Crowder v. Alumaflex

986 P.2d 1269, 163 Or. App. 143, 1999 Ore. App. LEXIS 1614
CourtCourt of Appeals of Oregon
DecidedSeptember 29, 1999
Docket94-12846; CA A95865
StatusPublished
Cited by8 cases

This text of 986 P.2d 1269 (Crowder v. Alumaflex) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crowder v. Alumaflex, 986 P.2d 1269, 163 Or. App. 143, 1999 Ore. App. LEXIS 1614 (Or. Ct. App. 1999).

Opinion

*145 ARMSTRONG, J.

Claimant seeks review of a decision by the Workers’ Compensation Board that denied his claim for increased permanent partial disability (PPD) benefits under the 1995 amendment to ORS 656.214(6). The Board denied the claim on the ground that claimant had not raised the issue of the PPD rate on reconsideration of the determination order in which the PPD rate had been applied. Claimant also challenges the Board’s determination that he failed to prove that his compensable injury was the major contributing cause of his current psychological condition. 1

The following facts are undisputed. Claimant was injured on February 1,1990, while working as a patio cover/ awning installer for employer. As a result of his compensable injury, claimant underwent low back surgery in March 1990 and April 1993. After a comprehensive pain evaluation, claimant was declared medically stationary in May 1994. Claimant’s claim was closed by a determination order in August 1994 that awarded him 50 percent, or 160 degrees, of unscheduled PPD. The order awarded claimant $16,000 for the 160 degrees of PPD, based on the existing statutory rate for such awards of $100 per degree of disability. See former ORS 656.214(5) (1995). Claimant requested reconsideration but did not challenge the rate at which his PPD benefits had been calculated. An order on reconsideration was issued on May 12, 1995, affirming the 50 percent unscheduled PPD and adding an award of 26 percent scheduled PPD. Claimant previously had requested a hearing and, on May 15, 1995, he *146 filed a notice of his intention to raise the following additional issues at that hearing: “Appeal order on reconsideration for time loss, premature closure, additional permanent partial disability, permanent total disability, penalties and fees.”

On June 7, 1995, an amendment to the Workers’ Compensation Law took effect that changed the rate at which PPD benefits were to be calculated. Or Laws 1995, ch 332, §§ 17-18; ORS 656.214(6). Under the new law, which was made applicable to cases pending at the time that it took effect, Or Laws 1995, ch 332, § 66, the rate at which PPD benefits were to be calculated was changed from a flat $100 per degree to a grid system based on the total degrees of a worker’s disability. On November 30, 1995, claimant designated the change in PPD rates as an additional issue for the scheduled hearing.

At the hearing, the administrative law judge (ALJ) determined that claimant’s unscheduled disability had been miscalculated and awarded him four percent more of unscheduled disability. The ALJ also concluded that the new statutory rate applied to all of claimant’s scheduled and unscheduled PPD benefits and ordered employer to recalculate those benefits under the new rates. The ALJ rejected claimant’s contentions that his claim had been prematurely closed and that his current psychological condition was a consequence of his compensable injury.

Employer appealed to the Board, contending that the ALJ had erred in applying the new statutory rate for PPD, because claimant had not raised the rate issue on reconsideration. Claimant cross-appealed, raising the issues of the compensability of his psychological condition, the denial of PTD benefits, and premature claim closure. 2 The Board affirmed the ALJ’s decisions as to claimant’s psychological condition, PTD benefits and claim closure but concluded that claimant was not entitled to have his 50 percent unscheduled PPD paid at the new rate, because he had not raised that issue on reconsideration. ORS 656.283(7). However, because the 26 percent scheduled PPD and the extra *147 four percent unscheduled PPD had been awarded at reconsideration, the Board concluded that claimant was entitled to have those awards paid at the new rate.

On review, claimant contends that ORS 656.283(7) applies only to issues that actually existed at the time of reconsideration. He points out that the new rates, which were intended to apply retroactively, did not become effective until after the reconsideration process had been completed. He argues that once those new rates became effective, he was entitled to be paid at the new rate and, accordingly, that he had raised the issue at the first possible moment, which was at his scheduled hearing.

Employer counters that, even though the new law had not been enacted at the time of reconsideration, there was sufficient information available to put claimant on notice that the law might change, so that claimant could have raised the rate issue on reconsideration. Employer argues that, because claimant in theory could have raised on reconsideration the issue of the rate at which his PPD was to be paid, even though the rate set at closure was proper under the existing law, claimant was precluded from raising it later. We are not persuaded. We conclude that an issue that, because of the state of the relevant statutes, did not exist at the time of reconsideration but which, because of a change in those statutes, became an issue before hearing is not barred by ORS 656.283(7) from being raised at hearing.

ORS 656.283(7) provides, in relevant part:

“Evidence on an issue regarding a notice of closure or determination order that was not submitted at the reconsideration required by ORS 656.268 is not admissible at hearing, and issues that were not raised by a party to the reconsideration may not be raised at hearing unless the issue arises out of the reconsideration order itself.”

Although we look first to the text of a statute when we seek to discern the intent of the legislature, we analyze that text in context. PGE v. Bureau of Labor and Industries, 317 Or 606, 610, 859 P2d 1143 (1993). “[T]he context of the statutory provision at issue * * * includes * * * preexisting common law and the statutory framework within which the law was enacted.” Denton and Denton, 326 Or 236, 241, 951 P2d 693 *148 (1998) (emphasis added; citations omitted). In this case, ORS 656.283(7) speaks of issues that must be raised or lost.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pietrzykowski v. Albertsons, Inc.
111 P.3d 802 (Court of Appeals of Oregon, 2005)
SAIF Corp. v. Santos
94 P.3d 906 (Court of Appeals of Oregon, 2004)
Santos v. Caryall Transport
987 P.2d 1271 (Court of Appeals of Oregon, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
986 P.2d 1269, 163 Or. App. 143, 1999 Ore. App. LEXIS 1614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crowder-v-alumaflex-orctapp-1999.