Cunningham-Woodward Co. v. State

119 Misc. 761
CourtNew York Court of Claims
DecidedDecember 15, 1922
DocketClaim No. 636-A
StatusPublished

This text of 119 Misc. 761 (Cunningham-Woodward Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cunningham-Woodward Co. v. State, 119 Misc. 761 (N.Y. Super. Ct. 1922).

Opinion

Wood, J.

On April 18, 1910, Cunningham & Woodward, a copartnership, entered into a contract with the state of New York for the construction of a dike and highway along the Oswego river in the vicinity of Fulton, N. Y. Thereafter the copartnership with the consent of the state assigned its contract to the Cunningham-Woodward Company, the claimant herein. The contract was to be completed by August 20, 1910, and embraced several items of work, but the claim here asserted arose out of items 1 and 2 of the itemized proposal for bidders. The work under these items called for excavating material from borrow pits and placing the material on the embankment forming the dike. The bidders’ map [762]*762which accompanied the proposal indicated that the borrow pit would be located on the Limbeck farm adjacent to the work.

The specifications of the contract provided in part:

Material used in forming embankment shall be satisfactory to the Engineer and of a nature that will under proper manipulation compact into a solid impervious and permanent embankment. It shall be free from perishable material and from other material liable to become unstable when saturated with water after having been compacted.

Material to be borrowed shall be taken from borrow pits shown upon the plans and if sufficient suitable material is not found in them, it shall be taken from the nearest available locations, selected by the Engineer.

When sufficient suitable material for forming embankment or backfill is not obtained from the excavation, the deficiency shall be supplied by the contractor, from borrow pits located and appropriated by the State for free use by said contractor.”

The claim is based, first, on the loss sustained by delays caused by the failure of the state to furnish a borrow pit from which to excavate material and by the additional time required to handle the material actually furnished by the state; and second, on the loss sustained by reason of the additional and increased cost of handling the material furnished by the state — material alleged to be substantially different than that bid on and specified in the contract.

With respect to the first part of the claim it appears that shortly after the signing of the contract the claimant began to assemble machinery, equipment and men and actually began work on and about the dike, preliminary to excavation, on April 28, 1910. At about this time the state decided to enlarge the contract and on May 5, 1910, asked claimant to consent to a change of borrow pits from the Limbeck farm to the Taylor farm, some half mile further south, giving as the reason that ample material for the increased excavation could there be had and that it was more convenient to the work. Claimant on the same day consented to the change. The modifying contract, known as alteration contract No. 2, providing for the additional excavation and for the change in borrow pits was, however, not approved by the canal board until June 25, 1910, and was not signed by the parties hereto until June 28, 1910. The time for the completion of the contract as amended was extended to the fall of that year. Thus the substituted Taylor pit was not made available to the claimant until fifty-four days after the consent was given.

In the meantime the steam shovel for excavation work and engines and cars for carrying the excavated material to the dike [763]*763and men to operate them were brought to the work area and remained idle pending the appropriation of a borrow pit by the state. The expense occasioned by this delay is sought to be recovered. Obviously there can be no recovery unless the state failed in a duty it owed to claimant. It cannot be denied that the state owed to' the claimant all reasonable opportunity to progress the work with all reasonable speed. The state agreed to furnish borrow pits for the excavation and fill. It failed to do so for at least fifty-four days after the change to the Taylor pit was consented to, and, as claimant was put to additional and unnecessary expense, recovery should be had for this item of claim.

Claimant also contends, and the proof amply supports the contention, that after excavation work was begun in the Taylor pit, material of a character entirely different from that specified in the contract for embankment was found and that the excavating of this material and the placing of it upon the dike so delayed the progress of the work that the. contract was not completed before November of the following year.

It appears that weather conditions made it necessary to shut down operations on November 23, 1910. This was done after conference with the state’s engineer and by his direction. The machinery and plant were dismantled and housed for the winter.

In the latter part of May, 1911, claimant began to take the machinery out of storage and to reassemble the plant for operation. By June 1, 1911, the plant was ready to resume work and actually did do so for a day or two but the borrow pit was so wet and the material so soft and unfit for use that work was discontinued and was not resumed until June 28, 1911. Between these dates the state inspected other lands adjacent to the work upon which to locate another borrow pit, and certain recommendations were made but nothing was accomplished and the contractor was directed to resume operations in the old pit on the latter date.

The claimant contends that it should be reimbursed for the expenses incurred in taking down the machinery and plant in the fall of 1910, in housing the machinery during the winter, and in reassembling it in the spring of 1911. Concurrence in this contention depends on whether the delay in completing the contract in 1910, and in the carrying of the work over until the spring of 1911 was caused by the state or was occasioned by any fault of claimant. We believe the testimony clearly established the fault to be entirely with the state in breaching its obligation to furnish borrow pits of specified material and that recovery should be had for the loss thereby sustained.

We now come to a consideration of the second part of the claim. [764]*764Under the terms of the contract the state was to locate and furnish, free to claimant, the necessary borrow pits from which to obtain suitable material to construct the dike and highway. It is conceded that claimant was obligated to take the material from borrow pits so designated by the state. The contractor could not itself select the material or borrow pits or on its own volition change the borrow pits if they contained improper material. The selection rested solely with the state. The contractor had to use what the state gave it to use and surely it cannot be successfully argued that if the state violated the terms of its own contract, it should not answer in damages. On the plans accompanying proposal for bidders the location of the borrow pits was designated and it appears that the contractor satisfied itself by an investigation that the required quantity of the specified material was there to be had and accordingly made its bid.

The work had progressed in its initial stage for some time when the state’s engineer requested the claimant to consent to a change in the location of the borrow pit from the Limbeck farm to the Taylor farm, and claimant readily consented after a hurried inspection of the test pit dug on the Taylor farm. It is evident that the state simply intended to effect a change of location of borrow pits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foundation Company v. . State of New York
135 N.E. 236 (New York Court of Appeals, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
119 Misc. 761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cunningham-woodward-co-v-state-nyclaimsct-1922.