Cross Creek Multifamily, LLC v. ICI Construction, Inc.

District Court, S.D. Mississippi·Decided October 8, 2020·No. 2:18-cv-00083·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI EASTERN DIVISION

CROSS CREEK MULTIFAMILY, LLC PLAINTIFF

v. CIVIL ACTION NO. 2:18-cv-83-KS-MTP

ICI CONSTRUCTION, INC. and HARTFORD FIRE INSURANCE COMPANY DEFENDANTS

ORDER

THIS MATTER is before the Court on Plaintiff’s Motion to Strike [487]. Having considered the parties’ submissions, the record, and the applicable law, the Court finds that the Motion should be granted. BACKGROUND

On May 10, 2018, Plaintiff Cross Creek Multifamily, LLC filed this action against Defendants ICI Constructions, Inc. (“ICI”) and its surety, Hartford Fire Insurance Company, asserting multiple claims arising from alleged construction defects in an apartment complex constructed by ICI and owned by Plaintiff. Thereafter, ICI asserted third-party claims against multiple subcontractors that performed work on the apartment complex, including Perren Masonry, LLC; All American Builders, Inc.; Burris Contracting, LLC; RJM McQueen Contracting, Inc.; Warner Construction Co. of MS, LLC; and Kimbel Mechanical Systems, Inc. ICI asserts that the subcontractors are responsible for the alleged defects. On October 24, 2018, the Court entered a Case Management Order [39], which, inter alia, set a May 1, 2019 deadline for Plaintiff’s expert designations, a May 31, 2019 deadline for Defendants’ expert designations, and an August 15, 2019 discovery deadline. On April 4, 2019, Plaintiff filed a Motion for Extensions [128]. The Court granted the Motion [128], extending Plaintiff’s expert designation deadline to May 31, 2019, Defendants’ expert designation deadline to July 1, 2019, and the discovery deadline to September 2, 2019. See Order [130]. On June 26, 2019, Defendant ICI filed a Motion for Extensions [197], and the Court extended the discovery deadline to September 16, 2019. See Order [199]. On August 16, 2019, after more than nine months of discovery, Plaintiff filed a Motion to

Amend [253], seeking to add as a defendant Pucciano & Associates, P.C., the architectural firm for the apartment complex. On September 23, 2019, the Court granted the Motion [253]. See Order [310]. After Pucciano was added as a defendant, the Court set a January 17, 2020 deadline for Plaintiff’s expert designations, a February 28, 2020 deadline for Defendants’ expert designations, and a May 1, 2020 discovery deadline. See Amended Case Management Order [322]; Order [349]. On June 12, 2020—more than a month after the discovery deadline—Plaintiff served its Eleventh Supplemental Disclosures, and on June 17, 2020, Plaintiff served its Third Supplemental Designation of Expert Witnesses. See Notices [416] [450]; Disclosures [455-1];

Designation [455-2]. These disclosures concerned what was said to be newly discovered damage to the complex, including damage caused by water intrusion into the interior of apartment units. Defendant Perren Masonry filed a Motion to Strike [455], arguing that Plaintiff’s Eleventh Supplemental Disclosures and Third Supplemental Designation of Expert Witnesses should be stricken as untimely. On July 16, 2020, the Court granted the Motion [455], striking Plaintiff’s latest disclosures. See Order [478]. On August 24, 2020—nearly four months after the discovery deadline—Defendant ICI served its Third Supplemental Disclosures [486], which included an August 19, 2020 supplemental report from its expert Robert Luke. In his supplemental report, Luke describes the newly discovered damage to the complex and opines that Plaintiff’s failure to make repairs has contributed to the continued deterioration of the complex. On September 14, 2020, Plaintiff filed its Motion to Strike [487] arguing that Luke’s supplemental report should be stricken for the same reasons the Court struck Plaintiff’s supplemental disclosures. ANALYSIS

“A party must make [expert] disclosures at the times and in the sequence that the court orders.” Fed. R. Civ. P. 26(a)(2)(D). Local Rule 26 provides that a “party must make full and complete disclosures as required by Fed. R. Civ. P. 26(a) and L.U. Civ. R. 26(a)(2)(D) no later than the time specified in the case management order.” L.U. Civ. R. 26(a)(2). Defendant ICI’s expert designation deadline ran on February 28, 2020. See Order [349]. Parties, however, must supplement their disclosures when required under Fed. R. Civ. P. 26(e). Pursuant to the Local Rules, “[a] party is under a duty to supplement disclosures at appropriate intervals under Fed. R. Civ. P. 26(e) and in no event later that the discovery deadline

established by the case management order.” L.U. Civ. R. 26(a)(5). “If a party fails to provide information or identify a witness as required by Rule 26(a) or (e), the party is not allowed to use that information or witness to supply evidence on a motion, at a hearing, or at trial, unless the failure was substantially justified or is harmless.” Fed. R. Civ. P. 37(c)(1). To determine whether to exclude evidence which was not properly or timely disclosed, the Court considers the following factors: (1) the explanation for the failure to disclose the evidence; (2) the importance of the evidence; (3) potential prejudice in allowing the evidence; and (4) the availability of a continuance to cure such prejudice. See Sierra Club, Lone Star Chapter v. Cedar Point Oil Co. Inc., 73 F.3d 546, 572 (5th Cir. 1996); City of Hattiesburg v. Hercules, Inc., 2016 WL 1090610, at *1 (S.D. Miss. Mar. 18, 2016) (citing Hamburger v. State Farm Mut. Auto. Ins. Co., 361 F.3d 875, 883 (5th Cir. 2004)). The Court will first address ICI’s explanation for its failure to timely supplement its expert designation. ICI asserts that it first learned of continued deterioration at the complex when Plaintiff served its Eleventh Supplemental Disclosures on June 12, 2020. On July 6, 2020,

ICI’s expert inspected the complex and, thereafter, drafted his supplemental report. ICI argues that its failure to timely supplement its expert designation is explained by Plaintiff’s failure to timely disclose the deterioration. ICI, however, admits that continued deterioration is not a “new opinion.” See [489] at 6. ICI points out the during Luke’s deposition taken April 23, 2020, he agreed with Plaintiff’s expert who opined that the complex would continue to deteriorate unless repairs were made. Id. at 3. ICI was aware of alleged water intrusion throughout this litigation. This action has been pending since May 10, 2018, and ICI has been aware that the complex would continue to deteriorate if repairs were not made.

Free access — add to your briefcase to read the full text and ask questions with AI

Cross Creek Multifamily, LLC v. ICI Construction, Inc., (S.D. Miss. 2020).

Cross Creek Multifamily, LLC v. ICI Construction, Inc. (Cross Creek Multifamily, LLC v. ICI Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related