CSX Transp., Inc. v. City of Fayetteville

785 S.E.2d 760, 247 N.C. App. 517, 2016 WL 2865094
CourtCourt of Appeals of North Carolina
DecidedMay 17, 2016
Docket15-1286
StatusPublished
Cited by9 cases

This text of 785 S.E.2d 760 (CSX Transp., Inc. v. City of Fayetteville) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CSX Transp., Inc. v. City of Fayetteville, 785 S.E.2d 760, 247 N.C. App. 517, 2016 WL 2865094 (N.C. Ct. App. 2016).

Opinion

TYSON, Judge.

*518 CSX Transportation, Inc. ("CSX") appeals from order granting summary judgment in favor of defendants City of Fayetteville and the Public Works Commission ("PWC") on whether the parties' contractual agreement required PWC to indemnify CSX for its own negligence, and denying CSX's motion for partial summary judgment on its contractual indemnity claim. CSX also appeals from order granting summary judgment in favor of PWC on CSX's claim for indemnification. We reverse the trial court's order granting summary judgment in favor of PWC, grant CSX's motion for partial summary judgment on its contractual indemnity claim, and remand.

I. Factual Background

In 1951, PWC entered into a contract ("the Crossings Agreement") with Atlantic Coast Line, CSX's predecessor-in-interest, which allowed PWC, as licensee, to install aerial power lines over a section of railroad tracks. The Crossings Agreement includes an indemnification provision, which states:

The Licensee will indemnify and save harmless the Railroad Company, its successors and assigns, from and against all loss, cost, damage and expense, and from and against any and all claims or demands therefor, on account of injury to person or property, which may be incurred by the Railroad Company by reason of the construction, maintenance, use or operation of the said conductors, wires or supports, *519 or by reason of the exercise of any of the privileges conferred by this license or agreement.

It is not disputed that CSX, as successor-in-interest to the Atlantic Coast Line, has the right to enforce the 1951 agreement.

The Crossings Agreement requires all power lines installed by PWC to be maintained at an elevation of at least twenty-seven or twenty-eight feet above the top of the railroad tracks, depending on the line's voltage. Pursuant to the Crossings Agreement, PWC installed utility poles on both sides of the railroad tracks running adjacent to 3024 Clinton Road, in Fayetteville, North Carolina, and connected two aerial lines between these poles.

On 14 March 2011, CSX employee Donald Herring ("Mr. Herring") was operating a crane on the railroad tracks and struck one or more of the power lines crossing over the tracks. By the time Mr. Herring realized his crane would not pass under the power lines, it was too late for him to stop.

The parties' briefs present conflicting evidence of whether the height of PWC's lines complied with the elevation requirements contained in the Crossings Agreement. A CSX investigation concluded PWC's lines were hanging lower than required by the Crossings Agreement. CSX alleged in its complaint the power lines were hung no higher than eighteen feet, seven inches.

Conversely, PWC's engineer measured one of the power lines as twenty-seven feet, seven inches above the tracks. PWC also hired an independent electrical engineer who opined that the height of the power lines was in compliance with the Crossings Agreement.

The collision caused a power surge of electrical current into equipment owned by a third party, CenturyLink, through a "common ground" which connected PWC's and *762 CenturyLink's lines. The power surge caused extensive damage to CenturyLink's equipment, including underground wiring and an above-ground utility pedestal. CenturyLink repaired its property and issued demands on CSX to pay for damages to CenturyLink's property purportedly caused by the power surge. CSX settled the CenturyLink claim by paying $118,000.00 in March 2013.

After CSX compensated CenturyLink, it sought indemnification from PWC pursuant to the indemnification provision within the Crossings Agreement. PWC denied CSX's claim for indemnification. On 11 March 2014, CSX filed a complaint against PWC, and alleged claims for: (1) breach of contract/contractual indemnity;

*520 (2) NEGLIGENCE/gross negligence; (3) common law indemnity; (4) trespass; (5) private nuisance; and, (6) contribution. PWC responded by filing an answer, a counterclaim, and a third-party complaint against Time Warner Cable Southeast, LLC ("Time Warner").

In April 2015, PWC and Time Warner filed motions for summary judgment, and CSX filed a motion for partial summary judgment. The parties' motions were heard on 7 May and 12 May 2015 before the Honorable Tanya T. Wallace. The trial court granted Time Warner's motion for summary judgment and dismissed it from the case. No party appealed from this ruling and order. The parties stipulate Time Warner is not a party to this appeal.

On 28 May 2015, Judge Wallace entered a written order granting in part and denying in part CSX's motion for partial summary judgment. Judge Wallace concluded a genuine issue of material fact existed with regard to CSX's claim for indemnification, and denied CSX's motion for summary judgment on this issue. Judge Wallace granted CSX's motion for summary judgment on PWC's counterclaim, and dismissed the counterclaim with prejudice.

That same day, Judge Wallace also entered a written order, which granted in part and denied in part PWC's motion for summary judgment. Judge Wallace ruled as follows:

1. [PWC's] Motion for Summary Judgment as to [CSX's] first claim for relief, Count One: Indemnification, is denied.
2. The Crossing[s] Agreement does not require [PWC] to indemnify [CSX] for the negligence of [CSX] or its employees. This issue is resolved as a matter of law.
3. [PWC's] Motion for Summary Judgment as to all of [CSX's] remaining claims for relief is granted. [CSX's] claims for relief designated as Count Two: Negligence/Gross Negligence; Count Three: Common Law Indemnity; Count Four: Trespass; Count Five: Private Nuisance; and Count Six: Contribution are hereby dismissed with prejudice.

Judge Wallace denied PWC's motion for summary judgment on CSX's claim for indemnification after she determined a genuine issue of material fact existed with regard to CSX's negligence.

On 18 May 2015, the day trial was scheduled to begin before the Honorable Beecher Gray, CSX filed an admission of negligence. In light of CSX's admission of negligence, PWC orally renewed its motion for summary judgment on CSX's claim for indemnification that same day.

*521 Judge Gray granted PWC's renewed motion for summary judgment based upon Judge Wallace's prior order, which had concluded as a matter of law PWC was not required to indemnify CSX for CSX's own negligence. This order was entered on 8 June 2015. CSX gave timely notice of appeal to this Court.

II. Issue

CSX argues the trial court erred by granting summary judgment in favor of PWC. CSX contends the trial court incorrectly concluded that North Carolina law does not allow a party to be indemnified for its own negligence.

III. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Encompass Servs., Pllc v. Maser Consulting P.A.
2021 NCBC 40 (North Carolina Business Court, 2021)
Knc Techs., LLC v. Tutton
2021 NCBC 25 (North Carolina Business Court, 2021)
Murphy-Brown, LLC v. Ace Am. Ins. Co.
2020 NCBC 96 (North Carolina Business Court, 2020)
Vanguard Pai Lung, LLC v. Moody
2020 NCBC 56 (North Carolina Business Court, 2020)
Duke Energy Carolinas, LLC v. Ag Ins. sa/nv.
2020 NCBC 47 (North Carolina Business Court, 2020)
Morgan v. Turn-Pro Maint. Servs., LLC
2020 NCBC 5 (North Carolina Business Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
785 S.E.2d 760, 247 N.C. App. 517, 2016 WL 2865094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/csx-transp-inc-v-city-of-fayetteville-ncctapp-2016.