Crispin Co. v. M/V MORNING PARK
This text of 578 F. Supp. 359 (Crispin Co. v. M/V MORNING PARK) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
MEMORANDUM AND ORDER
This case arises from the non-delivery of a cargo of steel pipe carried aboárd the vessel M/V MORNING PARK from the Port of Puerto Cabello, Venezuela, to Houston, Texas, in June, 1981. Plaintiff seeks damages, prejudgment interest, interest on its total judgment, costs of court, and attorney’s fees.
Defendants Nassau Navigation, Inc. and Valor Stevedoring have been dismissed from the case. Defendant Clover Trading Co. is presently in bankruptcy in Denmark and has not appeared or answered. Defendant Cho Yang Shipping Co., Ltd., owner of the M/V MORNING PARK, has appeared and denied Plaintiff’s claim. 1 All relevant facts have been stipulated by the Plaintiff and Defendant Cho Yang, the latter admitting liability for the non-delivery of eight bundles of Plaintiff’s cargo. Jurisdiction of this Court is proper pursuant to 28 U.S.C. § 1333.
The only contested issue of law is that of damages under § 1304(5) of the Carriage of Goods By Sea Act (“COGSA”), 46 U.S.C. § 1300 et seq. If the missing steel pipe 2 was shipped in “packages” as defined by COGSA then Defendants’ liability is limited to $4,000.00. If calculated by COGSA’s “customary freight unit” limitation, then Plaintiff’s damages total $7,492.00.
COGSA provides no definition of the term “package,” and the legislative history is unhelpful. Decisions on this issue fall into two general groups. Those courts following the Second Circuit’s approach adopt an expansive definition of the term “package” as “a class of cargo, irrespective of size, shape or weight, to which some packaging preparation for transportation has *360 been made which facilitates handling, but which does not necessarily conceal or completely enclose the goods.” Aluminios Pozuelo Ltd. v. S.S. NAVIGATOR, Et Al, 407 F.2d 152, 155 (2nd Cir.1968). Other courts have adopted the Ninth Circuit’s narrower view that a cargo is a “package” under COGSA only when the preparation of the goods for shipment conceals their identity. Hartford Fire Insurance Co. v. Pacific Far East Line, Inc., 491 F.2d 960, 964 (9th Cir.1974), cert. denied, 419 U.S. 873, 95 S.Ct. 134, 42 L.Ed.2d 112 (1974). While the Fifth Circuit apparently has not conclusively defined “package” in this context, it has stated clearly that cargo does not have to be fully enclosed to qualify as a package, Calmaquip Engineering West Hemisphere Corporation v. West Coast Carriers, Ltd., 650 F.2d 633, 639 (5th Cir.1981), and has identified itself more closely with the Second Circuit’s approach. Allstate Insurance Company v. Inversiones Navieras Imparca, C.A., 646 F.2d 169, 172 (5th Cir.1981); Croft & Scully Co. v. M/V Skulptor Vuchetich, 664 F.2d 1277, 1281 (5th Cir.1982).
Black’s defines “package” as
“[a] bundle put up for transportation or commercial handling; a thing in form to become, as such, an article of merchandise or delivery from hand to hand. A parcel is a small package; ‘parcel’ being the diminutive of ‘package.’ Each of the words denotes a thing in form suitable for transportation or handling, or sale from hand to hand. As ordinarily understood in the commercial world, it means a shipping package.”
Black’s Law Dictionary 998 (5th ed. 1979). It is stipulated that the bundling of the pipes into lifts “facilitated the handling and transportation of the pipe.” Joint Stipulation of Facts No. 11. The documentation used in the transaction on balance indicates that each lift of pipe constituted a package. 3 Although the parties’ characterization of the cargo cannot override the statutory definition, Brown & Root, Inc. v. M/V PEISANDER, 648 F.2d 415, 420 (5th Cir.1981), see also Gebr. Bellmer KG. v. Terminal Services Houston, Inc., 711 F.2d 622, 624 (5th Cir.1983), the Fifth Circuit permits an examination of documents which might indicate the intent and mutual understanding of the parties as to the meaning of the term “package.” Croft & Scully Co., supra, 664 F.2d at 1281. 4 Finally, the Court notes that the bundled pipe has the common sense, visual appearance of a package, and concludes that each five-piece lift constituted a “package” as that term is employed in § 1304(5) of COGSA. 5
It is therefore ORDERED that Plaintiff’s damages total $4,000, plus costs of court and attorney’s fees of $2,976.57 pursuant to TEX.REV.CIV.STAT.ANN. art. 2226 (Vernon Supp.1982-83). Plaintiff is entitled to prejudgment interest of 9%, said rate based on TEX.REV.CIV.STAT.ANN. art. 5069-1.05 (Vernon Supp.1982-83) and accruing from the date of delivery of the pipe, June 22, 1981. Postjudgment interest shall accrue at the applicable legal rate.
ORDER
Attorney’s fees were improvidently awarded in the Final Judgment previously entered in this admiralty suit based upon the Carriage of Goods by Sea Act (COG-SA), 46 U.S.C. § 1300 et seq. See Noritake Co., Inc. v. M/V HELLENIC CHAMPION, 627 F.2d 724, 730 (5th Cir.1980); Platoro Ltd., Inc. v. Unidentified Remains, Etc., 695 F.2d 893, 905-06 (5th Cir.1983), cert. *361 denied, — U.S. —, 104 S.Ct. 77, 78 L.Ed.2d 89; Brazosport Towing Co., Inc. v. Donjon Marine Co., Inc., 556 F.Supp. 640, 644 S.D.Tex. 1983). It is therefore ORDERED that the motion to amend judgment to exclude the award of attorney’s fees is hereby GRANTED.
Plaintiff’s motion to dismiss with prejudice and for relief from judgment, pursuant to Rules 41(a)(2) and 60(b)(5), FED.R. CIY.P. is hereby DENIED.
. The Marine Office of America Corporation has become subrogated to the named Plaintiff’s rights and is now the real party in interest.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
578 F. Supp. 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crispin-co-v-mv-morning-park-txsd-1984.