Croton Falls Construction Co. v. City of New York

168 A.D. 261, 154 N.Y.S. 76, 1915 N.Y. App. Div. LEXIS 8966
Appellate Division of the Supreme Court of the State of New York·Decided June 18, 1915·Published·Cited by 2 cases

Opinion

Dowling, J.:

This action was brought to recover the sum of $122,325.80, the amount claimed to be due under a contract for the construction of the Croton Falls reservoir. Plaintiff has recovered judgment in the sum of $35,388.95, and appeals from so much thereof as fails to give him the amount of certain claims aggregating $270,968.86, with interest. The judgment was entered by direction of the court, which dismissed the additional claims referred to, and refused to submit the issues involved in such claims to the j ury. The Croton Falls reservoir, which is one of the largest in New York city’s Croton water system, was initiated under the original aqueduct commission, and after the abolition thereof was completed by the department of water, supply, gas and electricity of the city of New York, in which the powers of the former commission were vested by chapter 220 of the Laws of 1910 (amdg. Greater New York charter [Laws of 1901, chap. 166], § 518). The contract was one for a unit price, as distinguished from a lump sum. The questions in controversy arise over the action of the city’s engineer in claiming that certain units of the work should not be paid for at all, and that certain other units should he paid for at a less price per unit than that claimed by the contractor. The final estimate of the city’s engineer fixes the aggregate contract price at $1,319,156.99. Plaintiff’s contention is that the correct amount is $1,590,125.85. Of the amount shown by the final estimate, $31,697.29 had been withheld by the comptroller of the city of New York, and it is that amount, with interest, for which the plaintiff has recovered judgment, and from which judgment the city does not appeal. The balance, being the amount now in controversy, is made up of eight items. We shall state [264] briefly the salient facts as to such of these claims as we think require our consideration:

(1) Plaintiff claims that it placed class A monolithic concrete around the reinforcing rods in the main dam, above elevation 280.8, under due order from the engineer, and that it should have been allowed and paid therefor at the contract price of $7 per cubic yard (the price for class A concrete), instead of the amount finally allowed by the engineer, $2.65 per cubic yard (the contract price for cyclopean masonry). The difference in the contract price, based upon these two units, is $58,043.79.

The method of construction of the portion of the dam in question is as follows: Its faces are made of concrete blocks so placed in courses as to overlap or bond, and in every second course parts of the blocks extend inside the face and towards the center of the dam, being called “headers,” and forming a bond between the face and the interior mass. Every third block in every second course is a “header,” and the face blocks not used as headers are called “ stretchers.” Inside of these block faces the dam consists, for the greater part, of cyclopean stone masonry. This masonry is composed of very large quarry block of irregular sizes and shapes, weighing up to six tons, the requirement being that they “ shall be sound, clean, strong and durable,” and “as large as can be economically quarried, transported and handled.” This construction was to be used under the specifications for substantially the whole of the main part of the dam except the faces. The method of laying these stones is specified in detail under section 85 of the contract, under which the faces of the dam were to be built somewhat in advance of the interior. Wet concrete was to be deposited in sufficient quantities in low places in the work, and before it had attained its initial set large stones were to be lowered into it as close together as possible. The stones were then to be joggled with a bar so as to settle them well into the concrete, and the concrete was to be worked with suitable tools so as to force the escape of entrained air or water, and insure the filling with concrete and mortar of all spaces between and beneath the large stones. If smaller stones could be imbedded between the large stones, and between those stones and the face of the [265] dam, this was to be done, the object being to obtain a monolithic mass of stone and concrete, with as large a proportion of stone as it was possible to secure, and a wall as nearly impervious to water as it was possible to make it. Up to level 280.8, the entire space was built up in this manner with cyclopean stones. So close were they placed to the facing blocks that in some cases they were only two inches ppart, while the average distance was six inches. One of the essential features of the construction was to insure bonding or overlapping of the large stones.

Free access — add to your briefcase to read the full text and ask questions with AI

Croton Falls Construction Co. v. City of New York, 168 A.D. 261, 154 N.Y.S. 76, 1915 N.Y. App. Div. LEXIS 8966 (N.Y. Ct. App. 1915).

168 A.D. 261 (Croton Falls Construction Co. v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
District Nursing Ass'n v. Koerner
159 N.Y.S. 1109 (Appellate Division of the Supreme Court of New York, 1916)