Cross Creek Multifamily, LLC v. ICI Construction, Inc.

CourtDistrict Court, S.D. Mississippi
DecidedJuly 16, 2020
Docket2:18-cv-00083
StatusUnknown

This text of Cross Creek Multifamily, LLC v. ICI Construction, Inc. (Cross Creek Multifamily, LLC v. ICI Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross Creek Multifamily, LLC v. ICI Construction, Inc., (S.D. Miss. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI EASTERN DIVISION

CROSS CREEK MULTIFAMILY, LLC PLAINTIFF

v. CIVIL ACTION NO. 2:18-cv-83-KS-MTP

ICI CONSTRUCTION, INC. and HARTFORD FIRE INSURANCE COMPANY DEFENDANTS

ORDER

THIS MATTER is before the Court on the Motion to Strike [455] filed by Third-Party Defendant Perren Masonry, LLC. Having considered the parties’ submissions, the record, and the applicable law, the Court finds that the Motion should be granted. BACKGROUND

On May 10, 2018, Plaintiff Cross Creek Multifamily, LLC filed this action against Defendants ICI Constructions, Inc. and its surety, Hartford Fire Insurance Company, asserting multiple claims arising from alleged construction defects in an apartment complex constructed by ICI Construction and owned by Plaintiff. Thereafter, ICI Construction asserted third-party claims against multiple subcontractors that performed work on the apartment complex, including Perren Masonry, LLC, All American Builders, Inc., Burris Contracting, LLC, RJM McQueen Contracting, Inc., Warner Construction Co. of MS, LLC, and Kimbel Mechanical Systems, Inc. ICI Construction asserts that the subcontractors are responsible for the alleged defects. On October 24, 2018, the Court entered a Case Management Order [39], which, inter alia, set a May 1, 2019 deadline for Plaintiff’s expert designations and set an August 15, 2019 discovery deadline. On April 4, 2019, Plaintiff filed a Motion for Extensions [128]. The Court granted the Motion [128] and extended Plaintiff’s expert designation deadline to May 31, 2019 and extended the discovery deadline to September 2, 2019. See Order [130]. On June 26, 2019, Defendant ICI Construction filed a Motion for Extensions [197], and the Court extended the discovery deadline to September 16, 2019. See Order [199]. On August 16, 2019, after more than nine months of discovery, Plaintiff filed a Motion to Amend [253], seeking to add as a defendant Pucciano & Associates, P.C., the architectural firm

for the apartment complex. On September 23, 2019, the Court granted the Motion [253]. On November 8, 2019, after Pucciano was added as a defendant, the Court conducted a scheduling conference and entered an Amended Case Management Order [322], which, inter alia, set a January 17, 2020 deadline for Plaintiff’s expert designations and set a May 1, 2020 discovery deadline. On June 12, 2020—more than a month after the discovery deadline—Plaintiff served its Eleventh Supplemental Disclosures. See Notice [416]; Disclosures [455-1]. Thereafter, on June 17, 2020, Plaintiff served its Third Supplemental Designation of Expert Witnesses. See Notice [450]; Designation [455-2]. Plaintiff’s supplemental disclosures included several photographs of

the apartment complex, and the expert’s supplemental report states as follows: “I have reviewed twenty-one photographs dated May 29, 2020 as well as additional photographs dated June 2 & 3, 2020. The photographs further illustrate failure of the masonry on the exterior walls of Cross Creek Village and that moisture has entered the building resulting in additional damage to the structures.” On June 23, 2020, Defendant Perren Masonry filed its Motion to Strike [155], arguing that Plaintiff’s Eleventh Supplemental Disclosures and Third Supplemental Designation of Expert Witnesses should be stricken as untimely. ANALYSIS

As part of the initial disclosures, a party must, without awaiting a discovery request, provide to the other parties a copy or description of information it may use to support its claims or defenses. See Fed. R. Civ. P 26(a)(1)(A)(ii). In this case, Plaintiff was required to serve its initial disclosures by October 17, 2018. See Order [20]. Additionally, “[a] party must make [expert] disclosures at the times and in the sequence that the court orders.” Fed. R. Civ. P. 26(a)(2)(D). Local Rule 26 provides that a “party must make full and complete disclosures as required by Fed. R. Civ. P. 26(a) and L.U. Civ. R. 26(a)(2)(D) no later than the time specified in the case management order.” L.U. Civ. R. 26(a)(2). Plaintiff’s expert designation deadline ran on January 17, 2020. See Order [322]. Parties, however, must supplement their disclosures when required under Fed. R. Civ. P. 26(e). Pursuant to the Local Rules, “[a] party is under a duty to supplement disclosures at appropriate intervals under Fed. R. Civ. P. 26(e) and in no event later that the discovery deadline

established by the case management order.” L.U. Civ. R. 26(a)(5). “If a party fails to provide information or identify a witness as required by Rule 26(a) or (e), the party is not allowed to use that information or witness to supply evidence on a motion, at a hearing, or at trial, unless the failure was substantially justified or is harmless.” Fed. R. Civ. P. 37(c)(1). To determine whether to exclude evidence which was not properly or timely disclosed, the Court considers the following factors: (1) the explanation for the failure to disclose the evidence; (2) the importance of the evidence; (3) potential prejudice in allowing the evidence; and (4) the availability of a continuance to cure such prejudice. See Sierra Club, Lone Star Chapter v. Cedar Point Oil Co. Inc., 73 F.3d 546, 572 (5th Cir. 1996); City of Hattiesburg v. Hercules, Inc., 2016 WL 1090610, at *1 (S.D. Miss. Mar. 18, 2016) (citing Hamburger v. State Farm Mut. Auto. Ins. Co., 361 F.3d 875, 883 (5th Cir. 2004)). The Court will first address Plaintiff’s explanation for its failure to timely supplement its disclosures and expert designation. Plaintiff points out that on May 15, 2020, Perren Masonry filed a Motion [388], seeking to exclude the testimony of Fred Pucciano because, inter alia, he

was unable to locate a specific photograph depicting stair stepping cracks during his deposition. Thereafter, Plaintiff had its maintenance supervisor inspect the masonry work and document cracks. According to Plaintiff, the maintenance supervisor discovered that new cracks had developed since the prior inspection of the apartment complex.1 The maintenance supervisor photographed the cracks on May 29, 2020, and the photographs were produced on June 12, 2020. Plaintiff also asserts that on May 31, 2020, a tenant vacated apartment 9108, and during the inspection of the apartment, water damage was discovered. Thus, Plaintiff inspected other apartments and discovered additional water damage. Plaintiff photographed the water damage on June 2 and 3, 2020, and the photographs were produced on June 12, 2020.

Plaintiff, however, admits that “[t]hese are not new issues, but rather a continuation of the damage being suffered by Cross creek that has been placed at issue in this civil action from the beginning . . . .” See [473] at 5. Thus, Plaintiff was aware of alleged water intrusion, and its continuing nature, throughout this litigation, and the apartment complex has been within Plaintiff’s control at all times during this litigation. Plaintiff does not explain why it was unable to discover these issues prior to the discovery deadline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Cross Creek Multifamily, LLC v. ICI Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-creek-multifamily-llc-v-ici-construction-inc-mssd-2020.