Critical Path Construction v. Viking Structural CA4/3

CourtCalifornia Court of Appeal
DecidedJune 6, 2024
DocketG062439
StatusUnpublished

This text of Critical Path Construction v. Viking Structural CA4/3 (Critical Path Construction v. Viking Structural CA4/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Critical Path Construction v. Viking Structural CA4/3, (Cal. Ct. App. 2024).

Opinion

Filed 6/6/24 Critical Path Construction v. Viking Structural CA4/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

CRITICAL PATH CONSTRUCTION, LLC, G062439 Plaintiff, Cross-defendant and Appellant, (Super. Ct. No. 30-2021-01185121)

v. OPINION

VIKING STRUCTURAL, INC.,

Defendant, Cross-complainant and Respondent.

Appeal from a judgment of the Superior Court of Orange County, Nick A. Dourbetas, Judge. Affirmed. Flangas Law Group and Kimberly P. Stein for Plaintiff, Cross-defendant and Appellant. National Choice Lawyers and Koorosh K. Shahrokh for Defendant, Cross- complainant and Respondent. Critical Path Construction, LLC (Critical Path) sued Viking Structural, Inc. (Viking), alleging Viking breached the parties’ master services agreement (the MSA) whereby Viking was to provide subcontractor work on a construction project owned by Critical Path. Viking filed a cross-complaint against Critical Path, alleging a claim for breach of the MSA and a common count for goods and services rendered. Following a bench trial, judgment was entered in Viking’s favor on both the complaint and cross- complaint, awarding Viking damages in the amount of $47,725.84. We affirm. For the reasons we explain, we conclude (1) Critical Path forfeited the argument the trial court erred by admitting extrinsic evidence to interpret the MSA, and (2) the court did not err in awarding damages to Viking.

FACTUAL AND PROCEDURAL BACKGROUND I. THE PLEADINGS In its complaint, Critical Path alleged, on July 5, 2020, the parties entered the MSA whereby Viking agreed to provide structural steel work for a construction project in Los Angeles (the project). The complaint alleged, on July 15, 2020, Critical Path paid Viking a $24,500 retention payment, constituting 10 percent of the total estimated cost ($245,000) of Viking’s performance under the MSA. Viking thereafter was to invoice Critical Path for payment for completed work. The complaint further alleged, “[a]fter it became clear that [Viking] was not performing as required,” Critical Path provided formal notice to Viking, demanding it perform under the MSA; Viking requested additional time. On October 21, 2020, Critical Path called a meeting offering Viking an additional bonus if it completed the work by December 4, 2020. In mid-November, after concluding Viking was not performing under the MSA, Critical Path retained another subcontractor to perform services that had not been provided by Viking. Critical Path alleged it performed as required under the MSA,

2 except to the extent its performance was waived, excused, or prevented by Viking’s alleged breach of the MSA. Critical Path sought recovery of the retention fee it paid Viking and its attorney fees and costs. Viking filed a cross-complaint against Critical Path, asserting a claim for breach of the MSA and a common count for goods and services rendered. Viking alleged the parties agreed on dates for the completion and payment of goods and services under the MSA, but as a result of circumstances outside of the parties’ control, the parties agreed to extend the time for Viking to complete performance under the MSA to December 4, 2020. Viking further alleged it continued to perform its obligations under the MSA until Critical Path unilaterally and wrongfully terminated the MSA in mid- November 2020, and thereafter refused to pay Viking for goods it had purchased and services it had performed to date. Viking alleged it had performed under the MSA, except to the extent its performance was waived, excused, or prevented by Critical Path. Viking sought recovery of, inter alia, “[t]he reasonable value of the services performed and good[s] supplied” in the amount of $75,000. II. THE STATEMENT OF DECISION Following the bench trial, the trial court issued a minute order in which it found Viking had fulfilled its obligations under the MSA but Critical Path breached the MSA, causing Viking to sustain damages in the “stipulated amount of $47,725.84.” After Critical Path filed a request for a statement of decision, at the trial court’s direction, Viking prepared a proposed statement of decision and judgment, to which Critical Path filed objections. The trial court tacitly overruled Critical Path’s objections by adopting

3 Viking’s proposed statement of decision as its own, which set forth the court’s findings, summarized as follows. The MSA, which was entered into by Mehryar Michael Parsee, as owner 1 and president of Critical Path, and Tomick Sarkissian, on behalf of Viking, provided “time [was] of the essence” with regard to performance under that agreement. The MSA also provided, however, in the event Critical Path caused a delay, Viking would be entitled to a reasonable extension of time to perform. Shortly after Viking joined the project, Critical Path terminated project manager and/or general contractor Shiraz Construction and hired a replacement, causing a three- to four-week delay of the project. Another delay of one and one-half months was caused by problems with the shop drawings Viking received which had been prepared by Shiraz Construction. In addition, Viking was unable to install base plates provided under the MSA because the necessary concrete was not poured until after September 23, 2020. The court found Viking to have performed according to the MSA, having acted “swiftly to try and finish this job.” The court noted Sarkissian’s testimony Viking had hoped to secure more business with Critical Path beyond its part in the instant project, which was worth $8 million, and in that effort had given Critical Path “a little bit of a better deal.” The court also found Sarkissian “very responsive” in e-mail communications with Critical Path and others involved in the project. In terms of deadlines under the MSA, the court also noted “testimony about anticipated supply chain issues,” and found: “As a result, things didn’t really work out to be on time pursuant to the MSA. The parties went back and forth and Mr. Parsee gave an extension on the MSA [Parsee testified Viking’s scope of work under the MSA was originally to be finished by October 1, 2020 ] and the court finds that the parties acted in a fluid ma[nn]er when it came to dates on this MSA.” The court found on October 21, 1 Sarkissian testified he is a former co-owner and responsible managing officer of Viking.

4 2020, Critical Path and Parsee provided Viking an extension to complete Viking’s portion of the project, which the parties agree was until December 4, 2020. The court also noted evidence Viking’s portion of the project, including the installation of columns and base plates, was about 40 percent complete by mid-November 2020. The court found Critical Path breached the MSA by terminating the MSA before December 4, 2020. III. JUDGMENT IS ENTERED IN FAVOR OF VIKING Judgment was entered in favor Viking on both Critical Path’s complaint and Viking’s cross-complaint, awarding Viking damages in the amount of $47,727.84 against Critical Path on the cross-complaint. The judgment further provided Viking was to recover attorney fees and costs as allowed under the MSA after filing a memorandum of 2 costs. Critical Path timely filed a notice of appeal.

DISCUSSION I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christoff v. Union Pacific Railroad
36 Cal. Rptr. 3d 6 (California Court of Appeal, 2005)
Fladeboe v. American Isuzu Motors Inc.
58 Cal. Rptr. 3d 225 (California Court of Appeal, 2007)
Founding Members of Newport Beach Country Club v. Newport Beach Country Club, Inc.
135 Cal. Rptr. 2d 505 (California Court of Appeal, 2003)
Chicago Title Insurance v. AMZ Insurance Services, Inc.
188 Cal. App. 4th 401 (California Court of Appeal, 2010)
Ochoa v. Anaheim City School District
11 Cal. App. 5th 209 (California Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Critical Path Construction v. Viking Structural CA4/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/critical-path-construction-v-viking-structural-ca43-calctapp-2024.