Croton Falls Construction Co. v. City of New York

168 A.D. 261, 154 N.Y.S. 76, 1915 N.Y. App. Div. LEXIS 8966
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 18, 1915
StatusPublished
Cited by2 cases

This text of 168 A.D. 261 (Croton Falls Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Croton Falls Construction Co. v. City of New York, 168 A.D. 261, 154 N.Y.S. 76, 1915 N.Y. App. Div. LEXIS 8966 (N.Y. Ct. App. 1915).

Opinion

Dowling, J.:

This action was brought to recover the sum of $122,325.80, the amount claimed to be due under a contract for the construction of the Croton Falls reservoir. Plaintiff has recovered judgment in the sum of $35,388.95, and appeals from so much thereof as fails to give him the amount of certain claims aggregating $270,968.86, with interest. The judgment was entered by direction of the court, which dismissed the additional claims referred to, and refused to submit the issues involved in such claims to the j ury. The Croton Falls reservoir, which is one of the largest in New York city’s Croton water system, was initiated under the original aqueduct commission, and after the abolition thereof was completed by the department of water, supply, gas and electricity of the city of New York, in which the powers of the former commission were vested by chapter 220 of the Laws of 1910 (amdg. Greater New York charter [Laws of 1901, chap. 166], § 518). The contract was one for a unit price, as distinguished from a lump sum. The questions in controversy arise over the action of the city’s engineer in claiming that certain units of the work should not be paid for at all, and that certain other units should he paid for at a less price per unit than that claimed by the contractor. The final estimate of the city’s engineer fixes the aggregate contract price at $1,319,156.99. Plaintiff’s contention is that the correct amount is $1,590,125.85. Of the amount shown by the final estimate, $31,697.29 had been withheld by the comptroller of the city of New York, and it is that amount, with interest, for which the plaintiff has recovered judgment, and from which judgment the city does not appeal. The balance, being the amount now in controversy, is made up of eight items. We shall state [264]*264briefly the salient facts as to such of these claims as we think require our consideration:

(1) Plaintiff claims that it placed class A monolithic concrete around the reinforcing rods in the main dam, above elevation 280.8, under due order from the engineer, and that it should have been allowed and paid therefor at the contract price of $7 per cubic yard (the price for class A concrete), instead of the amount finally allowed by the engineer, $2.65 per cubic yard (the contract price for cyclopean masonry). The difference in the contract price, based upon these two units, is $58,043.79.

The method of construction of the portion of the dam in question is as follows: Its faces are made of concrete blocks so placed in courses as to overlap or bond, and in every second course parts of the blocks extend inside the face and towards the center of the dam, being called “headers,” and forming a bond between the face and the interior mass. Every third block in every second course is a “header,” and the face blocks not used as headers are called “ stretchers.” Inside of these block faces the dam consists, for the greater part, of cyclopean stone masonry. This masonry is composed of very large quarry block of irregular sizes and shapes, weighing up to six tons, the requirement being that they “ shall be sound, clean, strong and durable,” and “as large as can be economically quarried, transported and handled.” This construction was to be used under the specifications for substantially the whole of the main part of the dam except the faces. The method of laying these stones is specified in detail under section 85 of the contract, under which the faces of the dam were to be built somewhat in advance of the interior. Wet concrete was to be deposited in sufficient quantities in low places in the work, and before it had attained its initial set large stones were to be lowered into it as close together as possible. The stones were then to be joggled with a bar so as to settle them well into the concrete, and the concrete was to be worked with suitable tools so as to force the escape of entrained air or water, and insure the filling with concrete and mortar of all spaces between and beneath the large stones. If smaller stones could be imbedded between the large stones, and between those stones and the face of the [265]*265dam, this was to be done, the object being to obtain a monolithic mass of stone and concrete, with as large a proportion of stone as it was possible to secure, and a wall as nearly impervious to water as it was possible to make it. Up to level 280.8, the entire space was built up in this manner with cyclopean stones. So close were they placed to the facing blocks that in some cases they were only two inches ppart, while the average distance was six inches. One of the essential features of the construction was to insure bonding or overlapping of the large stones.

In the winter of 1908-1909, Mr. Cook, the acting chief engineer, stated to the contractor that bad cracks had developed in the Cross River dam, and that the engineers were considering reinforcing the dam in question to prevent a similar recurrence. To do this it was decided to place two rows of rods inside the facing blocks above elevation 280.8, in the placing of which great care was required to be used by the engineer to lay the bars level and to insure a continuous straight line. The ends of the rods were forged into hooks which were interlocked to form a continuous, taut and level line along the entire length of the dam. Wedges were driven where necessary to keep this line taut, as it had to be perfect in alignment. When the rods were placed, they were surrounded with concrete. Before this reinforcing had begun the contractor claimed that it was physically impossible to place the bars in cyclopean masonry, and that the plan must be modified before the work reached the elevation in question, where the reinforcing was to begin, otherwise the contractor would positively stop work. It claimed, as one reason .for the inability to place reinforcing in cyclopean masonry, the irregularity of the large stones projecting at different angles and at different heights and the variation of shapes of the stones, which made the maintenance of perfect alignment through such construction impossible. The engineer, Cook, changed the classification and furnished a drawing showing what is described as “Limit for classification,” at a distance of one foot from the headers. The contractor claimed that the distance from the header at which the classification as class A concrete should cease, and that of cyclopean masonry begin, should be three feet, but the engineer said he would not classify beyond one foot, which was, he testifies, [266]*266simply “ to be the classification line between those two masonries or classes of masonry that was being mooted, ” and as he further says, That is what led up to the establishment of that line.” The controversy about this line lasted several days, and it sufficiently appears that the contractor was unwilling to proceed beyond the point in question and do any reinforcing until the exact nature of the classification of the part of the work in which the rods were to be inserted had been determined, so that his compensation might be fixed at the proper unit price. There is a question as to whether Cook made a final classification or only a tentative one. Plaintiff’s witnesses swear positively that the classification was a final and definite one, in reliance upon which they proceeded with their work. The engineer says that the words “limit for classification” upon the plan would indicate to the engineer that there were two classes of material to go in the dam other than the facing block, but would not indicate the kind of material that was to go in there. On cross-examination he testified that he said he

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
District Nursing Ass'n v. Koerner
159 N.Y.S. 1109 (Appellate Division of the Supreme Court of New York, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
168 A.D. 261, 154 N.Y.S. 76, 1915 N.Y. App. Div. LEXIS 8966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/croton-falls-construction-co-v-city-of-new-york-nyappdiv-1915.