Crudup v. Oklahoma Portland Cement Co.

1916 OK 386, 156 P. 899, 150 P. 899, 56 Okla. 786, 1916 Okla. LEXIS 779
CourtSupreme Court of Oklahoma
DecidedMarch 28, 1916
Docket6852
StatusPublished
Cited by3 cases

This text of 1916 OK 386 (Crudup v. Oklahoma Portland Cement Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crudup v. Oklahoma Portland Cement Co., 1916 OK 386, 156 P. 899, 150 P. 899, 56 Okla. 786, 1916 Okla. LEXIS 779 (Okla. 1916).

Opinion

Opinion by

LINN, C.

The Oklahoma Portland Cement-Company, defendant in error and plaintiff below, by proper proceedings in the district court, sought a recovery against defendants as sureties upon a certain obligation executed in favor of the independent school district of Celeste, Tex., and primarily for its benefit, but with a provision intended as security for parties who might furnish material, labor, etc.

In substance, among other things, it was alleged in the petition that plaintiff had furnished cement to the value of $503.10 which was used in the construction of a certain school building, and that defendants had refused to pay the same or any part thereof. A copy of the instrument sued on was attached to and made a part of the peti *788 tion. Plaintiff prayed judgment for said amount with interest and a reasonable attorney’s fee, which was provided for in said bond. The defendant Sam Dane filed a separate answer. The other defendants, the sureties, filed a joint answer. But both answers were substantially to the same effect. After a general denial, it was alleged, in substance: That the bond was signed on Sunday; that plaintiff was not entitled to recover under the law, ■ for the reason that no lien could attach in its faVor upon the building constructed; that the material furnished to the amount of $250 was not used in the construction of the building; that the architect for the school district, in violation of the building contract, and without the knowledge of the defendants, made certain changes in the plans, .increasing the cost in material used in said building'; that the said obligee, in violation of the building contract, paid the contractor in excess of 90 per cent, of the estimate provided for therein; that the directors of the school district, without a good cause, discharged the contractor and took charge of the building; that said bond was not signed by the principal obligor.

The obligation, the basis of this suit, among others, contains the following provision, to wit:

“It is also understood that this bond shall be considered as made to all creditors and conditioned that said contractor shall pay all indebtedness incurred for labor or material furnished in the construction of a certain 63 ft. x 107 ft. brick school building in accordance with plans, specifications and contract and any person or persons to whom there is due any sum of money for labor or material furnished as stated in said specifications and contract, or his assigns, may bring action on this bond for said indebtedness in the sum - of $10,000.00, lawful money of the United States of America to be paid to the said superintendent of the school district of Celeste, Tex., through *789 the school board and parties who may be entitled to any moneys as aforesaid, their executors, administrators or assigns, for which payment well and truly to be made, we bind ourselves and each of our heirs, executors, administrators, jointly and severally firmly by these presents.”

The cause was tried to the court, and separate findings of fact and law, being requested, were, made and filed, and judgment based thereon was rendered in favor of plaintiff in the sum of $253.10, and the further sum of $50, attorney’s fee. Motion for a new trial was filed, overruled, and exceptions saved, and error has been prosecuted to this' court by defendants filing their petition in ■error with case-made attached.

Various assignments of error are alleged, which we deem unnecessary to set out at length, but counsel for plaintiffs in error present certain questions for our determination, in substance, as follows: (1) What constitutes a bond, and what is a proper and legal execution thereof? (2) What changes in the original contract will release the sureties on the bond? (3) Will payment made to the contractor in excess of the amount specified in the contract release the sureties? (4) Did the obligation sued on secure the plaintiff a right of action against the sureties, said plaintiff under the law not having a lien against the building constructed? These questions will be considered in the order in which they are presented.

First. It is the contention of the plaintiffs in error that the purported obligation sued on is not a legal bond; (a) For the reason it was not signed by the purported obligor; and (b) that it was signed by the sureties on Sunday, hence is void.

*790 Under the facts found by the court, which findings are not seriously questioned by counsel as not supported by sufficient evidence, we are constrained to hold that the bond in question is not invalid for either of the assigned reasons. Under the second finding of fact, the court found that while the bond was signed on • Sunday in the State of Oklahoma, it bore date of the 5th of May (Monday), and that the bond was delivered by the contractor, the principal obligor, on a date other than Sunday; that the beneficiaries in the bond had no knowledge that it was signed on Sunday.

Undoubtedly the rule is supported by the great weight of authority that in the absence of a special statute making a contract void when executed under the circumstances as here, the same is not void. Hall v. Parker, 37 Mich. 590, 26 Am. Rep. 540; Evansville v. Morris, 87 Ind. 269, 44 Am. Rep. 763; Terry v. Platt, 1 Pennewill (Del.) 185, 40 Atl. 243; Hofer v. Cowan (Ky.) 68 S. W. 438; Barger v. Farnham, 130 Mich. 504, 90 N. W. 281; Diamond Glass v. Gould (N. J. Sup.) 61 Atl. 12; Gibbs & Sterrett v. Brucker, 111 U. S. 597, 4 Sup. Ct. 572, 28 L. Ed. 534.

In .the case of Gibbs & Sterrett v. Brucker, supra, where a bond in the State of Wisconsin was signed and delivered on Sunday to a representative of the obligee, but such obligee had no knowledge of such fact, which case' arose under a statute of that state making it a criminal offense to do any manner of labor, business, or work on Sunday, except work of necessity and charity, the court, speaking through Mr, Justice Woods, said:

“The grounds upon which courts have refused to maintain actions on contracts made in contravention of statutes for the observance of the Lord’s day is the ele *791 mentary principle that one who has himself participated in the violation of the law cannot be permitted to assert in a court of justice any right founded upon • or growing out of the illegal transaction.”

It will be noted that the statute referred to in the decision quoted from is similar to the statute of this state.

There being no specific statute in this state making a contract void when signed on Sunday but delivered on á week day, we are impelled to hold that the bond in question is not void solely on the ground that it was signed on Sunday, when, as here, it bore date of a week day, and was delivered on a day other than Sunday. The law is well settled that an agreement does not become a complete and effective contract until delivery; in other words, the execution of a contract includes both the signing and delivery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Cooper
1950 OK 327 (Supreme Court of Oklahoma, 1950)
Birmingham News Co. v. Moseley
141 So. 689 (Supreme Court of Alabama, 1932)
St. Paul Foundry Co. v. Evenson
211 N.W. 834 (Supreme Court of Minnesota, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
1916 OK 386, 156 P. 899, 150 P. 899, 56 Okla. 786, 1916 Okla. LEXIS 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crudup-v-oklahoma-portland-cement-co-okla-1916.