Curtis Park Group, LLC v. Allied World Specialty Insurance Company

CourtDistrict Court, D. Colorado
DecidedSeptember 9, 2020
Docket1:20-cv-00552
StatusUnknown

This text of Curtis Park Group, LLC v. Allied World Specialty Insurance Company (Curtis Park Group, LLC v. Allied World Specialty Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtis Park Group, LLC v. Allied World Specialty Insurance Company, (D. Colo. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO

Case No. 1:20-cv-00552-CMA-NRN

CURTIS PARK GROUP, LLC,

Plaintiff,

v.

ALLIED WORLD SPECIALTY INSURANCE COMPANY,

Defendant.

ORDER ON PLAINTIFF’S EMERGENCY MOTION FOR PROTECTIVE ORDER (Dkt. #25)

N. REID NEUREITER United States Magistrate Judge

This matter comes before the Court on Plaintiff Curtis Park Group’s (“Curtis Park”) Emergency Motion for Protective Order, filed July 8, 2020. Dkt. #25. I held a Telephonic Discovery Hearing on the issue on July 10, 2020. Dkt. #28. Recognizing the factual and legal complexity of the dispute, I allowed further briefing by the Parties. See Dkt. #29 (Curtis Park’s Brief Regarding Privilege and Waiver in Support of its Emergency Motion for Protective Order); Dkt. #33 (Allied World Specialty Insurance Company’s (“Allied World”) Brief in Response to Curtis Park’s Brief Regarding Privilege and Waiver in Support of its Emergency Motion for Protective Order); and Dkt. #34 (Curtis Park’s Reply Brief Regarding Privilege and Waiver in Further Support of its Emergency Motion for Protective Order). I denied Defendant Allied World’s Motion for Leave to File a Sur-Reply for failure to adequately confer with opposing counsel. See Dkt. #42. I heard post-briefing argument from the Parties on August 27, 2020. Now, being fully informed and for the reasons discussed below, it is hereby ORDERED that the Motion is GRANTED IN PART AND DENIED IN PART. Factual Background This is an insurance coverage case arising from a Builders’ Risk insurance policy covering construction of a condominium project. The condominium project had a

concrete slab that experienced deflection and cracking. The discovery dispute arises from reports and documents created by consultants retained by Curtis Park and its concrete subcontractor to determine the cause of cracks and deflections in the concrete slab and make recommendations for a potential fix. Depending on the cause of the problem, the costs associated with correcting the defect may or may not be covered by the builders’ risk insurance policy issued by Allied World. There are three categories of documents at issue. First is the “Harris Report,” a document issued on March 7, 2018 from J.R. Harris & Company, a structural engineering firm, to Mr. Patrick Casey of the Fox Rothschild law firm. See Dkt. #31

(submitted for in camera review). Second is the so-called “Basham Letter,” a letter written on May 17, 2018 to Mr. Todd Hensley, Project Manager at All-Phase Concrete Construction, from Kim Basham, Professional Engineer with KB Engineering. See Dkt. #30 (submitted for in camera review). The Basham Letter recites some preliminary findings regarding Mr. Basham’s investigation of the cause of the slab cracking. The final set of documents at issue are the underlying files, documents, and communications of the J.R. Harris & Company firm that Allied World has subpoenaed. These underlying files were presumably used by Dr. Harris to create the Harris Report. I have reviewed in camera both the Harris Report and the Basham Letter. Based on affidavits and representations of the Parties, the Court gleans the following about these documents and the dispute. In late December 2017, unexpected deflection was discovered in the concrete decks above the parking garage of the construction project. Curtis Park and its contractor, Milender White Residential (“MW”), investigated the property damage to

determine a fix. Those two reserved rights against each other and conducted preliminary investigations and repairs. In the spring of 2018, Curtis Park’s outside counsel with Fox Rothschild, Mr. Patrick Casey, retained Dr. James R. Harris as a consulting engineer to analyze the damage to the project. At the time of the retention, Curtis Park says it was anticipating litigation and Mr. Casey requested that Dr. Harris serve as a consultant to preliminarily opine on potential causes for the damage at the project. Dr. Harris produced the Harris Report reflecting his preliminary investigation, and delivered it to Mr. Casey. Mr. Casey says the Harris Report was confidential work product and was intended to be kept

confidential in order for Mr. Casey to provide legal assistance to Curtis Park. But, on its face, there is nothing to indicate that the Harris report was intended to be confidential or was to be limited in its circulation. The document does not have any “confidential” notation, does not say it is either “privileged” or “work product,” nor suggest that it would be inappropriate to distribute to anyone other than counsel. Around the same time, the project’s concrete subcontractor, All-Phase Concrete Construction, Inc. (“All-Phase”), retained Kim Basham of K.B. Engineering as a structural engineering consultant to analyze observed deflection and resulting damage to the project. All-Phase and MW were working together to address the deflection problem under a reservation of rights, purportedly with the hope of avoiding litigation. All-Phase and MW executed a settlement agreement in March of 2018 to allow All- Phase and MW to work together to address the deflection problem under a full reservation of rights. All-Phase’s lawyer has submitted an affidavit saying that Mr. Basham was

retained in anticipation of litigation and was serving as a consultant to investigate and opine on potential causes for the damage. Notably, All-Phase’s lawyer in his affidavit does not say that he retained Mr. Basham, only that Mr. Basham “was retained on behalf of All-Phase.” Dkt. #29-4 at 3. On May 17, 2018, Mr. Bashman prepared a letter outlining his preliminary engineering findings regarding his investigation and analysis (the Basham Letter). According to All-Phase’s lawyer, the Basham Letter “was intended to be kept confidential and was prepared in connection with legal advice and assistance to All-Phase.” According to All-Phase’s counsel, to the extent that the Basham Letter was shared with other members of the design and construction teams for the project, it

was done so under the auspices of a proposed settlement agreement. The Basham Letter was supplemented following a July 2018 meeting that Mr. Basham attended at the project site. All-Phase’s lawyer, John Zakham, says that the later version of the Basham Letter was similarly intended to be kept confidential and was prepared in connection with legal advice and assistance to All Phase. It, too, was purportedly shared with other members of the design and construction teams “under the auspices” of the proposed settlement. Like the Harris Report, there is nothing on the face of the Basham Letter to suggest that it was work product, was intended to be confidential, or that its distribution is to be limited in any way. There is nothing on the document itself suggesting that it was created or provided to other members of the design and construction teams in the context of settlement negotiations. In addition, the Basham Letter was written directly to the Project Manager at All-Phase, not to any attorney. The evidence indicates that All Phase hired Mr. Basham directly and that he was not hired by counsel.

Sometime after the receipt of the March 7, 2018 Harris Report, the document was shared with MW. Mr. Jason Miller of Curtis Park submitted an initial affidavit swearing that “per Curtis Park’s request, Mr. Casey [the lawyer] shared the Harris Report with Darren Hinton with MW as part of ongoing settlement communications that were intended to be kept confidential and result in an informal resolution.” Dkt. #29-1 at 4, ¶ 9. But the documentation tells a different story. It was Curtis Park’s Mr. Miller who wrote a March 13, 2018 letter to MW enclosing the Harris Report. There is nothing in the cover letter that suggests the Report is confidential and should be limited in distribution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hickman v. Taylor
329 U.S. 495 (Supreme Court, 1947)
In Re Qwest Communications International Inc.
450 F.3d 1179 (Tenth Circuit, 2006)
v. GEICO Casualty Company
2018 CO 87 (Supreme Court of Colorado, 2018)
Sanchez v. Matta
229 F.R.D. 649 (D. New Mexico, 2004)
Anaya v. CBS Broadcasting, Inc.
251 F.R.D. 645 (D. New Mexico, 2007)
Fox v. California Sierra Financial Services
120 F.R.D. 520 (N.D. California, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Curtis Park Group, LLC v. Allied World Specialty Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtis-park-group-llc-v-allied-world-specialty-insurance-company-cod-2020.