Crouse v. LaGrange Junction Ltd.

2012 Ohio 2972
Ohio Court of Appeals·Decided June 29, 2012·No. 11CA010065·Published·Cited by 3 cases

Opinion

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF LORAIN )

KEN CROUSE C.A. No. 11CA010065 Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE

LAGRANGE JUNCTION LTD COURT OF COMMON PLEAS COUNTY OF LORAIN, OHIO

Appellant CASE No. 11CV172042

DECISION AND JOURNAL ENTRY Dated: June 29, 2012

DICKINSON, Judge.

INTRODUCTION

{¶1} Ken Crouse bought a vacant lot and, nine months later, entered into a contract with LaGrange Junction Ltd. for construction of a house on that lot. This case arose after Mr. Crouse suffered a number of problems with the lot and house that prevented him from legally occupying the house. He sued LaGrange, which answered and moved for a stay pending arbitration. Mr. Crouse opposed the stay, arguing that the arbitration clause in the construction contract was both substantively and procedurally unconscionable. The trial court denied the stay, and LaGrange appealed. This Court reverses because Mr. Crouse did not provide sufficient evidence of procedural unconscionability.

BACKGROUND

{¶2} Mr. Crouse bought a vacant lot from Mr. Stiner, a member of LaGrange Junction Ltd., and then entered into a construction contract with LaGrange for the building of a single-

family dwelling on that lot. According to his complaint, Mr. Crouse’s claims in this case are based on “severe and continued flooding covering the lot” and “numerous construction and/or design problems with the interior of the home.”

{¶3} Mr. Crouse sued four defendants: (1) LaGrange Junction Ltd., which had served as his builder, (2) Erie Coast Engineering LLC, an architectural and engineering firm, (3) an individual member of Erie Coast, who had worked as the architect and engineer on the project, and (4) Dennis R. Stiner, the seller of the real property at issue. Mr. Crouse sued Mr. Stiner for breach of the purchase contract for the vacant lot. He sued LaGrange for breach of the construction contract and negligent construction and/or repair. He sued Erie Coast for negligent design. He also brought claims against “Defendants” for breach of implied and express warranties, negligent supervision and retention, fraud, negligent misrepresentation, and deceptive trade practices. It is unclear whether those claims were aimed at all the named defendants or just some of them.

{¶4} LaGrange and Mr. Stiner jointly moved under Section 2711.02(B) of the Ohio Revised Code to dismiss and/or stay the proceedings, arguing that the construction contract required arbitration of the dispute. Mr. Crouse opposed the motion to dismiss and/or stay the proceedings, arguing that the arbitration clause is unenforceable due to substantive and procedural unconscionability. The trial court denied the motion, and LaGrange and Mr. Stiner timely appealed.

{¶5} The issue on appeal is limited to the enforceability of the arbitration clause in the LaGrange construction contract. That clause, if enforceable, applies only to claims arising under that contract. Mr. Crouse sued Mr. Stiner individually based on a separate transaction, that is, the sale of the vacant lot. Mr. Stiner has not argued that he is a party to LaGrange’s contract

with Mr. Crouse nor that the real estate contract between him and Mr. Crouse contains an arbitration clause. Therefore, although LaGrange and Mr. Stiner are represented by the same lawyer and both parties’ names appear on the notice of appeal and the briefs, for the sake of clarity, this Court will address LaGrange’s arguments without reference to Mr. Stiner.

JURISDICTION

{¶6} On September 23, 2011, this Court ordered LaGrange to demonstrate this Court’s jurisdiction because the order appealed provides only that the “Motion to Dismiss and/or Stay [P]roceedings is denied.” LaGrange responded to the order, explaining that the entry was a final, appealable order under Section 2711.02(C) of the Ohio Revised Code because the motion to stay or dismiss was based on a demand for arbitration. “[Section] 2711.02(C) permits a party to appeal a trial court order that grants or denies a stay of trial pending arbitration, even when the order makes no determination pursuant to [Rule 54(B) of the Ohio Rules of Civil Procedure].” Mynes v. Brooks, 124 Ohio St. 3d 13, 2009-Ohio-5946, at syllabus. Thus, despite the fact that Mr. Crouse’s claims remain pending against other defendants not involved in this appeal, the trial court’s entry denying the requested stay is immediately appealable by statute.

ARBITRATION

{¶7} The sole assignment of error is that the trial court incorrectly denied the motion to dismiss and/or stay the proceedings pending arbitration because it incorrectly determined that the arbitration clause is unenforceable due to unconscionability. “Arbitration agreements are ‘valid, irrevocable, and enforceable, except upon grounds that exist at law or in equity for the revocation of any contract.’” Taylor Bldg. Corp. of Am. v. Benfield, 117 Ohio St. 3d 352, 2008–Ohio–938,

¶ 33 (quoting R.C. 2711.01(A)). Unconscionability is a valid basis for revoking a contract. Id.

{¶8} “Unconscionability includes both ‘an absence of meaningful choice on the part of one of the parties together with contract terms which are unreasonably favorable to the other party.’” Taylor Bldg. Corp. of Am. v. Benfield, 117 Ohio St. 3d 352, 2008–Ohio–938, ¶ 34 (quoting Lake Ridge Acad. v. Carney, 66 Ohio St. 3d 376, 383 (1993)). “The party asserting unconscionability of a contract bears the burden of proving that the agreement is both procedurally and substantively unconscionable.” Id. (citing Collins v. Click Camera & Video Inc., 86 Ohio App. 3d 826, 834 (1993) (“One must allege and prove a ‘quantum’ of both prongs in order to establish that a particular contract is unconscionable”)). “The issue of unconscionability is a question of law.” Eagle v. Fred Martin Motor Co., 157 Ohio App. 3d 150, 2004–Ohio–829, at ¶ 12. Therefore, this Court reviews a trial court’s unconscionability decision de novo. Taylor, 2008–Ohio–938, at ¶ 2.

{¶9} The LaGrange construction contract contains an arbitration clause: “Any controversy [or] claim which does arise, or which arises out of construction o[r] sale of the new house or improvement thereto which is the subject of this contract, and which cannot be settled by buyer and seller, shall be settled by arbitration in Lorain, Ohio, at the instance of either party hereto. Such arbitration to be held with the American Arbitration Association and the arbitration will be in accordance with the industry arbitration rules of said association and judgment upon the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.”

PROCEDURAL UNCONSCIONABILITY

{¶10} “Procedural unconscionability concerns the formation of the agreement and occurs when no voluntary meeting of the minds is possible.” Brunke v. Ohio State Home Servs. Inc., 9th Dist. No. 08CA009320, 2008–Ohio–5394, ¶ 10 (quoting Porpora v. Gatliff Bldg. Co., 160 Ohio App. 3d 843, 2005–Ohio–2410, ¶ 7). To evaluate procedural unconscionability, this

Free access — add to your briefcase to read the full text and ask questions with AI

Crouse v. LaGrange Junction Ltd., 2012 Ohio 2972 (Ohio Ct. App. 2012).

2012 Ohio 2972 (Crouse v. LaGrange Junction Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kaufman v. Relx Inc.
2022 NY Slip Op 07192 (Appellate Division of the Supreme Court of New York, 2022)
Green v. Full Serv. Property Inspections, L.L.C.
2013 Ohio 4266 (Ohio Court of Appeals, 2013)