wash. 207, 124 Pac. 502; Kaler v. Puget Sound Bridge & Dredging Co., 72 Wash. 497, 130 Pac. 894; Stern v. Spokane, 73 Wash. 118, 131 Pac. 476, 46 L. R. A. (N. S.) 620; Hieber v. Spokane, 73 Wash. 122, 131 Pac. 478; Larned v. Holt & Jeffery, 74 Wash. 274, 133 Pac. 460, 46 L. R. A. (N. S.) 635; Ettor v. Tacoma, 77 Wash. 267, 137 Pac. 820; Granger Tel. & Tel. Co. v. Sloan Bros., 96 Wash. 333, 165 Pac. 102.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Grays Harbor Community Hospital
675 P.2d 239 (Court of Appeals of Washington, 1983)
Fish v. Southern Pacific Co.
145 P.2d 991 (Oregon Supreme Court, 1943)
Fonda v. Northwestern Public Service Co.
292 N.W. 712 (Nebraska Supreme Court, 1940)
Muskatell v. Queen City Construction Co.
100 P.2d 380 (Washington Supreme Court, 1940)
Schosboek v. Chicago, Milwaukee, St. Paul & Pacific Railroad
71 P.2d 548 (Washington Supreme Court, 1937)
Wolten Grocery Co. v. Puget Sound Bridge & Dredging Co.
4 P.2d 863 (Washington Supreme Court, 1931)
Senske v. Washington Gas & Electric Co.
4 P.2d 523 (Washington Supreme Court, 1931)
Boggess v. King County
274 P. 188 (Washington Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
233 P. 936, 133 Wash. 323, 1925 Wash. LEXIS 1195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtis-v-puget-sound-bridge-dredging-co-wash-1925.