Crouch v. Gutmann

10 N.Y.S. 275, 32 N.Y. St. Rep. 254, 57 Hun 586, 1890 N.Y. Misc. LEXIS 2076
CourtNew York Supreme Court
DecidedJune 20, 1890
DocketNo. 1; No. 2
StatusPublished
Cited by3 cases

This text of 10 N.Y.S. 275 (Crouch v. Gutmann) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crouch v. Gutmann, 10 N.Y.S. 275, 32 N.Y. St. Rep. 254, 57 Hun 586, 1890 N.Y. Misc. LEXIS 2076 (N.Y. Super. Ct. 1890).

Opinion

Corlett, J.

On the 28th day of September, 1886, John Strachen, a mason and contractor of the city of Rochester, entered into a written agreement with Max L. Gutmann, of the same place, tó build and finish a four-story brick block and apartment-house in the city of Rochester, in pursuance of drawings, details, and general specifications made by James C. Cutler, an architect. The building was to be completed by the 1st day of April, 1887; the price, $16,500, to be paid in installments to the amount of 80 per cent, as the work progressed, and the balance on the proper completion of the work,—payments only to be made on the architect’s certificate. All the drawings or specifications are either embodied in, or referred to in, the agreement. On the same day John Wadsworth & Son, contractors of the village of Brockport, entered into a written contract with John R. Strachen to construct the carpenter work of said building for the sum of $6,000; payments to be made as the money should be received by Strachen from Gutmann on his contract, and on the architect’s certificate. The drawings and specifications of the original contract w„ere referred to as a part of this. The job was to be finished at the same time. On the same day Frank P. Crouch executed a bond to Strachen for $6,000, the condition of which was that, if Wadsworth & Son should in all things perform their contract, the agreement should be void; otherwise in full force. The plaintiffs in Ho. 1 brought the action to recover a balance alleged to be due of $1,650 on the $6,000 contract, over and above all payments. It is alleged this claim was assigned to the plaintiffs by the Wadsworths. It is also alleged that on the 27th day of June, 1887, the Wadsworths made and delivered to the plaintiffs an order of which the following is a copy: “Rochester, H. Y., June 27th, Í887. Max L. Gutmann: Please pay to G. W. & F. P. Crouch sixteen hundred and fifty (1,650.00) dollars, and charge the same to our contract. [Signed] Jqhn Wadsworth & Son.” This was accepted in the following form: “Aug. 6,11:30 A. h. This order is accepted, payable out of any balance which may be due Messrs. Wadsworth & Son when the building is completed, to the extent of such unpaid balance, and no [276]*276more, and on the architect’s certificate only. [Signed] Max L. Gutmann. ” It is alleged that the order or paper as accepted was assigned to the plaintiffs. The defendant denied performance by Strachen and Wadsworth & Son, and asked a dismissal of the complaint. In No. 2 the plaintiff seeks to recover the amount of the bond, upon the claim of non-performance by Wadsworth & Son. The complaint alleges an assignment by Strachen to the plaintiff, and further states Wadsworth & Son did not perform, and that thus Strachen was prevented from performing. The answer alleges substantial performance, and asks a dismissal of the complaint. Both cases were referred to the same referee. In No. 1 the referee reported $633.67 for the plaintiffs. In No. 2 the complaint was dismissed. Judgment was entered by the successful party upon each report, and the defendant in No. 1 and plaintiff in No. 2 appealed to this court.

As the rights of all the parties depend upon the same questions, the cases were practically tried as one action, with a stipulation that the testimony in one case, so far as applicable, should apply to the other. In No. 1 the referee finds the contracts, and that on the 5th day of August, 1887, Strachen served written notice to make no further payments to Wadsworth & Son. That the Wadsworths commenced work on the building about the 1st of November, 1886, and on the 1st day of February, 1887, stopped work at the instance of the architect, and also on account of inclement weather. At this time the roof was on the building. "Work was after that resumed, and continued until the 30th day of July, 1887, when it ceased. A strike in April caused a delay of two weeks, and there were some other delays. That Strachen substantially performed the work on his part, and that he was paid, from time to time, $8,500.45, which, with the $6,000 contract, and the amount allowed for deductions, equaled the contract price, $16,500. The referee also finds that the Wadsworths substantially performed their contract, except in certain particulars, in which they were guilty of no willful or intentional violation of their contract; that the work not performed by the Wadsworths was of the value of $145. He also found that, by arrangement, the defendant furnished the Wadsworths hardware to the amount of $293.64; also tile of the value of $140.50, and $14 for iron pipe; also $12 for iron transom guards. That they performed extra work to the amount of $260. That the walls of the building settled, affecting the carpenter work, for which the Wadsworths were not to blame, it being due to the settling of the walls, and shrinkage. That the materials furnished by the Wadsworths were in accordance with the terms of their contract, except in the case of shelving and closets and maple flooring for the halls, part of which was second-rate material. That the Wadsworths stopped work on the building in July, 1887, and did nothing further upon it. That at that time there were defects in the bath-room, on the hard wood floors, in piecing casings on windows in the rear of the building, in defective hand-rails of the front stairs, moulding in some portions of the building not being planed smooth, and improper painting of the building in the front part. That it would cost, to remedy all defects, $203, which was deducted from the contract price. That, after the Wadsworths stopped work, the defendant had the keys, and took possession of the building on the 21st day of September, 1887, and has since occupied the same. That after April 1,1887, Strachen and the Wadsworths continued work, with the knowledge and consent of the defendant, and that the architect visited and inspected the same, and made various estimates for payment on the contract. That the defendant made payments up to the 22d day of June. That" the payments actually made to the Wadsworths were $2,369. That, in addition thereto, the defendant accepted an order for $500. That there should be added to the contract price $266 for extra work. That the deductions to which the defendant was entitled were $293.64 for hardware; $148.50 for tiling; $26 for iron pipe; $439.29, amount of J. B. Pike’s bill; $148, an omission by consent of defend[277]*277ant; $203, cost of repairing defects not repaired by Pike,—amounting to $1,258.43, which, added to the amount of payments, made $4,369, leaving a balance due on the contract and extras of $633.67. The order of June 27th was given to the plaintiff for lumber which was furnished to the Wadsworths, and used in the erection of the building. The plaintiff had requested the architect for a certificate, but he had refused to give one, and that such refusal was unjust and unreasonable. That the plaintiffs or the Wadsworths did not receive notice to complete the job. That Strachen and the architect had a settlement on the 8th day of August, 1887. That on this settlement the $6,000 was deducted from the contract price of $16,500, and also $1,499.55 for damages under the contract, which included $1,300 for lost time. That the assignment to the plaintiffs was for a valuable consideration. The findings in No. 2 were substantially the same as those in No. 1, with the additional finding that no consideration was paid to Strachen for the assignment of said bond. It was stipulated that the referee might inspect the building, which he did.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
10 N.Y.S. 275, 32 N.Y. St. Rep. 254, 57 Hun 586, 1890 N.Y. Misc. LEXIS 2076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crouch-v-gutmann-nysupct-1890.