Crest Plumbing & Heating Co. v. DiLoreto

531 A.2d 177, 12 Conn. App. 468, 1987 Conn. App. LEXIS 1086
CourtConnecticut Appellate Court
DecidedSeptember 22, 1987
Docket3101; 3102; 3103
StatusPublished
Cited by45 cases

This text of 531 A.2d 177 (Crest Plumbing & Heating Co. v. DiLoreto) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crest Plumbing & Heating Co. v. DiLoreto, 531 A.2d 177, 12 Conn. App. 468, 1987 Conn. App. LEXIS 1086 (Colo. Ct. App. 1987).

Opinion

Spallone, J.

This is a consolidated appeal involving three separate contract actions against a common defendant.1 The trial court rendered judgment for the plaintiff in each of the actions, and the defendant appealed from each of the judgments. We find error in the second case and no error in the first and third cases.

The following facts are not in dispute and are common to all three appeals. The defendant is a partner in a general partnership (D & T Construction Company) which was, at the time of the matter in question, engaged as a general contractor. The plaintiff in the first case, Crest Plumbing and Heating Company [470]*470(Crest), is a plumbing contractor. The plaintiff in the second case, Mac’s Car City, Inc. (Mac’s), is a new and used car dealership in Berlin, Connecticut. The plaintiff in the third case, Howard Asal Construction Company, Inc. (Asal), is a paving contractor.

Pursuant to a written building construction contract dated October 5, 1978, the defendant agreed to construct a building to house Mac’s dealership. Thereafter, the defendant entered into agreements with Crest and Asal to perform subcontracting work on that project. Disputes arose between the defendant and each of the plaintiffs which ultimately resulted in each plaintiff filing a lawsuit against the defendant. The defendant filed an answer and counterclaim in each of the three lawsuits. All three cases were consolidated and tried together to the court. After trial, the court, Shaughnessy, J., rendered judgment for the plaintiff on both the complaint and the counterclaim in each case, from which judgments the defendant has filed three appeals. The appeals were consolidated and this opinion will serve all three.

Appeal No. 3101-Crest Plumbing & Heating Co. v. DiLoreto

Pursuant to a written contract between the defendant and Crest dated November 3,1978, Crest agreed to perform plumbing work on the project. Upon completing the required performance, the defendant was indebted to Crest in the amount of $2090, which he refused to pay. Accordingly, Crest commenced a contract action against the defendant to recover the unpaid balance. As a result of the suit brought by Mac’s against the defendant, the defendant counterclaimed against Crest seeking damages for alleged unfinished and improper work. After a trial, the trial court rendered judgment for Crest on the complaint and on the defend[471]*471ant’s counterclaim. The court awarded Crest the claimed $2090, plus interest equal to $752.40, for a total judgment of $2842.40.

The defendant has appealed from the judgment, claiming that the trial court erred in concluding that Crest performed its agreement with the defendant. The defendant asserts that the court’s conclusion was inconsistent with its conclusion in Mac’s Car City, Inc. v. DiLoreto, where the court found that the plumbing work was not done in accordance with the agreement between Mac’s and the defendant.

We find no merit in this contention. The defendant has failed to establish that Crest’s agreement with the defendant was identical in relevant part with the defendant’s agreement with Mac’s. Without such proof, we cannot find that the court’s conclusions in the two cases were inconsistent. See also Ryan v. Mill River Country Club, Inc., 8 Conn. App. 1, 5-6, 510 A.2d 462 (1986). The court’s conclusion that the plaintiff properly performed its obligation under the contract is supported by the evidence and is not clearly erroneous. Practice Book § 4061; Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980); Buddenhagen v. Lugue, 10 Conn. App. 41, 45, 521 A.2d 221 (1987). Consequently, we find no error.

Appeal No. 3102-Mac’s Car City, Inc. v. DiLoreto

This appeal involves a suit for breach of a contract for the construction of premises to be used by Mac’s as an automobile dealership. The contract was prepared by the defendant and essentially provided that the defendant would construct, ready to use, a building and parking facilities to accommodate a functioning automobile dealership. The construction was to be completed within 100 days and called for total payment of [472]*472$256,000. There were two approved change orders, bringing the total due for the job to $263,380. Up to the time of the defendant’s default, the defendant had been paid $236,400, plus $4000 to a subcontractor for a total of $240,400.

Construction delays eventually resulted in the defendant’s default under the contract. Consequently, Mac’s completed the construction on its own. On June 5,1980, Mac’s commenced a breach of contract action against the defendant, alleging incomplete and improper workmanship. The defendant counterclaimed for the balance due him under the contract.

After a trial, the court rendered judgment in favor of Mac’s on its complaint and on the defendant’s counterclaim. The court awarded cost of completion damages in the amount of $46,469.33, inclusive of attorney’s fees equal to $6750, plus interest from July 1,1979 to March 1, 1984, for a total award of $63,817.88.

The defendant has appealed and has claimed that the trial court erred (1) in determining the plaintiffs damages, (2) in awarding the plaintiff prejudgment interest, (3) in rejecting the defendant’s counterclaim for the cost of extra work performed, (4) in refusing to admit into evidence the periodic progress reports of the construction mortgagee’s engineer, and (5) in failing to conclude that the measure of the defendant’s performance, and therefore his right to payment, was established by the approval of the periodic payment requisitions. We agree with the defendant’s fourth claim of error, that the court erred in refusing to admit the reports of the mortgagee’s project engineer as business records under General Statutes § 52-180.

The facts pertinent to this claim are as follows. American National Bank, the construction mortgagee, [473]*473entered into an agreement2 with Alfred Wilner, Inc., a corporation engaged in the business of construction management. Pursuant to this agreement, Alfred Wilner, Inc., periodically sent an engineer or architect employed by it to the job site to make an inspection of the work in progress in order to determine if the work conformed with the approved plans and specifications governing the defendant’s performance. During the course of construction, Alfred Wilner, Inc., sent six reports to the mortgagee bank. The bank, through the testimony of one of its officers, stated that it was in the bank’s general course of business to keep a record of the reports and that the reports were of field [474]*474inspections made by an engineer employed by the bank. When the defendant attempted to introduce the reports into evidence, the trial court sustained the plaintiff’s objection, holding that because the reports were not business records of the bank but were business records of someone else, they were inadmissible under General Statutes § 52-180.3 We disagree.

[475]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LM Ins. Corp. v. Connecticut Dismanteling, LLC
161 A.3d 562 (Connecticut Appellate Court, 2017)
WiFiLand, LLP v. Hudson
Connecticut Appellate Court, 2014
Pedroza v. Lomas Auto Mall, Inc.
716 F. Supp. 2d 1031 (D. New Mexico, 2010)
McMullen v. Kutz
985 A.2d 769 (Supreme Court of Pennsylvania, 2009)
MCDOWELL MOUNTAIN RANCH COMMUNITY ASS'N v. Simons
165 P.3d 667 (Court of Appeals of Arizona, 2007)
First Union National Bank v. Woermer
887 A.2d 893 (Connecticut Appellate Court, 2005)
Kurtz v. Kurtz
158 S.W.3d 12 (Court of Appeals of Texas, 2005)
Kurtz, Julia L. v. Kurtz, Ronald D.
Court of Appeals of Texas, 2004
Barber v. Hafez Hafez Company, No. Cv00-0340305 S (Apr. 9, 2002)
2002 Conn. Super. Ct. 4515 (Connecticut Superior Court, 2002)
Sender v. Sender, No. Fa94 0046243s (Mar. 9, 2001)
2001 Conn. Super. Ct. 3277 (Connecticut Superior Court, 2001)
Premier Capital, Inc. v. Grossman, No. Cv99 0334654 S (Nov. 22, 2000)
2000 Conn. Super. Ct. 14432 (Connecticut Superior Court, 2000)
Federal Deposit Insurance v. Carabetta
739 A.2d 311 (Connecticut Appellate Court, 1999)
State v. Hoffler
738 A.2d 1145 (Connecticut Appellate Court, 1999)
State v. Huckabee
738 A.2d 681 (Connecticut Appellate Court, 1999)
New England Savings Bank v. Bedford Realty Corp.
717 A.2d 713 (Supreme Court of Connecticut, 1998)
Connecticut Post Ltd. Parts. v. Allen, No. Cvnh 9610-7875 (Jan. 12, 1998)
1998 Conn. Super. Ct. 625 (Connecticut Superior Court, 1998)
Rizzo Pool Co. v. Del Grosso
689 A.2d 1097 (Supreme Court of Connecticut, 1997)
Smith v. Bridgeport Futures Initiative, Inc., No. 326697 (Aug. 13, 1996)
1996 Conn. Super. Ct. 5744 (Connecticut Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
531 A.2d 177, 12 Conn. App. 468, 1987 Conn. App. LEXIS 1086, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crest-plumbing-heating-co-v-diloreto-connappct-1987.